← Back
BuildNYC
Primarily 2 family with 1 store or office
10-41 47TH AVENUE
QUEENS · BIN 4000357
💬 Discuss this project
1910Year Built
3Stories
S2Building Class
M1-4/R6BZoning
—Gross Floor Area
3Units
0 Active ViolationsFDNY Report ↗
Primarily 2 family with 1 store or office · Owner of record: Jenkins Property Holdings · 1.83 FAR built · Flood zone X500
Locations of Work
ArchitectureMechanicalGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofBuka Derm ManagementUnder Construction3p · 1 filing · 20 docs
Floor 1Buka Derm ManagementUnder Construction4p · 1 filing · 20 docs
CellarBuka Derm ManagementUnder Construction12p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Jenkins Property Holdings3410/13/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Dka Consulting209/14/2026
Judge Architecture208/26/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
HNL Construction CompanyGeneral Contractor109/23/2026
Signa DevelopmentGeneral Contractor109/16/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Dka Consulting3150209/14/2026
Judge Architecture748409/14/2026
Building Lifecycle
All (49)Filed (4)Permit Issued (2)Violation (13)Special Inspection (30)
09/22/2026
Permit issued — Mechanical Systems
Q01430221-S1-MS
09/15/2026
Permit issued — General Construction
Q01430221-I1-GC
09/14/2026
Filed — Alteration
New Split system Heat Pump @ roof with new condensing units @ cellar
Q01430221-P2
09/08/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Damon Amadio
09/08/2026
Special inspection requirement — Shutoff dampers
Damon Amadio
09/08/2026
Special inspection requirement — HVAC-R and service water heating system controls
Damon Amadio
09/08/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Rachael Judge
09/08/2026
Special inspection requirement — Mechanical Systems
Damon Amadio
09/08/2026
Special inspection requirement — Tenant Protection Plan Compliance
Rachael Judge
09/08/2026
Special inspection requirement — Energy Code Compliance Inspections
Damon Amadio
09/08/2026
Special inspection requirement — Final
Damon Amadio
09/08/2026
Special inspection requirement — HVAC-R and service water heating equipment
Damon Amadio
09/08/2026
Special inspection requirement — Duct leakage testing, insulation and design
Damon Amadio
09/08/2026
Special inspection requirement — Maintenance information
Damon Amadio
08/26/2026
Filed — Alteration
New Split system Heat Pump @ roof with new condensing units @ cellar
Q01430221-P1
08/24/2026
Special inspection requirement — Tenant Protection Plan Compliance
Rachael Judge
08/24/2026
Special inspection requirement — Post-installed Anchors
Rachael Judge
08/24/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Rachael Judge
08/24/2026
Special inspection requirement — Energy Code Compliance Inspections
Rachael Judge
08/24/2026
Special inspection requirement — Final
Rachael Judge
08/24/2026
Special inspection requirement — Fire-Resistance Rated Construction
Rachael Judge
08/24/2026
Special inspection requirement — Interior lighting power
Rachael Judge
08/24/2026
Special inspection requirement — Lighting controls
Rachael Judge
08/17/2026
Filed — Alteration
New Split system Heat Pump @ roof with new condensing units @ cellar
Q01430221-S1
08/17/2026
Filed — Alteration
New Split system Heat Pump @ roof with new condensing units @ cellar
Q01430221-I1
07/30/2026
Special inspection requirement — Lighting controls
Rachael Judge
07/30/2026
Special inspection requirement — Mechanical Systems
Damon Amadio
07/30/2026
Special inspection requirement — Tenant Protection Plan Compliance
Rachael Judge
07/30/2026
Special inspection requirement — Final
Damon Amadio
07/30/2026
Special inspection requirement — Energy Code Compliance Inspections
Damon Amadio
07/30/2026
Special inspection requirement — HVAC-R and service water heating system controls
Damon Amadio
07/30/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Damon Amadio
07/30/2026
Special inspection requirement — Duct leakage testing, insulation and design
Damon Amadio
07/30/2026
Special inspection requirement — Maintenance information
Damon Amadio
07/30/2026
Special inspection requirement — Shutoff dampers
Damon Amadio
07/30/2026
Special inspection requirement — HVAC-R and service water heating equipment
Damon Amadio
