← Back
Elevator apt, miscellaneous
NY823_Avalon Morningside Park
1 MORNINGSIDE DRIVE · BIN 1087754
💬 Discuss this project
2008Year Built
18Stories
D9Building Class
R7-2Zoning
358,800 sfGross Floor Area
295Units
LL97 CoveredRent Stabilized0 Open ViolationsFISP: SAFE
Elevator apt, miscellaneous · Owner of record: AVB MORNINGSIDE PARK, LLC · 24,876 sf lot · 14.42 FAR built · Flood zone X
Locations of Work
Structural
Roof1p · 1 filing · 2 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
AVALONBAY NYC DEVELOPMENT, INC3307/08/2026
NEW AMERICAN CONSTRUCTION INC807/08/2026
AVB MORNINGSIDE PARK, LLC603/22/2026
RJ GREEN CONSTRUCTION COR203/22/2026
SHAH GROUP ENTERPRISES303/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
STRUCTURAL WORKSHOP LLC212/11/2025
LORING CONSULTING ENGINEERS, INC.712/12/2024
JEFFREY S DEGEN101/31/2024
GREEN DESIGN108/02/2018
AME SERVICES INC203/07/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
DOMANI CONSULTING1903/21/2026
ATLANTIC BUILDING SUPPLY INC.403/21/2026
SMEP DESIGN & CONSULTATION LLC203/21/2026
AME SERVICES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
AVALONBAY NYC DEVELOPMENTGeneral Contractor603/21/2026
CAPITOL FIRE SPRINKLERPlumbing303/22/2026
CAPITOL FIRE SPRINKLER COFire Protection107/08/2026
INFRASTRUCTURE REPAIR SERVICEGeneral Contractor104/09/2026
JASCO, INCGeneral Contractor107/08/2026
NEW AMERICAN CONSTRUCTION INCGeneral Contractor107/08/2026
R J GREEN CONSTRUCTI CORPGeneral Contractor107/08/2026
4000 ELECTRIC CORPElectrical103/22/2026
MACCARONE PLUMBING INCPlumbing107/08/2026
GUSTAVE DILEO, JR.Electrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DOMANI INSPECTION SERVICE843812/04/2025
Building Lifecycle
All (130)Filed (14)Permit Issued (9)Signed Off (9)Facade (FISP) (12)Violation (60)Inspection (6)Special Inspection (20)
06/15/2026
Signed off — Alteration
M01265709-I1
02/05/2026
Cycle 10 facade report signed — SAFE
01/22/2026
Cycle 10 facade inspection completed
12/16/2025
Permit issued — General Construction
M01325242-I1-GC-CX
12/15/2025
Cycle 10 facade report submitted
12/11/2025
Filed — Alteration
RESTORATION AND REPAIR OF EXISTING GARAGE STRUCTURE
M01325242-P1
12/11/2025
Special inspection requirement — Tenant Protection Plan Compliance
JOHN MCMONAGLE
12/11/2025
Special inspection requirement — Final
JOHN MCMONAGLE
12/11/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
JOHN MCMONAGLE
12/09/2025
Special inspection requirement — Final
12/09/2025
Special inspection requirement — Tenant Protection Plan Compliance
12/09/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
12/04/2025
Filed — Alteration
RESTORATION AND REPAIR OF EXISTING GARAGE STRUCTURE
M01325242-I1
09/02/2025
Permit issued — Suspended Scaffold
M01265709-I1-SC
08/28/2025
Filed — Alteration
M01265709-I1
01/22/2025
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/03/2025
Signed off — Alteration
sprinkler work being filed in conjunction with M00947177-I1
M00947177-S3
01/03/2025
Signed off — Alteration
sprinkler work being filed in conjunction with M00947177-I1
M00947177-S2
01/03/2025
Signed off — Alteration
sprinkler work being filed in conjunction with M00947177-I1
M00947177-S1
12/31/2024
Signed off — Alteration
sprinkler work being filed in conjunction with M00947177-I1
M00947177-I1
12/12/2024
Filed — Alteration
sprinkler work being filed in conjunction with M00947177-I1
M00947177-P3
12/12/2024
Special inspection requirement — Sprinkler Systems
JOHN MCMONAGLE
12/12/2024
Special inspection requirement — Tenant Protection Plan Compliance
JOHN MCMONAGLE
12/09/2024
Special inspection requirement — Sprinkler Systems
JOHN MCMONAGLE
12/09/2024
Special inspection requirement — Tenant Protection Plan Compliance
10/08/2024
Filed — Alteration
sprinkler work being filed in conjunction with M00947177-I1
M00947177-P2
10/03/2024
