Stadium, race track, baseball field
1 TENNIS PLACE
QUEENS · Forest Hills · BIN 4437648
💬 Discuss this project
1915Year Built
2Stories
Q6Building Class
R3-2Zoning
56,388 sfGross Floor Area
2Units
LL97 Covered0 Active ViolationsFDNY Report ↗
Stadium, race track, baseball field · 509,215 sf lot · 0.11 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofTiebreaker Productions1p · 1 filing · 16 docs
Floor 1Forest Hills Stadium34p · 10 filings · 20 docs
CellarForest Hills Tennis Center2p · 1 filing · 5 docs
Site & exteriorBowery Presents, Tiebreaker Productions +3Under Construction122p · 25 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Madison House Presents2207/08/2026
Tiebreaker Productions409/15/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SYNC Architecture3409/23/2026
ADG Architecture and Design105/21/2026
RLM Engineering412/13/2024
Cornerstone107/09/2024
Robert Papazian Architect409/07/2023
Urban Associates206/15/2021
Fzad206/01/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Municipal Building Consultants1203/21/2026
Robert Papazian Architect803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Arena Event ServicesGeneral Contractor807/08/2026
Timocon Interior ConstructionGeneral Contractor504/09/2026
Richards Plum & Heating CoGeneral Contractor303/21/2026
T & J Elect'l ContractingElectrical303/22/2026
Dynamic Construction ServiceGeneral Contractor303/21/2026
Winick ProductionsGeneral Contractor309/07/2026
RRP PlumbingPlumbing207/08/2026
Richards P and H CoPlumbing207/08/2026
NYFF EventsGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
RLM Engineering6913211/06/2024
Ryan Special Engineering2018107/09/2024
Structural Engineering Integ4174409/07/2023
Robert Papazian Architect3491204/14/2023
Urban Engineering2575206/15/2021
Building Lifecycle
All (154)Filed (48)Permit Issued (20)Signed Off (9)Violation (14)Inspection (5)Objection (28)Special Inspection (30)
09/23/2026
Filed — No Work
Q01464110-I1
09/14/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/03/2026
Permit issued — General Construction
Q01454043-I1-GC
09/01/2026
Filed — No Work
Q01453845-I1
09/01/2026
Filed — Alteration
Temporary structures for the Forest Hills Stadium programming. No changes to existing structures, use or egress.
Q01454043-I1
09/01/2026
Special inspection requirement — Final
ANDY ENGLER ROTH
08/10/2026
Filed — No Work
Q01443210-I1
06/08/2026
Signed off — Alteration
Temporary Installations to be used on a temporary event "TOMA Nike Forest Hills". All Installations are to be removed upon completion of the event.
Q01405485-I1
06/01/2026
Objection resolved — Addressed
06/01/2026
Objection resolved — Addressed
05/30/2026
Objection raised — Other
05/30/2026
Objection raised — Other
05/27/2026
Permit issued — General Construction
Q00548983-I1-GC
05/26/2026
Filed — No Work
Q01407429-I1
05/26/2026
Permit issued — General Construction
Q01405485-I1-GC
05/21/2026
Filed — Alteration
Temporary Installations to be used on a temporary event "TOMA Nike Forest Hills". All Installations are to be removed upon completion of the event.
Q01405485-I1
05/21/2026
Special inspection requirement — Final
Christopher Carrano
12/09/2025
Signed off — Alteration
Sound attenuation partitions for Forest Hills Stadium. No changes to use or egress.
Q01037622-I1
10/24/2025
Special inspection requirement — Final
ANDY ENGLER ROTH
10/23/2025
Filed — Alteration
Temporary structures for Forest Hills Stadium Programming as per plans filed herewith. No changes to existing structures, use or egress.
Q00548983-P5
10/20/2025
Filed — No Work
Q01305210-I1
08/18/2025
Permit issued — General Construction
Q00548983-I1-GC
08/12/2025
Filed — No Work
Q01269768-I1
07/11/2025
Signed off — Alteration
Installation of new 19KW Generac generator OSP as per plans filed herewith.