11/08/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/06/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/24/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/24/2017
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/01/2015
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/01/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/01/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/01/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/01/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
07/13/2005
Violation issued (ECB, closed)
Construction
05/16/2005
Violation issued (ECB, closed)
Construction
04/07/2005
Violation issued (ECB, closed)
Construction
05/16/1995
Violation issued (FDNY_NOV, closed)
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedHNL Construction Company09/22/2026
DOB NOWGeneral ConstructionPermit IssuedSigna Development09/15/2026
BISSPISSUEDQMB Plumbing & Heating06/18/2021
BISSPISSUEDRRP Plumbing06/06/2017
BISPLISSUEDRRP Plumbing06/01/2017
BIS—ISSUEDTeng Fei Construction05/30/2017
BISOTISSUEDTeng Fei Construction04/14/2017
BISOTISSUEDCustom Interiors Renovation04/02/2015
BISPLISSUEDEnobrac Plumbing02/11/2013
BISBLISSUEDEnobrac Plumbing02/11/2013
BISMHISSUEDD&E Refrigeration & Air09/25/2012
BISPLISSUEDGenesis Plumbing and Heating07/11/2012
BIS—ISSUEDCustom Interiors06/17/2011
BISPLISSUEDGenesis Plumbing and Heating04/25/2011
BIS—ISSUEDCustom Interiors04/08/2011
BISOTISSUEDN/A10/26/2005
BISOTISSUEDUnited Pak Construction08/09/2005
BISEQISSUEDOutdoor Installation05/27/2005
BISEQISSUEDOutdoor Installation05/27/2005
BISPLISSUEDBent Mechanical03/18/1999
BISOTISSUEDNA02/19/1999
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 38
DateRequirementInspectorRole
09/08/2026HVAC-R and service water piping design and insulationDamon Amadioenergy_progress
09/08/2026Shutoff dampersDamon Amadioenergy_progress
09/08/2026HVAC-R and service water heating system controlsDamon Amadioenergy_progress
09/08/2026Fire-Resistant Penetrations and JointsRachael Judgespecial
09/08/2026Mechanical SystemsDamon Amadiospecial
09/08/2026Tenant Protection Plan ComplianceRachael Judgespecial
09/08/2026Energy Code Compliance InspectionsDamon Amadioprogress
09/08/2026FinalDamon Amadioprogress
09/08/2026HVAC-R and service water heating equipmentDamon Amadioenergy_progress
09/08/2026Duct leakage testing, insulation and designDamon Amadioenergy_progress
09/08/2026Maintenance informationDamon Amadioenergy_progress
08/24/2026Tenant Protection Plan ComplianceRachael Judgespecial
08/24/2026Post-installed AnchorsRachael Judgespecial
08/24/2026Fire-Resistant Penetrations and JointsRachael Judgespecial
08/24/2026Energy Code Compliance InspectionsRachael Judgeprogress
08/24/2026FinalRachael Judgeprogress
08/24/2026Fire-Resistance Rated ConstructionRachael Judgeprogress
08/24/2026Interior lighting powerRachael Judgeenergy_progress
08/24/2026Lighting controlsRachael Judgeenergy_progress
07/30/2026Lighting controlsRachael Judgeenergy_progress
07/30/2026Mechanical SystemsDamon Amadiospecial
07/30/2026Tenant Protection Plan ComplianceRachael Judgespecial
07/30/2026FinalDamon Amadioprogress
07/30/2026Energy Code Compliance InspectionsDamon Amadioprogress
07/30/2026HVAC-R and service water heating system controlsDamon Amadioenergy_progress
Latest 25 of 38.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Buka Derm ManagementMedical / HealthcareCellar, Floor 1, Roof
Project Q01430221 Alteration · Permit Entire · 08/17/2026
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 150 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/18/2026Q01430221-S1Request digital key ↗
08/18/2026Q01430221-I1Request digital key ↗
▸Applications & Permits22
▸BISPLAN / WORK APPROVAL APPLICATION12
12/05/2022421469495Open ↗
07/22/2021440397802Open ↗
06/21/2017421469495Open ↗
Showing 3 of 12 on file for this type
▸BISWORK PERMIT APPLICATION8
09/20/2021440397802Open ↗
06/07/2017421468003Open ↗
06/06/2017440397802Open ↗
Showing 3 of 8 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
09/27/2017421468003Open ↗
▸BISBPP-15 - Application for waiver of Builders pavement requirements1
06/05/2017421468003Open ↗
▸Zoning, Tax Lot & Property Records2
▸BISVERIFY TAX LOT1
11/01/2023421468003Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
