10-01 HAZEN STREET · BIN 2109476
💬 Discuss this project
1933Year Built
6Stories
Y3Building Class
C8-2Zoning
5,519,372 sfGross Floor Area
1Units
LL97 Covered11 Open Violations 0 unresolved · 11 paperwork only ▸FDNY Report ↗
Prison, jail, house of detention · Owner of record: NYC DEPARTMENT OF CORRECTIONS · 17,825,000 sf lot · 0.31 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingGeneral
Floor 181p · 1 filing · 20 docs
Cellar85p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC DEPARTMENT OF CORRECTION1406/28/2026
DOC 072903/22/2026
DOC 0 072103/22/2026
DOC803/21/2026
DGS103/21/2026
DEPT OF DESIGN CONSTRUCTION1703/21/2026
GOVERNMENT DEPARTMENT OF CORRECT203/21/2026
CITY OF NY DEPT OF DESIGN C403/21/2026
NYC DEPT OF DESIGN CONSTRUCT303/21/2026
DEPT OF GENERAL SERVICES803/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
URBAHN ARCHITECTS206/23/2026
LAKHANI & JORDAN208/15/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ARCHETYPE CONSULTANTS603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PADILLA CONSTRUCTION SERVICESGeneral Contractor406/28/2026
LORD, JOHNElectrical203/21/2026
JOHNSEN, WARRENElectrical203/21/2026
G V PLBG & HTG CORPElectrical103/21/2026
CIOFFI, JOHNElectrical103/21/2026
MULLIN, NEILElectrical103/21/2026
PERONE, RALPHElectrical103/21/2026
WINDLE, DElectrical103/21/2026
LLANOS, CARLOSElectrical103/21/2026
DIMITRIOS TOMBORISElectrical103/21/2026
FRANK MERESHENSKYElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
TECTONIC ENGINEERING CONS106406/23/2026
Building Lifecycle
All (78)Filed (4)Permit Issued (3)Violation (41)Special Inspection (30)
06/24/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
GEORGE GHEBRYAL
06/24/2026
Special inspection requirement — Fire-Resistance Rated Construction
GEORGE GHEBRYAL
06/24/2026
Special inspection requirement — Lighting controls
GEORGE GHEBRYAL
06/24/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
GEORGE GHEBRYAL
06/24/2026
Special inspection requirement — Fenestration air leakage
GEORGE GHEBRYAL
06/24/2026
Special inspection requirement — Interior lighting power
GEORGE GHEBRYAL
06/24/2026
Special inspection requirement — Air barrier - visual inspection
GEORGE GHEBRYAL
06/24/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
GEORGE GHEBRYAL
06/24/2026
Special inspection requirement — Energy Code Compliance Inspections
GEORGE GHEBRYAL
06/24/2026
Special inspection requirement — Final
GEORGE GHEBRYAL
06/24/2026
Special inspection requirement — Insulation placement and R values
GEORGE GHEBRYAL
06/23/2026
Filed — Alteration
General construction alterations on the 1st floor & cellar level for proposed upgrades to existing locker rooms and restrooms; related work as per plans. No proposed change in building use, egress, or occupancy.
