| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/23/2026 | Permit Issued | DE LUX CONSTRUCTION INC | Heating and Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/23/2026 | Signed-off | EXPERT FIRE SPRINKLER,LLC | 35 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/23/2026 | Permit Issued | NEW PHASE PLUMBING & HEAT | Water/Sanitary |
| 07/14/2026 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/20/2026 | Permit Issued | A ELECTRICAL MAIN SVC INC | — |
| 07/07/2026 | Permit Issued | KJK ELECTRIC INC | General Wiring |
| 09/19/2025 | Permit Issued | AMBER ELECTL CONTNG INC | General Wiring |
| 05/01/2025 | Complete | ZIP ELECTRIC INC | General Wiring |
| 11/04/2024 | Permit Issued | E & M ELECTRICAL NY CORP | General Wiring |
| 06/10/2024 | Complete | LIVE WIRE ELECTRIC 1 LLC | General Wiring |
| 05/31/2024 | Complete | GLENDALE ELECTL CONTNG IN | General Wiring |
| 05/11/2024 | Complete | R-2 ELECTRIC INC | General Wiring |
| 08/16/2023 | Complete | DELTA PHASE ELEC'L CORP. | General Wiring |
| 06/28/2023 | Complete | DELTA PHASE ELEC'L CORP. | — |
| 01/09/2023 | Complete | AP ELECTL SER & MAIN INC | General Wiring |
| 09/29/2022 | Complete | KNIGHT ELEC'L SERV. CORP. | General Wiring |
| 09/29/2022 | Complete | KNIGHT ELEC'L SERV. CORP. | General Wiring |
| 09/29/2022 | Complete | KNIGHT ELEC'L SERV. CORP. | General Wiring |
| 09/06/2022 | Complete | EIS ELECTRIC CORP DBA | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/20/2026 | Permit Issued | BR CONSTRUCTION GROUP INC | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/21/2024 | Permit Issued | — | — |
| Owner | Filings | Most Recent |
|---|---|---|
| 515 WEST 18TH STREET CONDOMINIUM | 73 | 09/09/2026 |
| 18TH HIGHLINE ASSOCIATES, LLC | 114 | 07/08/2026 |
| RELATED MANAGEMENT COMPANY | 3 | 04/09/2026 |
| BABA CONSTRUCTION CORP. | 5 | 03/22/2026 |
| FLO RESTORATION INC | 5 | 03/22/2026 |
| INTEGRATED PROJECT DELIVERY PARTNER | 1 | 03/22/2026 |
| 515 WEST 18TH STREET UNIT 2201 LLC | 1 | 03/22/2026 |
| COLGATE ENTERPRISE | 2 | 03/21/2026 |
| 18TH STREET HIGHLINE ASSOCIATES | 4 | 03/21/2026 |
| SOMATIC REALTY | 10 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| IW ARCHITECTURE, PLLC | 1 | 08/04/2026 |
| CQ&J CORPORATION | 6 | 07/23/2026 |
| AZSK ARCHITECTS PC | 2 | 07/14/2026 |
| FERGUSON & SHAMAMIAN ARCHITECTS | 1 | 03/13/2026 |
| MOJO STUMER ASSOCIATES, P.C. | 1 | 02/20/2026 |
| ROBERT PROFFITT | 1 | 12/15/2025 |
| RANDALL P. COLLINS ARCHITECT, PC | 1 | 05/07/2025 |
| MICHAEL WAECHTER | 2 | 01/09/2025 |
| COLOMBO ARCHITECTURAL STUDIO PC | 4 | 11/21/2024 |
| NDKAZALAS ARCHITECTURE P.C. | 6 | 09/05/2024 |
| CHARLES G. MICHEL ENGINEERING, PC. | 5 | 02/29/2024 |
| PIER FINE ASSOCIATES | 2 | 02/27/2024 |
| MCALPINE ASSOCIATES ARCHITECTS PC | 10 | 12/28/2023 |
| SIDERIS KEFALAS ENGINEERS PC | 3 | 08/03/2023 |
| RONALD VILLANO ARCHITECT PC | 1 | 03/02/2023 |
| DEREK ZIEMER ARCHITECTURE, PLLC | 2 | 02/08/2023 |
| JEFFREY FLANIGAN, ARCHITECT | 1 | 10/06/2022 |
| DESIMONE CONSULTING ENGINEERS | 3 | 07/20/2022 |
| GC ENG & ASSOCIATES, PC | 7 | 06/16/2022 |
| MICHAEL ZENREICH ARCHITECT PC | 3 | 02/22/2022 |
| KOHN ARCHITECTURE, PLLC | 1 | 10/04/2021 |
| ARCH EXPRESS LLC | 1 | 06/16/2021 |