Special inspection requirement — Sprinkler Systems
JOHN MCMONAGLE
10/03/2024
Special inspection requirement — Tenant Protection Plan Compliance
JOHN MCMONAGLE
10/01/2024
Violation issued (ECB, closed)
Construction
08/30/2024
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
08/22/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
07/17/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/16/2024
Special inspection requirement — Tenant Protection Plan Compliance
JOHN MCMONAGLE
07/12/2024
Filed — Alteration
sprinkler work being filed in conjunction with M00947177-I1
M00947177-P1
07/09/2024
Special inspection requirement — Tenant Protection Plan Compliance
06/25/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
06/25/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/03/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/20/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/20/2024
Permit issued — Mechanical Systems
M00947177-S2-MS
02/16/2024
Permit issued — General Construction
M00947177-I1-GC
02/13/2024
Permit issued — Sprinklers
M00947177-S3-EW-SP
02/12/2024
Permit issued — Plumbing
M00947177-S1-PL
02/02/2024
Filed — Alteration
sprinkler work being filed in conjunction with M00947177-I1
M00947177-S2
02/01/2024
Filed — Alteration
sprinkler work being filed in conjunction with M00947177-I1
M00947177-S3
02/01/2024
Filed — Alteration
sprinkler work being filed in conjunction with M00947177-I1
M00947177-S1
01/31/2024
Filed — Alteration
sprinkler work being filed in conjunction with M00947177-I1
M00947177-I1
01/31/2024
Violation issued (ECB, closed)
Elevators
01/19/2024
Special inspection requirement — Tenant Protection Plan Compliance
JOHN MCMONAGLE
01/19/2024
Special inspection requirement — Tenant Protection Plan Compliance
JOHN MCMONAGLE
11/07/2023
Special inspection requirement — Final
JOHN MCMONAGLE
11/07/2023
Special inspection requirement — Mechanical Systems
JOHN MCMONAGLE
10/12/2023
Special inspection requirement — Final
JOHN MCMONAGLE
07/27/2022
Violation issued (ECB, closed)
Elevators
03/11/2022
Signed off — Alteration
HEREWITH FILING PLUMBING WORK FOR DOMESTIC WATER AND SANITARY WATER IN COMPLIANCE WITH LOCAL LAW 110 OF 2013 AND 2014 NYC BUILDING CODE SECTION 614.1, WHEREAS BUILDINGS ARE REQUIRED TO PROVIDE ALTERNATIVE POTABLE WATER ACCESS.
M00397467-I1
06/24/2021
Cycle 9 facade report submitted
06/18/2021
Cycle 9 facade inspection completed
06/18/2021
Cycle 9 facade report signed — SAFE
02/16/2021
Filed — Alteration
HEREWITH FILING PLUMBING WORK FOR DOMESTIC WATER AND SANITARY WATER IN COMPLIANCE WITH LOCAL LAW 110 OF 2013 AND 2014 NYC BUILDING CODE SECTION 614.1, WHEREAS BUILDINGS ARE REQUIRED TO PROVIDE ALTERNATIVE POTABLE WATER ACCESS.
M00397467-I1
09/30/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Latest 60 of 130 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offINFRASTRUCTURE REPAIR SER12/16/2025
DOB NOWSuspended ScaffoldSigned-offSTRUCTUAL PRESV SYSTEM09/02/2025
DOB NOWMechanical SystemsSigned-offAVALONBAY NYC DEVELOPMENT02/20/2024
DOB NOWGeneral ConstructionSigned-offAVALONBAY NYC DEVELOPMENT02/16/2024
DOB NOWSprinklersSigned-offCAPITOL FIRE SPRINKLER CO02/13/2024
DOB NOWPlumbingSigned-offMACCARONE PLUMBING INC02/12/2024
DOB NOWSidewalk ShedSigned-offNEW AMERICAN CONSTRUCTION08/10/2018
DOB NOWConstruction FenceSigned-offR J GREEN CONSTRUCTI CORP03/08/2018
DOB NOWSidewalk ShedSigned-offJASCO, INC02/17/2018
BISSPISSUEDSTANDARD FIRE SUPP CORP01/30/2019
BISOTISSUEDR J GREEN CONSTRUCTI CORP03/09/2018
BISEQISSUEDSHAH GROUP ENTERPRISES IN04/28/2017
BISPLISSUEDRAPTOR MECHANICAL,INC03/21/2012
BISMHISSUEDAEGIS ENERGY SERVICES LLC03/19/2012
BIS—ISSUEDTHE CATHEDRAL CHURCH02/15/2012
BIS—ISSUEDGOING SIGN & SVCNG CO,INC09/06/2011
BIS—ISSUEDAVALONBAY NYC DEVELOPMENT07/27/2009
BISEQISSUEDAVALONBAY NYC DEVELOPMENT07/27/2009
BIS—ISSUEDAVALONBAY NYC DEVELOPMENT09/30/2008