X00764827-P2
05/14/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
GEORGE GHEBRYAL
05/14/2026
Special inspection requirement — Interior lighting power
GEORGE GHEBRYAL
05/14/2026
Special inspection requirement — Lighting controls
GEORGE GHEBRYAL
05/14/2026
Special inspection requirement — Air barrier - visual inspection
GEORGE GHEBRYAL
05/14/2026
Special inspection requirement — Fenestration air leakage
GEORGE GHEBRYAL
05/14/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
GEORGE GHEBRYAL
05/14/2026
Special inspection requirement — Insulation placement and R values
GEORGE GHEBRYAL
05/14/2026
Special inspection requirement — Fire-Resistance Rated Construction
GEORGE GHEBRYAL
05/14/2026
Special inspection requirement — Final
GEORGE GHEBRYAL
05/14/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
GEORGE GHEBRYAL
05/14/2026
Special inspection requirement — Energy Code Compliance Inspections
GEORGE GHEBRYAL
08/22/2025
Permit issued — General Construction
X00764827-I1-GC
07/07/2025
Violation issued (FDNY_ORDER, closed)
07/07/2025
Violation issued (FDNY_ORDER, closed)
05/07/2025
Violation issued (FDNY_ORDER, closed)
05/07/2025
Violation issued (FDNY_ORDER, closed)
05/07/2025
Violation issued (FDNY_ORDER, closed)
05/07/2025
Violation issued (FDNY_ORDER, closed)
10/17/2023
Permit issued — General Construction
X00764827-I1-GC
11/15/2022
Permit issued — General Construction
X00764827-I1-GC
08/15/2022
Filed — Alteration
General construction alterations on the 1st floor & cellar level for proposed upgrades to existing locker rooms and restrooms; related work as per plans. No proposed change in building use, egress, or occupancy.
X00764827-S2
08/11/2022
Special inspection requirement — Sprinkler Systems
GEORGE GHEBRYAL
08/04/2022
Filed — Alteration
General construction alterations on the 1st floor & cellar level for proposed upgrades to existing locker rooms and restrooms; related work as per plans. No proposed change in building use, egress, or occupancy.
X00764827-S1
08/03/2022
Special inspection requirement — Duct leakage testing, insulation and design
GEORGE GHEBRYAL
08/03/2022
Special inspection requirement — Maintenance information
GEORGE GHEBRYAL
08/03/2022
Special inspection requirement — Shutoff dampers
GEORGE GHEBRYAL
08/03/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
GEORGE GHEBRYAL
08/03/2022
Special inspection requirement — HVAC-R and service water heating equipment
GEORGE GHEBRYAL
08/03/2022
Special inspection requirement — HVAC-R and service water heating system controls
GEORGE GHEBRYAL
08/03/2022
Special inspection requirement — Electrical motors and elevators
GEORGE GHEBRYAL
07/08/2022
Filed — Alteration
General construction alterations on the 1st floor & cellar level for proposed upgrades to existing locker rooms and restrooms; related work as per plans. No proposed change in building use, egress, or occupancy.
X00764827-I1
10/02/2018
Violation issued (ECB, closed)
Elevators
10/02/2018
Violation issued (ECB, closed)
Elevators
10/02/2018
Violation issued (ECB, closed)
Elevators
10/02/2018
Violation issued (ECB, closed)
Elevators
09/12/2017
Violation issued (ECB, closed)
Elevators
09/12/2017
Violation issued (ECB, closed)
Elevators
09/12/2017
Violation issued (ECB, closed)
Elevators
09/12/2017
Violation issued (ECB, closed)
Elevators
09/12/2017
Violation issued (ECB, closed)
Elevators
01/13/2015
Violation issued (ECB, closed)
Elevators
01/13/2015
Violation issued (ECB, closed)
Elevators
01/13/2015
