Two family frame · 4,563 sf lot · 0.63 FAR built · Flood zone X500
Locations of Work
ArchitectureElectricalGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofAs built PV solar system1p · 1 filing · 12 docs
Floor 2As built PV solar system1p · 1 filing · 12 docs
Floor 1
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Trinity Solar205/28/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Aca Associates203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Trinity Solarspecialty_contractor303/21/2026
Oml BuildingGeneral Contractor203/21/2026
B R Harry ConstructionGeneral Contractor203/21/2026
Redline ElectricElectrical203/22/2026
Advanced Piping ServicesPlumbing110/02/2003
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Jay Kavi8500205/28/2025
Building Lifecycle
06/16/2025
Signed off — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01045739-I1
05/28/2025
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Q01045739-P1
05/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jay Kavi
05/28/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Jay Kavi
05/28/2025
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
9 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offTrinity Solar05/10/2024
BIS—ISSUEDB&R Harry Construction04/13/2004
BISEQISSUEDB&R Harry Construction04/13/2004
BISPLISSUEDZara Plumbing10/02/2003
BISEQISSUEDB&R Harry Construction09/05/2003
BIS—ISSUEDB&R Harry Construction09/05/2003
BIS—ISSUEDO.M.L. Building02/28/2003
BISEQISSUEDO.M.L. Building02/19/2003
BIS—ISSUEDO.M.L. Building11/15/2002
1 project · most recent 04/10/2024
FiledStatusContractorScope
04/10/2024CompleteRedline Electric—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
05/28/2025Fire-Resistant Penetrations and JointsJay Kavispecial
05/28/2025Structural Stability – Alterations of existing buildingsJay Kavispecial
05/28/2025Energy Code Compliance InspectionsAyracon Almarazprogress
05/28/2025FinalAyracon Almarazprogress
05/28/2025Air barrier - visual inspectionAyracon Almarazenergy_progress