BIS—ISSUEDAVALONBAY NYC DEVELOPMENT08/12/2008
BISEQISSUEDAVALONBAY NYC DEVELOPMENT08/12/2008
BISCCISSUEDAVALONBAY NYC DEVELOPMENT INC07/30/2008
BISPLISSUEDPARKVIEW P&H INC04/29/2008
BISEQISSUEDUNITED HOISTING & SCAFFOLDING03/25/2008
BISEQISSUEDUNITED HOISTING & SCAFFOLDING CO03/25/2008
BISEQISSUEDUNITED HOISTING & SCAFFOLDING CO03/21/2008
BISBLISSUEDACE-ATLAS PLBING & HTG03/04/2008
BISEQISSUEDUNITED HOISTING & SCAFFOLDING CO01/08/2008
BISEQISSUEDUNITED HOISTING & SCAFFOLDING12/28/2007
BISSPISSUEDACTIVE FIRE SPRIKLER12/12/2007
BISEQISSUEDAVALONBAY NYC DEVELOPMENT12/11/2007
BISEQISSUEDUNITED HOISTING & SCAFFOLDING09/27/2007
BISSDISSUEDACTIVE FIRE SPRINKLER CORP.09/13/2007
BISEQISSUEDUNITED HOISTING & SCAFFOLDING CO09/04/2007
BISEQISSUEDUNITED HOISTING & SCAFFOLDING CO09/04/2007
BISOTISSUEDAVALONBAY NYC DEVELOPMENT08/27/2007
BIS—ISSUEDAVALONBAY NYC DEVELOPMENT07/30/2007
BISEQISSUEDAVALONBAY NYC DEVELOPMENT07/30/2007
BIS—ISSUEDAVALONBAY NYC DEVELOPMENT06/15/2007
BISPLISSUEDPARKVIEW P&H INC04/10/2007
+ 3 more permits on file
4 projects · most recent 09/18/2024
General Wiring
FiledStatusContractorScope
09/18/2024Permit IssuedHYLAN DATACOM & ELECL LLC2 meters, 1 new_meters
09/08/2021CompleteSWITCH INC. ELEC'L CONTRGeneral Wiring
08/08/2018CompleteRICHARD NEU—
02/16/2018Permit Issued4000 ELECTRIC CORP—
1 project · most recent 12/11/2025
Concrete
FiledStatusContractorScope
12/11/2025Signed-offINFRASTRUCTURE REPAIR SERConcrete
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
08/30/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/22/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/17/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/25/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/25/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/20/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 20
DateRequirementInspectorRole
12/11/2025Tenant Protection Plan ComplianceJOHN MCMONAGLEspecial
12/11/2025FinalJOHN MCMONAGLEprogress
12/11/2025Structural Stability – Alterations of existing buildingsJOHN MCMONAGLEspecial
12/09/2025Final—progress
12/09/2025Tenant Protection Plan Compliance—special
12/09/2025Structural Stability – Alterations of existing buildings—special
12/12/2024Sprinkler SystemsJOHN MCMONAGLEspecial
12/12/2024Tenant Protection Plan ComplianceJOHN MCMONAGLEspecial
12/09/2024Sprinkler SystemsJOHN MCMONAGLEspecial
12/09/2024Tenant Protection Plan Compliance—special
10/03/2024Sprinkler SystemsJOHN MCMONAGLEspecial
10/03/2024Tenant Protection Plan ComplianceJOHN MCMONAGLEspecial
07/16/2024Tenant Protection Plan ComplianceJOHN MCMONAGLEspecial
07/09/2024Tenant Protection Plan Compliance—special
01/19/2024Tenant Protection Plan ComplianceJOHN MCMONAGLEspecial
01/19/2024Tenant Protection Plan ComplianceJOHN MCMONAGLEspecial
11/07/2023FinalJOHN MCMONAGLEprogress
11/07/2023Mechanical SystemsJOHN MCMONAGLEspecial
10/12/2023FinalJOHN MCMONAGLEprogress
02/15/2018FinalASMA FARUQIprogress
▾Documents — 155 on file (BIS + DOB NOW)
▸Plans & Drawings14
▸DOB NOWPlans/Sketch13
09/06/2026M00019958-I1Request digital key ↗
09/06/2026M00016666-I1Request digital key ↗
09/06/2026M00067466-I1Request digital key ↗
Showing 3 of 13 on file for this type
▸DOB NOWPlans/Sketch - Plumbing1
09/04/2026M00397467-I1Request digital key ↗
▸Applications & Permits21
▸BISWORK PERMIT APPLICATION9
01/30/2019122214772Open ↗
03/12/2018123313832Open ↗
04/27/2017140634464Open ↗
Showing 3 of 9 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION9
01/23/2019122214772Open ↗
10/19/2018123313832Open ↗
08/07/2017123313832Open ↗
Showing 3 of 9 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION3
03/07/2012120850962Open ↗
02/02/2009110095557Open ↗
02/22/2012120850962Open ↗
▸Seals & Professional Certifications52
▸DOB NOWDPL-1: Design Professional Seal & Signature13
09/06/2026M00019958-I1Open ↗