Q01097725-I1
06/25/2025
Signed off — Alteration
Installation of new 19KW Generac generator OSP as per plans filed herewith.
Q01097725-S1
05/30/2025
Objection resolved — Addressed
05/29/2025
Permit issued — General Construction
Q00548983-I1-GC
05/29/2025
Objection raised — Other
05/28/2025
Filed — No Work
Q01213622-P1
04/21/2025
Filed — No Work
Q01213622-I1
02/13/2025
Violation issued (FDNY_NOV, closed)
01/06/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/24/2024
Permit issued — Mechanical Systems
Q01097725-S1-MS
12/20/2024
Special inspection requirement — HVAC-R and service water heating equipment
Ronald Merhige
12/20/2024
Special inspection requirement — Maintenance information
Ronald Merhige
12/20/2024
Special inspection requirement — Energy Code Compliance Inspections
Ronald Merhige
12/13/2024
Filed — Alteration
Installation of new 19KW Generac generator OSP as per plans filed herewith.
Q01097725-P1
12/12/2024
Inspection — Certified Sprinkler (PL)-SP-Fixtures (PL)-Finish
Certified
View inspection ↗
12/12/2024
Special inspection requirement — Energy Code Compliance Inspections
Ronald Merhige
12/12/2024
Special inspection requirement — Maintenance information
Ronald Merhige
12/12/2024
Special inspection requirement — HVAC-R and service water heating equipment
Ronald Merhige
12/06/2024
Inspection — Certified Sprinkler (PL)-Sprinkler-Hydro
Certified
View inspection ↗
12/06/2024
Inspection — Certified Sprinkler (PL) - SP - Roughing
Certified
View inspection ↗
11/21/2024
Permit issued — Plumbing
Q01097725-I1-PL
11/06/2024
Filed — Alteration
Installation of new 19KW Generac generator OSP as per plans filed herewith.
Q01097725-I1
11/06/2024
Filed — Alteration
Installation of new 19KW Generac generator OSP as per plans filed herewith.
Q01097725-S1
11/04/2024
Special inspection requirement — Maintenance information
Ronald Merhige
10/31/2024
Permit issued — Plumbing
Q01086271-I1-PL
10/31/2024
Special inspection requirement — Emergency and Standby Power Systems (Generator)
Ronald Merhige
10/31/2024
Special inspection requirement — Energy Code Compliance Inspections
Ronald Merhige
10/21/2024
Special inspection requirement — Final
Ronald Merhige
10/21/2024
Special inspection requirement — Mechanical Systems
Ronald Merhige
10/09/2024
Filed — No Work
Q01124095-I1
09/27/2024
Filed — Alteration
Temporary structures for Forest Hills Stadium Programming as per plans filed herewith. No changes to existing structures, use or egress.
Q00548983-P4
09/27/2024
Special inspection requirement — Final
ANDY ENGLER ROTH
09/26/2024
Filed — No Work
Q01117371-I1
09/26/2024
Signed off — Alteration
Installation of open, exterior wood frame deck for accessory recreational occupancy.
