Bungalow colony - cooperatively owned land
1 MAPLE AVENUE
BRONX · BIN 2097655
💬 Discuss this project
1921Year Built
2Stories
A8Building Class
R4AZoning
63,464 sfGross Floor Area
44Units
1 Open Violation 0 unresolved · 1 paperwork only ▸
Bungalow colony - cooperatively owned land · Owner of record: SILVER BEACH GARDENS CORPORATION · 134,000 sf lot · 0.47 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectrical
Permit Issued — active, not yet Signed-off
RoofUnder Construction5p · 2 filings · 19 docs
Floor 21 filing · 3 docs
Floor 11p · 2 filings · 6 docs
Cellar1p · 1 filing · 3 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC208/25/2026
KENNETH KOONS, ARCHITECTS201/08/2022
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BROTHER'S QUALITY GENENERGeneral Contractor303/21/2026
SUNRUN INSTALLATION SVCGeneral Contractor107/30/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272208/25/2026
KENNETH KOONS, ARCHITECTS1548101/08/2022
Building Lifecycle
All (18)Filed (4)Permit Issued (2)Inspection (1)Special Inspection (11)
08/25/2026
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF-MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X01435517-P1
08/07/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
08/07/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
08/07/2026
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
08/07/2026
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
08/07/2026
Special inspection requirement — Final
Walid Abdulla
07/29/2026
Permit issued — Solar
X01435517-I1-SL
07/24/2026
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF-MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X01435517-I1
07/24/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
07/24/2026
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
07/23/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
07/23/2026
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
07/23/2026
Special inspection requirement — Final
Walid Abdulla
08/02/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/16/2022
Permit issued — Structural
X00614000-I1-GC-CX
01/08/2022
Filed — Alteration
X00614000-I1
01/08/2022
Filed — Alteration
NEW BATHROOM AT SECOND FLOOR
X00617735-I1
10/24/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedSUNRUN INSTALLATION SVC07/29/2026
DOB NOWStructuralPermit IssuedBROTHER'S QUALITY GENENER08/16/2022
1 project · most recent 01/08/2022
Water/Sanitary
FiledStatusContractorScope
01/08/2022——Water/Sanitary
1 project · most recent 09/29/2026
General Wiring
FiledStatusContractorScope
09/29/2026Permit IssuedSUNRUN SOLAR ELECTL CORPGeneral Wiring
1 project · most recent 08/25/2026
FiledStatusContractorScope
08/25/2026Permit IssuedSUNRUN INSTALLATION SVC54 panels, 24.3 kw, 378.41 roof_area_sqft
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
08/02/2023Pass-Final CND-Occupancy InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 11
DateRequirementInspectorRole
08/07/2026Fire-Resistant Penetrations and JointsWalid Abdullaspecial
08/07/2026Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
08/07/2026Air barrier - visual inspectionWalid Abdullaenergy_progress
08/07/2026Energy Code Compliance InspectionsWalid Abdullaprogress
08/07/2026FinalWalid Abdullaprogress
07/24/2026Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
07/24/2026Air barrier - visual inspectionWalid Abdullaenergy_progress
07/23/2026Fire-Resistant Penetrations and JointsWalid Abdullaspecial
07/23/2026Energy Code Compliance InspectionsWalid Abdullaprogress
07/23/2026FinalWalid Abdullaprogress
10/24/2021Fire-Resistant Penetrations and Joints—special
▾Documents — 23 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/24/2026X00617735-I1Request digital key ↗
08/24/2026X00614000-I1Request digital key ↗
08/16/2026X01435517-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications14
▸DOB NOWProgress Inspector Seal & Signature6
09/23/2026X01435517-P1Open ↗
09/23/2026X01435517-P1Open ↗
09/23/2026X01435517-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/24/2026X00617735-I1Open ↗
08/24/2026X00614000-I1Open ↗
08/16/2026X01435517-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/23/2026X01435517-P1Open ↗
09/23/2026X01435517-P1Open ↗
08/24/2026X01435517-I1Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
09/10/2026X01435517-P1Open ↗
08/24/2026X00617735-I1Open ↗
08/24/2026X00614000-I1Open ↗
Showing 3 of 5 on file for this type