Violation issued (ECB, closed)
Elevators
01/13/2015
Violation issued (ECB, closed)
Elevators
01/13/2015
Violation issued (ECB, closed)
Elevators
01/13/2015
Violation issued (ECB, closed)
Elevators
01/13/2015
Violation issued (ECB, closed)
Elevators
01/13/2015
Violation issued (ECB, closed)
Elevators
Latest 60 of 78 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedPADILLA CONSTRUCTION SERVICES08/22/2025
DOB NOWGeneral ConstructionPermit IssuedPADILLA CONSTRUCTION SERVICES10/17/2023
DOB NOWGeneral ConstructionPermit IssuedPADILLA CONSTRUCTION SERVICES11/15/2022
BISOTISSUEDA.B.C.D. CONSTRUCTION COR07/30/2020
BISOTISSUEDA.B.C.D. CONSTRUCTION COR10/01/2019
BISOTISSUEDAWL INDUSTRIES INC06/10/2019
BISMHISSUEDAWL INDUSTRIES INC05/22/2019
BISOTISSUEDA.B.C.D. CONSTRUCTION COR10/24/2018
BISOTISSUEDCOMMERCE ELECTRICAL CONTR03/29/2018
BISOTISSUEDFRITCH CONSTRUCTION CO.IN01/10/2018
BISPLISSUEDEAGLE 1 MECHANICAL, INC11/20/2017
BISOTISSUEDA.B.C.D. CONSTRUCTION COR09/20/2017
BISSPISSUEDGRINNELL LLC08/29/2017
BISOTISSUEDA.B.C.D. CONSTRUCTION COR07/27/2017
BISOTISSUEDFRITCH CONSTRUCTION CO.IN06/06/2017
BISOTISSUEDSEA BREEZE GENERAL CONSTR06/02/2017
BISPLISSUEDEAGLE 1 MECHANICAL, INC11/18/2016
BISOTISSUEDFRITCH CONSTRUCTION CO.IN11/02/2016
BISOTISSUEDSEA BREEZE GENERAL CONSTR10/21/2016
BISSPISSUEDGRINNELL LLC01/25/2016
BISMHISSUEDCRESCENT CONTRACTING CORP02/03/2015
BISMHISSUEDCRESCENT CONTRACTING CORP02/03/2015
BISSPISSUEDGRINNELL LLC01/29/2015
BISMHISSUEDCRESCENT CONTRACTING CORP02/03/2014
BISSPISSUEDGRINNELL LLC01/14/2014
BISMHISSUEDCRESCENT CONTRACTING CORP01/13/2014
BISMHISSUEDCRESCENT CONTRACTING CORP01/13/2014
BISMHISSUEDCRESCENT CONTRACTING CORP01/13/2014
BISMHISSUEDCRESCENT CONTRACTING CORP01/13/2014
BISPLISSUEDCRESCENT CONTRG CORP12/31/2013
BISMHISSUEDAWL INDUSTRIES INC07/02/2013
BISSPISSUEDGRINNELL LLC12/18/2012
BISPLISSUEDCRESCENT CONTRG CORP09/24/2012
BISMHISSUEDCRESCENT CONTRACTING CORP09/24/2012
BISMHISSUEDAWL INDUSTRIES INC06/15/2012
BISMHISSUEDCRESCENT CONTRACTING CORP06/13/2012
BISPLISSUEDCRESCENT CONTRG CORP06/13/2012
BISSPISSUEDGRINNELL LLC09/28/2011
BISMHISSUEDAWL INDUSTRIES INC06/20/2011
BISPLISSUEDCHARLES A. DIMINO INC05/03/2010
+ 13 more permits on file
1 project · most recent 06/23/2026
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
06/23/2026Permit IssuedPADILLA CONSTRUCTION SERVAir Conditioning Systems
Cooling
Mitsubishi Electric PUHY-P144TNU-A(-BS) 144,000 BTU · Vrf Outdoor ×9
PUHY-EP192TNU-A 240,000 BTU · Vrf Outdoor ×7
Aaon RN-006 62,400 BTU · Doas ×2
RN-007 73,200 BTU · Doas ×1
RN-010 115,700 BTU · Doas ×1
RQ-003 33,400 BTU · Rooftop Unit ×1
1 project · most recent 06/23/2026
Sprinkler System
FiledStatusContractorScope
06/23/2026——Sprinkler System
1 project · most recent 06/23/2026
Water/Sanitary
FiledStatusContractorScope
06/23/2026——Water/Sanitary
▾Special Inspection Requirements (DOB NOW) — 32
DateRequirementInspectorRole
06/24/2026Exterior Insulation and Finish Systems (EIFS)GEORGE GHEBRYALspecial
06/24/2026Fire-Resistance Rated ConstructionGEORGE GHEBRYALprogress
06/24/2026Lighting controlsGEORGE GHEBRYALenergy_progress
06/24/2026Fenestration and door U-factor and product ratingsGEORGE GHEBRYALenergy_progress
06/24/2026Fenestration air leakageGEORGE GHEBRYALenergy_progress
06/24/2026Interior lighting powerGEORGE GHEBRYALenergy_progress
06/24/2026Air barrier - visual inspectionGEORGE GHEBRYALenergy_progress
06/24/2026Fire-Resistant Penetrations and JointsGEORGE GHEBRYALspecial
06/24/2026Energy Code Compliance InspectionsGEORGE GHEBRYALprogress