Q00851331-I1
08/20/2024
Objection resolved — Addressed
08/19/2024
Filed — No Work
Q01097940-I1
08/19/2024
Objection raised — Other
Latest 60 of 154 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedWinick Productions09/03/2026
DOB NOWGeneral ConstructionPermit IssuedArena Event Services05/27/2026
DOB NOWGeneral ConstructionSigned-offNYFF Events05/26/2026
DOB NOWGeneral ConstructionPermit IssuedArena Event Services08/18/2025
DOB NOWGeneral ConstructionPermit IssuedArena Event Services05/29/2025
DOB NOWMechanical SystemsSigned-offRichards Plum & Heating Co12/24/2024
DOB NOWPlumbingSigned-offRichards P and H Co11/21/2024
DOB NOWPlumbingSigned-offRichards P and H Co10/31/2024
DOB NOWGeneral ConstructionSigned-offTimocon Interior Construction08/15/2024
DOB NOWGeneral ConstructionPermit IssuedArena Event Services08/14/2024
DOB NOWGeneral ConstructionPermit IssuedArena Event Services05/02/2024
DOB NOWGeneral ConstructionSigned-offTimocon Interior Construction01/26/2024
DOB NOWFoundationSigned-offTimocon Interior Construction12/06/2023
DOB NOWGeneral ConstructionSigned-offWinick Productions08/02/2023
DOB NOWGeneral ConstructionPermit IssuedArena Event Services08/05/2022
DOB NOWPlumbingSigned-offRRP Plumbing02/14/2022
DOB NOWGeneral ConstructionPermit IssuedArena Event Services08/09/2021
DOB NOWGeneral ConstructionPermit IssuedArena Event Services07/21/2021
DOB NOWStructuralSigned-offDynamic Construction Service06/03/2021
DOB NOWPlumbingSigned-offRRP Plumbing03/26/2021
BISOTISSUEDDynamic Construction Service03/15/2021
BISOTISSUEDArena Event Services09/26/2019
BISOTISSUEDArena Event Services05/03/2019
BISOTISSUEDTimocon Interior Construction02/11/2019
BISOTISSUEDArena Event Services10/03/2018
BISOTISSUEDArena Event Services05/25/2018
BISPLISSUEDInfiniti Esc Plumbing04/25/2018
BISPLISSUEDInfiniti Esc Plumbing04/19/2018
BISOTISSUEDTimocon Interior Construction03/20/2018
BISOTISSUEDTimocon Interior Construction03/19/2018
BISOTISSUEDTimocon Interior Construction03/14/2018
BISOTISSUEDArena Event Services08/22/2017
BISOTISSUEDArena Event Services08/18/2017
BISOTISSUEDArena Event Services05/10/2017
BISOTISSUEDArena Event Services09/29/2016
BISOTISSUEDArena Event Services08/10/2016
BISOTISSUEDArena Event Services07/26/2016
BISOTISSUEDArena Event Services07/19/2016
BISOTISSUEDArena Event Services07/19/2016
BISOTISSUEDArena Event Services07/19/2016
+ 21 more permits on file
1 project · most recent 08/08/2024
FiledStatusContractorScope
08/08/2024——4 heads
1 project · most recent 08/08/2024
Plumbing-Sprinkler
FiledStatusContractorScope
08/08/2024Signed-offRichards P and H CoPlumbing-Sprinkler
7 projects · most recent 08/11/2026
General Wiring
FiledStatusContractorScope
08/11/2026Permit IssuedScientific Electric CoGeneral Wiring
12/04/2025Permit IssuedEtricity Electrical CoGeneral Wiring
07/08/2025CompleteEtricity Electrical CoGeneral Wiring
06/06/2025Permit IssuedT & J Elect'l ContractingGeneral Wiring
04/28/2021CompleteAccurate Electrical ContractorsGeneral Wiring
05/15/2019Permit IssuedT & J Elect'l Contracting1 meters, 1 new_meters
05/17/2018CompleteT & J Elect'l ContractingGeneral Wiring
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
09/14/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/06/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/12/2024Certified Sprinkler (PL)-SP-Fixtures (PL)-FinishCertifiedView ↗
12/06/2024Certified Sprinkler (PL)-Sprinkler-HydroCertifiedView ↗
12/06/2024Certified Sprinkler (PL) - SP - RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 54
DateRequirementInspectorRole
09/01/2026FinalANDY ENGLER ROTHprogress
05/21/2026FinalChristopher Carranoprogress
