| Owner | Filings | Most Recent |
|---|---|---|
| NEW YORK UNIVERSITY | 88 | 07/08/2026 |
| BROSNA CONSTRUCTION GROUP | 1 | 03/22/2026 |
| NYU REAL ESTATE | 12 | 03/21/2026 |
| NYU OFFICE OF CONSTRUCTION MGMT | 4 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| LANGAN ENGINEERING | 1 | 07/28/2026 |
| STAGEBERG ARCHITECTURE PLLC | 10 | 03/11/2026 |
| BELMONT FREEMAN ARCHITECTS | 4 | 06/29/2021 |
| PAUL PERDEK, PROF. ENG. PLLC | 2 | 02/05/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| BURNHAM NATIONWIDE INC | 16 | 03/21/2026 |
| CONVERSANO ASSOCIATES, INC. | 12 | 03/21/2026 |
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PJP INSTALLERS INC | General Contractor | 9 | 07/08/2026 |
| HUDSON PLMBING & MCH, LLC | Plumbing | 7 | 07/08/2026 |
| BROSNA CONSTRUCTION CORPO | General Contractor | 6 | 07/08/2026 |
| JAN VARJAN | Electrical | 4 | 03/21/2026 |
| OMD ELECTRICAL CORP | Electrical | 3 | 03/22/2026 |
| MADZY, JOHN | Electrical | 1 | 03/21/2026 |
| JUMPER ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| HYDROKINETIC PLBG & HTG I | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| FENAGH, INC | 6942 | 10 | 03/11/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | HUDSON PLMBING & MCH, LLC | 04/09/2026 |
| DOB NOW | General Construction | Permit Issued | BROSNA CONSTRUCTION CORPO | 03/25/2026 |
| DOB NOW | Plumbing | Signed-off | HUDSON PLMBING & MCH, LLC | 03/27/2025 |
| DOB NOW | General Construction | Signed-off | BROSNA CONSTRUCTION CORPO | 03/24/2025 |
| DOB NOW | Plumbing | Signed-off | HYDROKINETIC PLBG & HTG I | 08/11/2023 |
| DOB NOW | General Construction | Signed-off | BROSNA CONSTRUCTION CORPO | 08/03/2023 |
| DOB NOW | Plumbing | Signed-off | HUDSON PLMBING & MCH, LLC | 05/03/2023 |
| DOB NOW | General Construction | Signed-off | BROSNA CONSTRUCTION CORPO | 04/25/2023 |
| DOB NOW | Plumbing | Signed-off | HUDSON PLMBING & MCH, LLC | 05/14/2021 |
| DOB NOW | Plumbing | Signed-off | HUDSON PLMBING & MCH, LLC | 05/14/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | PJP INSTALLERS INC | 04/16/2020 |
| DOB NOW | Supported Scaffold | Signed-off | PJP INSTALLERS INC | 04/16/2020 |
| DOB NOW | Supported Scaffold | Signed-off | PJP INSTALLERS INC | 02/10/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | PJP INSTALLERS INC | 01/17/2020 |
| DOB NOW | Supported Scaffold | Signed-off | PJP INSTALLERS INC | 02/05/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | PJP INSTALLERS INC | 01/16/2019 |
| BIS | OT | ISSUED | SKYLINE RESTORATION INC | 09/01/2021 |
| BIS | OT | ISSUED | SKYLINE RESTORATION INC | 05/06/2021 |
| BIS | OT | ISSUED | BROSNA CONSTRUCTION CORPO | 03/02/2021 |
| BIS | OT | ISSUED | BROSNA CONSTRUCTION CORPO | 10/26/2020 |
| BIS | OT | ISSUED | BROSNA CONSTRUCTION CORPO | 10/15/2020 |
| BIS | OT | ISSUED | BROSNA CONSTRUCTION CORPO | 10/14/2020 |
| BIS | OT | ISSUED | BROSNA CONSTRUCTION CORPO | 10/01/2020 |
| BIS | OT | ISSUED | SKYLINE RESTORATION INC | 02/28/2020 |
| BIS | OT | ISSUED | SKYLINE RESTORATION INC | 03/06/2019 |
| BIS | EQ | ISSUED | PJP INSTALLERS INC | 01/25/2019 |
| BIS | PL | ISSUED | MEGA PLBG CORP | 11/19/2015 |
| BIS | OT | ISSUED | VANGUARD CONSTRUCTION AND | 01/07/2015 |
| BIS | MH | ISSUED | VANGUARD CONSTRUCTION AND | 01/07/2015 |
| BIS | PL | ISSUED | MEGA PLBG CORP | 07/21/2014 |
| BIS | OT | ISSUED | VANGUARD CONSTRUCTION AND | 05/14/2014 |
| BIS | MH | ISSUED | VANGUARD CONSTRUCTION AND | 05/14/2014 |
| BIS | MH | ISSUED | POWER COOLING INC | 10/03/2013 |
| BIS | PL | ISSUED | PARAMOUNT PLBG & HTG CORP | 01/30/2013 |
| BIS | OT | ISSUED | J LAWRENCE CONSTRCTN CORP | 10/22/2012 |
| BIS | PL | ISSUED | EAST COAST MECHANICAL LLC | 10/18/2012 |
| BIS | OT | ISSUED | J LAWRENCE CONSTRCTN CORP | 10/05/2012 |
| BIS | OT | ISSUED | PLAZA CONSTRUCTION CORP | 05/10/2012 |
| BIS | OT | ISSUED | PLAZA CONSTRUCTION CORP | 05/10/2012 |
