| 2025-09-08 | Protection and Mechanical Methods | Signed-off | Nova Construction Service | INSTALLATION OF TEMPORARY BETAMAX HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| 2025-08-04 | Supported Scaffold | Signed-off | Nova Construction Service | INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| 2025-08-04 | General Construction | Signed-off | Nova Construction Service | MASONRY CLADDING INSTALLATION, PARAPET REBUILD, RAILING INSTALATION, BRICK REPLACEMENT, MASONRY RE-POINTING, AND PARTIAL ROOF REPLACEMENT . NO CHANGE IN USE, EGRESS OR O… |
| 2025-08-04 | Protection and Mechanical Methods | Signed-off | Nova Construction Service | INSTALLATION OF TEMPORARY SHANTY AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| 2025-07-16 | Sidewalk Shed | Signed-off | Nova Construction Service | INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| 2025-05-21 | Protection and Mechanical Methods | Signed-off | Nova Construction Service | INSTALLATION OF TEMPORARY STORAGE OF MATERIALS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| 2024-10-08 | Protection and Mechanical Methods | Signed-off | Nova Construction Service | INSTALLATION OF TEMPORARY BETAMAX HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| 2024-08-09 | Protection and Mechanical Methods | Signed-off | Nova Construction Service | INSTALLATION OF TEMPORARY SHANTY AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| 2024-08-09 | Supported Scaffold | Signed-off | Nova Construction Service | INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| 2024-08-07 | General Construction | Signed-off | Nova Construction Service | MASONRY CLADDING INSTALLATION, PARAPET REBUILD, RAILING INSTALATION, BRICK REPLACEMENT, MASONRY RE-POINTING, AND PARTIAL ROOF REPLACEMENT . NO CHANGE IN USE, EGRESS OR O… |
| 2024-07-23 | Sidewalk Shed | Signed-off | Nova Construction Service | INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. |
| 2021-10-26 | Boiler Equipment | Signed-off | Pro Star Plbg Htg & Mech | Installation of two new low pressure steam boilers, gas fired, for space heating only. A boiler does not currently exist. New gas service, solely for firing of boilers,… |
| 2021-07-19 | Boiler Equipment | Permit Issued | Pro Star Plbg Htg & Mech | Filing the other new low pressure steam boiler, gas fired, for space heating that was not captured in the initial filing M00434492-I1. No change in use, egress or occupa… |
| 2021-07-15 | Boiler Equipment | Permit Issued | Pro Star Plbg Htg & Mech | New Gas Service (1) boiler being installed (a boiler does not currently exist). Two new low pressure steam boilers, gas fired, for space heating. No change in use, egres… |
| 2021-07-15 | Plumbing | Signed-off | Pro Star Plbg Htg & Mech | Installation of new & relocated sprinkler heads and piping. New floor drains and roof drains connected to existing sewer, new water closets and lavatories. New gas servi… |
| 2021-06-10 | Mechanical Systems | Signed-off | Quest Builders Group Inc. | Installation of new low pressure steam boiler plant, associated equipment and accessories. Installation of new VRF heating and cooling equipment for limited areas. No ch… |
| 2021-05-28 | Plumbing | Signed-off | Five Boro Associates Inc. | Installation of new & relocated sprinkler heads and piping. New floor drains and roof drains connected to existing sewer, new water closets and lavatories. New gas servi… |
| 2021-05-17 | Structural | Signed-off | Quest Builders Group Inc. | DEMOLITION OF EXISTING INTERIOR MASONRY WALL. SLAB ON METAL DECK INFILL WITH STRUCTURAL STEEL. WELD SPLICING OF EXISTING STEEL BEAMS. NO CHANGE IN USE, EGRESS OR OCCUPAN… |
| 2021-05-12 | Boiler Equipment | Permit Issued | Pro Star Plbg Htg & Mech | New Gas Service (1) boiler being installed (a boiler does not currently exist). Two new low pressure steam boilers, gas fired, for space heating. No change in use, egres… |
| 2021-05-03 | Plumbing | Signed-off | Pro Star Plbg Htg & Mech | Installation of new & relocated sprinkler heads and piping. New floor drains and roof drains connected to existing sewer, new water closets and lavatories. New gas servi… |
| 2021-05-01 | General Construction | Signed-off | Quest Builders Group Inc. | REMOVAL OF INTERIOR NON-BEARING PARTITIONS AND RELATED FINISHES AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.APPLICATION FILED IN CONJUNCTION WITH… |
| 2020-07-01 | Structural | Signed-off | Signs Cad Corp. | REPLACE AN ACCESSORY D/F PYLON SIGN STRUCTURE ON THE GROUND INSIDE OF PROPERTY LINE, NO CHANGE IN USE, EGRESS, OR OCCUPANCY. This is not attached to the existing buildin… |
| 2020-04-08 | Sign | Signed-off | Signs Cad Corp. | REPLACE ACCESSORY D/F PYLON SIGN ON THE GROUND INSIDE OF PROPERTY LINE, NON-FLASHING, NON-ADVERTISING SIGN, NO CHANGE IN USE, EGRESS, OR OCCUPANCY |