10/24/2025FinalANDY ENGLER ROTHprogress
12/20/2024HVAC-R and service water heating equipmentRonald Merhigeenergy_progress
12/20/2024Maintenance informationRonald Merhigeenergy_progress
12/20/2024Energy Code Compliance InspectionsRonald Merhigeprogress
12/12/2024Energy Code Compliance InspectionsRonald Merhigeprogress
12/12/2024Maintenance informationRonald Merhigeenergy_progress
12/12/2024HVAC-R and service water heating equipmentRonald Merhigeenergy_progress
11/04/2024Maintenance informationRonald Merhigeenergy_progress
10/31/2024Emergency and Standby Power Systems (Generator)Ronald Merhigespecial
10/31/2024Energy Code Compliance InspectionsRonald Merhigeprogress
10/21/2024FinalRonald Merhigeprogress
10/21/2024Mechanical SystemsRonald Merhigespecial
09/27/2024FinalANDY ENGLER ROTHprogress
07/25/2024Sprinkler SystemsRonald Merhigespecial
07/25/2024Fire-Resistant Penetrations and JointsRonald Merhigespecial
01/25/2024Concrete - Cast-In-PlaceRobert Papazianspecial
01/25/2024Structural Steel - DetailsRobert Papazianspecial
01/25/2024Subgrade InspectionsChris Yiuspecial
01/25/2024Structural Cold-Formed SteelRobert Papazianspecial
01/25/2024Footing and FoundationRobert Papazianprogress
01/25/2024FinalRobert Papazianprogress
11/22/2023Concrete - Cast-In-PlaceRobert Papazianspecial
11/22/2023Subgrade InspectionsChris Yiuspecial
Latest 25 of 54.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Bowery PresentsArts / Culture / EntertainmentFloor 1
Project Q01454043 Alteration · Permit Entire · 09/01/2026
Forest Hills StadiumArts / Culture / EntertainmentFloor 1
Project Q01405485 Alteration · LOC Issued · 05/21/2026
Project Q01037622 Alteration · LOC Issued · 07/09/2024
Project Q00852826 Alteration · LOC Issued · 04/14/2023
Forest Hills Tennis CenterFitness / RecreationCellar
Project Q01097725 Alteration · LOC Issued · 11/06/2024
Project Q01086271 Alteration · Permit Entire · 08/08/2024
Tiebreaker ProductionsPrivate clubFloor 1
Project Q00911946 Alteration · LOC Issued · 08/01/2023
Project Q00548983 Alteration · Permit Entire · 06/30/2021
Forest Hills Tennis ClubPrivate club—
Project Q00851331 Alteration · LOC Issued · 04/03/2023
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 591 on file (BIS + DOB NOW)
▸Plans & Drawings44
▸DOB NOWPlans/Sketch - Temporary Place of Assembly26
10/13/2026Q01453845-I1Request digital key ↗
10/04/2026Q01464110-I1Request digital key ↗
08/28/2026Q00200155-I1Request digital key ↗
Showing 3 of 26 on file for this type
▸DOB NOWPlans/Sketch16
09/15/2026Q01454043-I1Request digital key ↗
08/27/2026Q00548983-P4Request digital key ↗
08/27/2026Q00548983-P5Request digital key ↗
Showing 3 of 16 on file for this type
▸DOB NOWPlans/Sketch - Plumbing2
08/28/2026Q00273432-P1Request digital key ↗
08/28/2026Q00273432-I1Request digital key ↗
▸Applications & Permits99
▸BISPLAN / WORK APPROVAL APPLICATION60
02/12/2024400875567Open ↗
02/05/2024410114246Open ↗
01/31/2024410114246Open ↗
Showing 3 of 60 on file for this type
▸BISWORK PERMIT APPLICATION38
03/15/2021440605070Open ↗
09/27/2019421917126Open ↗
05/15/2019421859563Open ↗
Showing 3 of 38 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications226
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION78
04/27/2020421917126Open ↗
04/27/2020421917126Open ↗
05/10/2019421859563Open ↗
Showing 3 of 78 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature45
10/13/2026Q01453845-I1Open ↗
10/04/2026Q01464110-I1Open ↗
09/15/2026Q01454043-I1Open ↗
Showing 3 of 45 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST29
09/26/2019421917126Open ↗
05/10/2019421859563Open ↗
11/10/2018421695339Open ↗
Showing 3 of 29 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT27