| BIS | OT | ISSUED | PLAZA CONSTRUCTION CORP | 05/10/2012 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/29/2021 | Signed-off | HUDSON PLMBING & MCH, LLC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/15/2026 | Permit Issued | CONDUCTOR ELECL SVCS INC | General Wiring |
| 07/30/2025 | Complete | JUMPER ELECTRIC CORP | General Wiring |
| 12/26/2023 | Complete | DENMAR ELECTRIC CORP | General Wiring |
| 11/29/2023 | Complete | CONDUCTOR ELECL SVCS INC | General Wiring |
| 03/07/2023 | Permit Issued | OMD ELECTRICAL CORP | 39 meters, 1 new_meters |
| 11/16/2020 | Complete | CONDUCTOR ELECL SVCS INC | General Wiring |
| 02/05/2020 | Complete | CONDUCTOR ELECL SVCS INC | General Wiring |
| 01/11/2019 | Complete | TOP SHELF ELECTRIC CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/28/2026 | — | — | 2 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/11/2026 | Signed-off | HUDSON PLMBING & MCH, LLC | Tenant Protection Plan 72 Hour |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/07/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/20/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/16/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/14/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/23/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/31/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/31/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/15/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 08/28/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/29/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/18/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/14/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/07/2021 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/07/2021 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/17/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/01/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/21/2026 | Tenant Protection Plan Compliance | — | special |
| 07/21/2026 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 07/21/2026 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 01/06/2026 | Tenant Protection Plan Compliance | AILANTO DANIEL MINAWI | special |
| 01/05/2026 | Fire-Resistance Rated Construction | AILANTO DANIEL MINAWI | progress |
| 01/05/2026 | Energy Code Compliance Inspections | AILANTO DANIEL MINAWI | progress |
| 12/11/2025 | Fire-Resistant Penetrations and Joints | AILANTO DANIEL MINAWI | special |
| 12/11/2025 | Final | AILANTO DANIEL MINAWI | progress |
| 12/11/2025 | Tenant Protection Plan Compliance | AILANTO DANIEL MINAWI | special |
| 11/13/2024 | Tenant Protection Plan Compliance | AILANTO DANIEL MINAWI | special |
| 11/13/2024 | Fire-Resistance Rated Construction | AILANTO DANIEL MINAWI | progress |
| 11/13/2024 | Energy Code Compliance Inspections | AILANTO DANIEL MINAWI | progress |
| 11/13/2024 | Lighting controls | AILANTO DANIEL MINAWI | energy_progress |
| 11/04/2024 | Interior lighting power | AILANTO DANIEL MINAWI | energy_progress |
| 11/04/2024 | Tenant Protection Plan Compliance | AILANTO DANIEL MINAWI | special |
| 11/04/2024 | Fire-Resistant Penetrations and Joints | AILANTO DANIEL MINAWI | special |
| 11/04/2024 | Lighting in dwelling units | AILANTO DANIEL MINAWI | energy_progress |
| 11/04/2024 | Final | AILANTO DANIEL MINAWI | progress |
| 10/17/2023 | Tenant Protection Plan Compliance | AILANTO DANIEL MINAWI | special |
| 09/28/2023 | Tenant Protection Plan Compliance | AILANTO DANIEL MINAWI | special |
| 08/11/2023 | Tenant Protection Plan Compliance | AILANTO DANIEL MINAWI | special |
| 07/26/2023 | Tenant Protection Plan Compliance | AILANTO DANIEL MINAWI | special |
| 06/14/2023 | Tenant Protection Plan Compliance | AILANTO DANIEL MINAWI | special |
| 05/11/2023 | Interior lighting power | AILANTO DANIEL MINAWI | energy_progress |
| 05/11/2023 | Lighting in dwelling units | AILANTO DANIEL MINAWI | energy_progress |