RoofUnder Construction86p · 9 filings · 20 docs
ArchitectureCivilElectricalEquipmentFire ProtectionGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
Earth Work · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Supported Scaffold
This PAA is includes the additional SOE required for the Con Ed vault for the project. The new work is shown on Dwg SOE-500. None of the other drawings have any changes.
On file for this project
130 documents · 12 drawing sheets
INSTALLATION AND USE OF SCAFFOLD AS PER PLANS SUBMITTED.SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF NYC BUILDING CODE. THIS APPLICATION INVOLVES NO CHANGE INOCCUPANCY, USE OR EGRESS.
On file for this project
2 documents
Installation of temporary construction fence in conjunction with NB
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 9 filings on this floor.
Floor 4Under Construction182p · 1 filing · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
This PAA is includes the additional SOE required for the Con Ed vault for the project. The new work is shown on Dwg SOE-500. None of the other drawings have any changes.
On file for this project
130 documents
Floor 3Under Construction188p · 2 filings · 20 docs
ArchitectureCivilFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural · Supported Scaffold
This PAA is includes the additional SOE required for the Con Ed vault for the project. The new work is shown on Dwg SOE-500. None of the other drawings have any changes.
On file for this project
130 documents
INSTALLATION AND USE OF SCAFFOLD STAIR TOWERS AS PER PLANS SUBMITTED. SCAFFOLD STAIR TOWERS SHALL COMPLY WITH CHAPTER #33 OF NYC BUILDING CODE. THIS APPLICATION INVOLVES NO CHANGE IN OCCUPANCY, USE OR EGRESS.
On file for this project
3 documents
Floor 2Under Construction208p · 7 filings · 20 docs
ArchitectureCivilElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural · Supported Scaffold
This PAA is includes the additional SOE required for the Con Ed vault for the project. The new work is shown on Dwg SOE-500. None of the other drawings have any changes.
On file for this project
130 documents · 7 drawing sheets
INSTALLATION AND USE OF SCAFFOLD AS PER PLANS SUBMITTED.SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF NYC BUILDING CODE. THIS APPLICATION INVOLVES NO CHANGE INOCCUPANCY, USE OR EGRESS.
On file for this project
2 documents
Installation and use of temporary mini crane filed herein. No change in egress, use, and occupancy.
On file for this project
2 documents
Latest 3 of 7 filings on this floor.
Floor 1Under Construction231p · 8 filings · 20 docs
ArchitectureCivilElectricalEquipmentFire ProtectionGeneralLandscapeMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Earth Work · General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sidewalk Shed · Sprinklers · Structural · Supported Scaffold
This PAA is includes the additional SOE required for the Con Ed vault for the project. The new work is shown on Dwg SOE-500. None of the other drawings have any changes.
On file for this project
130 documents · 16 drawing sheets
INSTALLATION AND USE OF SCAFFOLD AS PER PLANS SUBMITTED.SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF NYC BUILDING CODE. THIS APPLICATION INVOLVES NO CHANGE INOCCUPANCY, USE OR EGRESS.
On file for this project
2 documents
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED AS PER PLANS IN CONJUNCTION WITH NB CONSTRUCTION. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2022.
On file for this project
3 documents
Latest 3 of 8 filings on this floor.
MezzanineUnder Construction4p · 1 filing · 5 docs
EquipmentGeneralMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods
Installation of temporary monorail construction equipment at North Facade as per plans filed herewith.
On file for this project
5 documents
CellarUnder Construction20p · 1 filing · 20 docs
Plumbing
Issued Permit Scope
Plumbing
This PAA is includes the additional SOE required for the Con Ed vault for the project. The new work is shown on Dwg SOE-500. None of the other drawings have any changes.
On file for this project
130 documents
Site & exteriorUnder Construction72p · 3 filings · 20 docs
CivilElectricalEquipmentGeneralStructural
Issued Permit Scope
Construction Fence · Earth Work · Foundation · Support of Excavation
This PAA is includes the additional SOE required for the Con Ed vault for the project. The new work is shown on Dwg SOE-500. None of the other drawings have any changes.
On file for this project
130 documents · 12 drawing sheets
Installation of temporary construction fence in conjunction with NB
On file for this project
3 documents · 7 drawing sheets
HUB CONSULTATION ACCEPTED - Herewith Filing Earthwork in advance of/ associated with converting existing parking lot to recreation building and accessory parking lot.
On file for this project
7 documents · 8 drawing sheets
Filed — no permit issued4p · 2 filings · 7 docs
CivilPlumbingStructural
No filed description on record for this project.
On file for this project
4 documents · 3 drawing sheets
No filed description on record for this project.
On file for this project
3 documents · 1 drawing sheet