04/28/2023421468003Open ↗
▸Seals & Professional Certifications43
▸DOB NOWProgress Inspector Seal & Signature11
09/23/2026Q01430221-P2Open ↗
09/23/2026Q01430221-P2Open ↗
09/23/2026Q01430221-P2Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/23/2026Q01430221-P2Open ↗
09/23/2026Q01430221-P2Open ↗
09/23/2026Q01430221-P2Open ↗
Showing 3 of 9 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION8
11/15/2017440397802Open ↗
11/15/2017440397802Open ↗
10/28/2017421468003Open ↗
Showing 3 of 8 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
04/14/2017421468003Open ↗
04/13/2017440398035Open ↗
04/13/2017440397802Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
09/26/2026Q01430221-P1Open ↗
09/26/2026Q01430221-P2Open ↗
08/18/2026Q01430221-S1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
04/13/2017440398035Open ↗
04/13/2017440397802Open ↗
04/01/2015440210497Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
04/13/2017440398035Open ↗
04/13/2017440397802Open ↗
04/01/2015440210497Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
04/14/2017421468003Open ↗
▸Trade Schedules & Equipment13
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT6
03/15/2013420789908Open ↗
03/15/2013420789908Open ↗
01/28/2013420789908Open ↗
Showing 3 of 6 on file for this type
▸BISSCHEDULE B - PLUMBING2
04/13/2017440397802Open ↗
01/09/2013420789908Open ↗
▸BISSELF-CERT PLUMBING NOTICE1
04/29/2013420789908Open ↗
▸BISFIRE ALARM: FDNY RECEIVED & ACCEPTED PLANS1
10/14/2022421469495Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
09/22/2022421469495Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
04/14/2017421468003Open ↗
▸BISBOILERS - SUPPORTING DOCUMENTATION1
04/29/2013420789908Open ↗
▸Safety & Tenant Protection5
▸BISTENANT PROTECTION PLAN AND NOTES3
04/13/2017440398035Open ↗
04/13/2017440397802Open ↗
04/14/2017421468003Open ↗
▸BISSTREET TREE CHECKLIST1
04/14/2017421468003Open ↗
▸BISSTREET TREE SIGNOFF1
03/19/2023421468003Open ↗
▸Environmental & Asbestos10
▸BISASBESTOS: CERTIFICATION (DEP ACP5)5
04/14/2017421468003Open ↗
04/13/2017440398035Open ↗
04/13/2017440397802Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
09/26/2026Q01430221-P2Open ↗
09/26/2026Q01430221-P1Open ↗
08/18/2026Q01430221-S1Open ↗
Showing 3 of 4 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
01/09/2013420789908Open ↗
▸Energy Compliance11
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS6
10/28/2017421468003Open ↗
04/14/2017421468003Open ↗
07/14/2015440210497Open ↗
Showing 3 of 6 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
10/28/2017421468003Open ↗
07/02/2015440210497Open ↗
05/06/2013420789908Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
04/01/2015440210497Open ↗
▸BISTR8: Energy Code Progress Inspections1
05/10/2013420789908Open ↗
▸Inspections & Test Reports4
▸BISTECHNICAL REPORT: RESPONSIBILITY4
06/05/2023421468003Open ↗
04/13/2017440398035Open ↗
04/13/2017440397802Open ↗
Showing 3 of 4 on file for this type
▸Approvals, Objections & Sign-offs14
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST6
10/18/2022421469495Open ↗
05/16/2022440397802Open ↗
11/17/2017440398035Open ↗
Showing 3 of 6 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
10/17/2017440398035Open ↗
04/13/2017440398035Open ↗
05/10/2013420789908Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE2
05/08/2017421468003Open ↗
04/14/2017421468003Open ↗
▸BISSUPERSEDING LETTER1
09/20/2021440397802Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
01/09/2013420789908Open ↗
▸Cost, Insurance & Ownership12
▸BISCOST AFFIDAVIT10
11/17/2017440398035Open ↗
10/28/2017421468003Open ↗
10/17/2017440398035Open ↗
Showing 3 of 10 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
10/13/2022421469495Open ↗
05/12/2022440397802Open ↗
▸Filing & Intake Forms10
▸BISEFILING JOB APPLICATION COVER SHEET4
04/13/2017440398035Open ↗
04/13/2017440397802Open ↗
04/01/2015440210497Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM3
09/20/2021440397802Open ↗
11/17/2017440398035Open ↗
09/27/2017421468003Open ↗
▸BISEFILING COVER SHEET2
04/25/2017421469495Open ↗
04/14/2017421468003Open ↗
▸BISADDITIONAL INFORMATION1
05/12/2023421468003Open ↗
▸Other Documents2
▸BISPLOT DIAGRAM2
05/08/2017421468003Open ↗
04/14/2017421468003Open ↗