06/24/2026FinalGEORGE GHEBRYALprogress
06/24/2026Insulation placement and R valuesGEORGE GHEBRYALenergy_progress
05/14/2026Fire-Resistant Penetrations and JointsGEORGE GHEBRYALspecial
05/14/2026Interior lighting powerGEORGE GHEBRYALenergy_progress
05/14/2026Lighting controlsGEORGE GHEBRYALenergy_progress
05/14/2026Air barrier - visual inspectionGEORGE GHEBRYALenergy_progress
05/14/2026Fenestration air leakageGEORGE GHEBRYALenergy_progress
05/14/2026Fenestration and door U-factor and product ratingsGEORGE GHEBRYALenergy_progress
05/14/2026Insulation placement and R valuesGEORGE GHEBRYALenergy_progress
05/14/2026Fire-Resistance Rated ConstructionGEORGE GHEBRYALprogress
05/14/2026FinalGEORGE GHEBRYALprogress
05/14/2026Exterior Insulation and Finish Systems (EIFS)GEORGE GHEBRYALspecial
05/14/2026Energy Code Compliance InspectionsGEORGE GHEBRYALprogress
08/11/2022Sprinkler SystemsGEORGE GHEBRYALspecial
08/03/2022Duct leakage testing, insulation and designGEORGE GHEBRYALenergy_progress
08/03/2022Maintenance informationGEORGE GHEBRYALenergy_progress
Latest 25 of 32.
▾Documents — 437 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/24/2026X00764827-S2Request digital key ↗
08/24/2026X00764827-S1Request digital key ↗
08/24/2026X00764827-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits82
▸BISWORK PERMIT APPLICATION44
05/23/2019220698644Open ↗
05/23/2019220698644Open ↗
10/25/2018440398516Open ↗
Showing 3 of 44 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION38
12/13/2019220553880Open ↗
12/10/2019220553880Open ↗
09/17/2019220714804Open ↗
Showing 3 of 38 on file for this type
▸Seals & Professional Certifications110
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION52
09/17/2019220714804Open ↗
09/17/2019220714804Open ↗
04/18/2019220698644Open ↗
Showing 3 of 52 on file for this type
▸DOB NOWProgress Inspector Seal & Signature26
09/12/2026X00764827-S1Open ↗
09/12/2026X00764827-S1Open ↗
09/12/2026X00764827-S1Open ↗
Showing 3 of 26 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT9
09/17/2019220714804Open ↗
04/18/2019220698644Open ↗
06/14/2018421637731Open ↗
Showing 3 of 9 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST8
09/17/2019220714804Open ↗
04/18/2019220698644Open ↗
06/14/2018421637731Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/12/2026X00764827-S1Open ↗
09/02/2026X00764827-S2Open ↗
09/01/2026X00764827-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/24/2026X00764827-S2Open ↗
08/24/2026X00764827-S1Open ↗
08/24/2026X00764827-I1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
01/09/2018440455945Open ↗
05/03/2017440398516Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
01/09/2018440455945Open ↗
05/03/2017440398516Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment27
▸BISSCHEDULE B - PLUMBING11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸BISSELF-CERT PLUMBING NOTICE10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
12/13/2019220553880Open ↗
10/03/2016220553880Open ↗
09/09/2016220549280Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT3
11/28/2016220562004Open ↗
09/29/2016220552952Open ↗
09/29/2016220552952Open ↗
▸Safety & Tenant Protection1
▸BISSTREET TREE CHECKLIST1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos38
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'21
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 21 on file for this type
▸BISASBESTOS-CERTIFICATION (DEP ACP5)12
11/28/2016220562004Open ↗