| IHAB SHAFEI | 1 | 05/18/2021 |
| KENDALL ENGINEERING PC | 1 | 10/22/2019 |
| PCS ENGINEERING | 1 | 12/12/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| RELATED COMPANIES | 7 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 3 | 03/21/2026 |
| J CALLAHAN CONSULTING | 2 | 03/21/2026 |
| A1 EXPEDITING SERVICE CORP. | 1 | 03/21/2026 |
| AGOUTI CONSTRUCTION CONSULTING | 2 | 03/21/2026 |
| NDKAZALAS ARCHITECTURE | 9 | 03/21/2026 |
| CLARKE CONSTRUCTION CONSULTANTS | 7 | 03/21/2026 |
| LLOYD NOEL BUILDING CONSULTANT | 1 | 03/21/2026 |
| DEREK ZIEMER ARCHITECTURE | 14 | 03/21/2026 |
| BOUTIQKEY | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| INTEGRATED PROJECT DELIVE | General Contractor | 23 | 07/08/2026 |
| FLO RESTORATION INC | General Contractor | 9 | 03/21/2026 |
| AIK RENOVATION INC | General Contractor | 8 | 07/08/2026 |
| TERRY DESIGN INC | General Contractor | 7 | 07/08/2026 |
| ROCKLEDGE SCAFFOLD CORP | General Contractor | 5 | 07/08/2026 |
| CGR SYSTEMS MANAGEMENT | General Contractor | 4 | 03/21/2026 |
| V. DISALVO CONTRACTING CO | General Contractor | 4 | 07/08/2026 |
| R.J.C. MECHANICAL CORP | Plumbing | 4 | 07/08/2026 |
| BABA CONSTRUCTION CORP | General Contractor | 4 | 07/08/2026 |
| A + SPRINKLER CORP | Fire Protection | 4 | 07/08/2026 |
| A PLUS PLUMBING CORP | Plumbing | 3 | 07/08/2026 |
| JEM CONTRACTING CORP | General Contractor | 2 | 03/21/2026 |
| NICON BUILD LLC | General Contractor | 2 | 07/08/2026 |
| KNIGHT ELEC'L SERV. CORP. | Electrical | 2 | 03/22/2026 |
| SILVERLINING INTERIORS | General Contractor | 2 | 04/09/2026 |
| WEST VILLAGE GC LLC | General Contractor | 2 | 07/08/2026 |
| DYNAMIC BLUE WATER MECH | Plumbing | 2 | 07/08/2026 |
| DE LUX CONSTRUCTION INC | General Contractor | 2 | 04/09/2026 |
| KBRNY, INC | General Contractor | 2 | 03/21/2026 |
| AMBER ELECTL CONTNG INC | Electrical | 1 | 03/22/2026 |
| CITY SIGNS | Scaffold | 1 | 09/09/2026 |
| ANTONIO TZOUMAS | Electrical | 1 | 03/21/2026 |
| DELTA PHASE ELEC'L CORP. | Electrical | 1 | 03/22/2026 |
| EINSTEIN ELEC'L CORP | Electrical | 1 | 03/22/2026 |
| FOREST BROOK ELEC'L CONTR | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TWIG SPECIAL INSPECTIONS | 885 | 6 | 07/23/2026 |
| ALAN MARGOLIN & ASSOC | 423 | 1 | 03/13/2026 |
| COMPLY BUILDING GROUP | 8622 | 1 | 02/20/2026 |
| MILROSE CONSULTANTS LLC | 2003 | 1 | 05/07/2025 |
| INTEGRITY CONSULTING SERV | 666 | 2 | 01/09/2025 |
| JOSE A SANTOS PE, PC | 3292 | 3 | 11/21/2024 |
| COLOMBO ARCHITECTURAL STU | 4930 | 2 | 11/21/2024 |
| QUALITY TESTING, LLC | 7344 | 7 | 09/05/2024 |
| CHARLES G MICHEL ENGINEER | 2871 | 3 | 02/29/2024 |
| SPECIAL TESTING & CONSULT | 1688 | 16 | 12/28/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sign | Signed-off | CITY SIGNS INC | 09/08/2026 |
| DOB NOW | Structural | Permit Issued | BR CONSTRUCTION GROUP INC | 06/26/2026 |
| DOB NOW | General Construction | Signed-off | V. DISALVO CONTRACTING CO | 04/29/2026 |
| DOB NOW | Structural | Signed-off | V. DISALVO CONTRACTING CO | 04/29/2026 |
| DOB NOW | Sprinklers | Signed-off | EXPERT FIRE SPRINKLER,LLC | 03/31/2026 |
| DOB NOW | General Construction | Permit Issued | DE LUX CONSTRUCTION INC | 02/19/2026 |