07/02/2020440605070Open ↗
09/26/2019421917126Open ↗
05/10/2019421859563Open ↗
Showing 3 of 27 on file for this type
▸DOB NOWProgress Inspector Seal & Signature26
10/02/2026Q01097725-P1Open ↗
10/02/2026Q01097725-P1Open ↗
10/02/2026Q01097725-P1Open ↗
Showing 3 of 26 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature16
09/02/2026Q00851331-P1Open ↗
08/28/2026Q01086271-I1Open ↗
08/28/2026Q01086271-I1Open ↗
Showing 3 of 16 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
07/02/2020440605070Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
07/02/2020440605070Open ↗
▸Trade Schedules & Equipment5
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
02/26/2018421606104Open ↗
02/26/2018421606122Open ↗
Showing 2 of 3 on file for this type
▸BISSELF-CERT PLUMBING NOTICE1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSCHEDULE B - PLUMBING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection4
▸BISTenant Protection Plan and Notes3
02/26/2018421606113Open ↗
02/26/2018421606097Open ↗
07/02/2020440605070Open ↗
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos13
▸BISASBESTOS: CERTIFICATION (DEP ACP5)6
07/02/2020440605070Open ↗
Showing 1 of 6 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/28/2026Q00273432-P1Open ↗
08/28/2026Q00273432-I1Open ↗
08/21/2026Q01086271-I1Open ↗
Showing 3 of 4 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Energy Compliance20
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
10/27/2023440605070Open ↗
▸BISLIGHTING CONTROLS1
10/27/2023440605070Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
10/27/2023440605070Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
07/02/2020440605070Open ↗
▸BISINTERIOR LIGHTING POWER1
10/27/2023440605070Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
07/02/2020440605070Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026Q01097725-I1Open ↗
▸Inspections & Test Reports11
▸BISTECHNICAL REPORT: RESPONSIBILITY4
11/17/2020421640031Open ↗
11/16/2020421640031Open ↗
10/01/2020421684617Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER3
03/22/2018421606113Open ↗
Showing 1 of 3 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX2
03/26/2018421606113Open ↗
Showing 1 of 2 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
03/17/2021421695339Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
03/22/2018421606113Open ↗
▸Approvals, Objections & Sign-offs56
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST32
03/17/2021421695339Open ↗
11/16/2020421640031Open ↗
06/11/2020410114246Open ↗
Showing 3 of 32 on file for this type
▸BISADMINISTRATIVE OBJECTIONS12
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 12 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION9
02/06/2024400875567Open ↗
03/17/2021421695339Open ↗
06/11/2020410114246Open ↗
Showing 3 of 9 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Cost, Insurance & Ownership59
▸BISCOST AFFIDAVIT57
07/02/2020440605070Open ↗
05/11/2020421917126Open ↗
09/26/2019421917126Open ↗
Showing 3 of 57 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
03/17/2021421695339Open ↗
10/01/2020421684617Open ↗
▸Filing & Intake Forms53
▸BISEFILING COVER SHEET34
09/25/2019421917126Open ↗
05/10/2019421859563Open ↗
11/10/2018421695339Open ↗
Showing 3 of 34 on file for this type
▸BISADDITIONAL INFORMATION17
02/13/2024400875567Open ↗
02/13/2024400875567Open ↗
02/06/2024400875567Open ↗
Showing 3 of 17 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET1
07/02/2020440605070Open ↗
▸BISBOROUGH INTAKE FORM1
04/27/2020421917126Open ↗
▸Other Documents1
▸BISPLOT DIAGRAM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type