09/06/2026M00016666-I1Open ↗
09/04/2026M00397467-I1Open ↗
Showing 3 of 13 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION12
09/16/2019140634464Open ↗
09/16/2019140634464Open ↗
01/30/2019122214772Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/01/2026M00947177-S3Open ↗
09/01/2026M00947177-S3Open ↗
08/26/2026M00947177-S1Open ↗
Showing 3 of 9 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST5
01/23/2019122214772Open ↗
03/23/2012121006632Open ↗
10/11/2011120850962Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM4
03/23/2012121006632Open ↗
10/11/2011120850962Open ↗
07/15/2011120741812Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/26/2026M00019958-I1Open ↗
08/24/2026M00947177-I1Open ↗
08/23/2026M01325242-I1Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
01/23/2019122214772Open ↗
04/27/2017140634464Open ↗
▸BISPC FULL REPORT1
02/15/2008110095557Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
04/27/2017140634464Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
04/27/2017140634464Open ↗
▸Trade Schedules & Equipment8
▸BISSELF-CERT PLUMBING NOTICE4
01/22/2013121006632Open ↗
08/06/2012121006632Open ↗
08/06/2012121006632Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT2
07/11/2008110095557Open ↗
02/15/2008110095557Open ↗
▸BISSCHEDULE B - PLUMBING1
03/23/2012121006632Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
01/23/2019122214772Open ↗
▸Safety & Tenant Protection4
▸BISTenant Protection Plan and Notes2
01/30/2019122214772Open ↗
09/07/2017123313832Open ↗
▸BISSTREET TREE CHECKLIST1
02/17/2012120850962Open ↗
▸DOB NOWTenant Protection Plan1
09/04/2026M00397467-I1Open ↗
▸Environmental & Asbestos7
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER3
07/15/2011120741812Open ↗
03/13/2008110111600Open ↗
01/29/2008110085425Open ↗
▸BISTHIS IS NOT AN ASBESTOS PROJECT2
02/19/2008110095557Open ↗
03/23/2012121006632Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
09/07/2017123313832Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
09/04/2026M00397467-I1Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
11/20/2018123313832Open ↗
08/07/2017123313832Open ↗
06/12/2013121006632Open ↗
▸BISAS-BUILT ENERGY ANALYSIS2
11/20/2018123313832Open ↗
06/12/2013121006632Open ↗
▸BISTECHNICAL REPORT: ENERGY1
03/23/2012121006632Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
04/27/2017140634464Open ↗
▸Inspections & Test Reports2
▸BISNOTIF.-PROPOSED STEAM/HOT WATER INSPECTION2
07/11/2008110095557Open ↗
02/15/2008110095557Open ↗
▸Approvals, Objections & Sign-offs13
▸BISADMINISTRATIVE OBJECTIONS6
03/23/2012121006632Open ↗
10/11/2011120850962Open ↗
07/15/2011120741812Open ↗
Showing 3 of 6 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
09/16/2019140634464Open ↗
11/20/2018123313832Open ↗
06/12/2013121006632Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION1
06/12/2013121006632Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE1
10/11/2011120850962Open ↗
▸Cost, Insurance & Ownership9
▸BISCOST AFFIDAVIT9
01/23/2019122214772Open ↗
11/20/2018123313832Open ↗
10/19/2018123313832Open ↗
Showing 3 of 9 on file for this type
▸Filing & Intake Forms14
▸BISADDITIONAL INFORMATION5
12/21/2017123313832Open ↗
12/21/2017123313832Open ↗
11/30/2017123313832Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING COVER SHEET4
01/23/2019122214772Open ↗
08/07/2017123313832Open ↗
03/23/2012121006632Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM3
09/16/2019140634464Open ↗
11/20/2018123313832Open ↗
10/19/2018123313832Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET2
04/27/2017140634464Open ↗
07/15/2011120741812Open ↗
▸Other Documents4
▸BISPLOT DIAGRAM1
10/11/2011120850962Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
03/12/2018123313832Open ↗
▸DOB NOWDHCR Document1
09/04/2026M00397467-I1Open ↗
▸DOB NOWIRA Certification1
08/13/2026M01265709-I1Open ↗