10/03/2016220553880Open ↗
09/29/2016220552952Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/24/2026X00764827-S1Open ↗
08/24/2026X00764827-I1Open ↗
08/24/2026X00764827-S2Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
05/03/2017440398516Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance50
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS29
04/18/2019220698644Open ↗
04/18/2019220698644Open ↗
06/14/2018421637731Open ↗
Showing 3 of 29 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS6
03/16/2021440398516Open ↗
06/06/2017220131596Open ↗
01/26/2017220131603Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
03/16/2021440398516Open ↗
01/09/2018440455945Open ↗
07/27/2017440398516Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: ENERGY3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTR8: Energy Code Progress Inspections2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
01/09/2018440455945Open ↗
05/03/2017440398516Open ↗
▸BISNYCECC ANALYSIS2
01/09/2018440455945Open ↗
05/03/2017440398516Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
05/03/2017440398516Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
05/03/2017440398516Open ↗
▸Inspections & Test Reports12
▸BISTECHNICAL REPORT: RESPONSIBILITY6
03/16/2021440398516Open ↗
03/16/2021440398516Open ↗
01/09/2018440455945Open ↗
Showing 3 of 6 on file for this type
▸BISHYDRAULIC FLOW CALCULATIONS3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
05/03/2017440398516Open ↗
▸BISMASONRY1
05/03/2017440398516Open ↗
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
05/03/2017440398516Open ↗
▸Approvals, Objections & Sign-offs57
▸BISADMINISTRATIVE OBJECTIONS16
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 16 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION14
09/18/2019220714804Open ↗
09/17/2019220714804Open ↗
04/18/2019220698644Open ↗
Showing 3 of 14 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST13
06/06/2017220131596Open ↗
05/30/2017220136797Open ↗
05/26/2017220131523Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)5
08/24/2026X00764827-P2Open ↗
08/13/2026X00764827-S1Open ↗
08/13/2026X00764827-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter4
08/24/2026X00764827-S1Open ↗
08/24/2026X00764827-I1Open ↗
08/24/2026X00764827-P2Open ↗
Showing 3 of 4 on file for this type
▸BISDESIGN COMM. APPROVAL: CITY-OWNED PROPERTY (EXTERIOR WORK)2
01/09/2018440455945Open ↗
05/03/2017440398516Open ↗
▸BISCONSTRUCTION CODE DETERMINATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISDESIGN COMM. SIGNOFF: CITY-OWNED PROPERTY (EXTERIOR WORK)1
03/16/2021440398516Open ↗
▸BISFINAL1
05/03/2017440398516Open ↗
▸Cost, Insurance & Ownership32
▸BISCOST AFFIDAVIT32
03/16/2021440398516Open ↗
09/17/2019220714804Open ↗
04/18/2019220698644Open ↗
Showing 3 of 32 on file for this type
▸Filing & Intake Forms22
▸BISEFILING COVER SHEET11
09/17/2019220714804Open ↗
04/18/2019220698644Open ↗
06/14/2018421637731Open ↗
Showing 3 of 11 on file for this type
▸BISADDITIONAL INFORMATION7
11/04/2019220714804Open ↗
07/08/2019220698644Open ↗
07/05/2019220698644Open ↗
Showing 3 of 7 on file for this type
▸BISBOROUGH INTAKE FORM2
12/10/2019220553880Open ↗
07/05/2019220698644Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET2
01/09/2018440455945Open ↗
05/03/2017440398516Open ↗
▸Other Documents2
▸BISOP-129 INTERNAL (SECONDARY) BACKFLOW PREVENTION DEVICE TEST REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISFEE EXEMPTION DOCUMENTATION1
05/03/2017440398516Open ↗