| DOB NOW | Plumbing | Permit Issued | TESTERMAN PLBG & HTG INC | 11/26/2025 |
| DOB NOW | General Construction | Signed-off | NICON BUILD LLC | 11/07/2025 |
| DOB NOW | General Construction | Permit Issued | DE LUX CONSTRUCTION INC | 10/30/2025 |
| DOB NOW | General Construction | Signed-off | FLO RESTORATION INC | 12/24/2024 |
| DOB NOW | General Construction | Signed-off | FLO RESTORATION INC | 12/10/2024 |
| DOB NOW | General Construction | Signed-off | SILVERLINING INTERIORS | 09/12/2024 |
| DOB NOW | Mechanical Systems | Signed-off | SILVERLINING INTERIORS | 09/12/2024 |
| DOB NOW | General Construction | Signed-off | BABA CONSTRUCTION CORP | 07/02/2024 |
| DOB NOW | General Construction | Signed-off | QUAD CONTRACTING LLC | 05/31/2024 |
| DOB NOW | Mechanical Systems | Signed-off | AIK RENOVATION INC | 05/06/2024 |
| DOB NOW | General Construction | Signed-off | AIK RENOVATION INC | 05/06/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | TWO-TONE CONTRACTING CORP | 04/03/2024 |
| DOB NOW | Plumbing | Signed-off | DONATO PLUMBING, INC | 03/29/2024 |
| DOB NOW | Mechanical Systems | Signed-off | INTEGRATED PROJECT DELIVE | 08/30/2023 |
| DOB NOW | Mechanical Systems | Signed-off | AIK RENOVATION INC | 08/24/2023 |
| DOB NOW | General Construction | Signed-off | AIK RENOVATION INC | 08/24/2023 |
| DOB NOW | Sprinklers | Signed-off | H M SPRINKLER INC | 08/22/2023 |
| DOB NOW | Plumbing | Signed-off | ARCON PLBG SOLUTIONS | 08/22/2023 |
| DOB NOW | Sprinklers | Signed-off | A PLUS PLUMBING CORP | 06/21/2023 |
| DOB NOW | Plumbing | Signed-off | A + SPRINKLER CORP | 06/21/2023 |
| DOB NOW | General Construction | Signed-off | INTEGRATED PROJECT DELIVE | 06/17/2023 |
| DOB NOW | Plumbing | Signed-off | SUPER PLUMBERS CORP | 05/08/2023 |
| DOB NOW | General Construction | Signed-off | V. DISALVO CONTRACTING CO | 05/04/2023 |
| DOB NOW | General Construction | Signed-off | BABA CONSTRUCTION CORP | 04/06/2023 |
| DOB NOW | General Construction | Signed-off | FLO RESTORATION INC | 03/14/2023 |
| DOB NOW | Plumbing | Signed-off | SUPER PLUMBERS CORP | 01/30/2023 |
| DOB NOW | Structural | Signed-off | TERRY DESIGN INC | 11/29/2022 |
| DOB NOW | Structural | Signed-off | TERRY DESIGN INC | 11/17/2022 |
| DOB NOW | General Construction | Signed-off | TERRY DESIGN INC | 11/11/2022 |
| DOB NOW | Plumbing | Signed-off | R.J.C. MECHANICAL CORP | 09/13/2022 |
| DOB NOW | Plumbing | Signed-off | A PLUS PLUMBING CORP | 07/26/2022 |
| DOB NOW | Sprinklers | Signed-off | A + SPRINKLER CORP | 07/26/2022 |
| DOB NOW | Mechanical Systems | Signed-off | INTEGRATED PROJECT DELIVE | 07/19/2022 |
| DOB NOW | Structural | Signed-off | INTEGRATED PROJECT DELIVE | 06/03/2022 |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/04/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/27/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/16/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/23/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/12/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/07/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/05/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/29/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/28/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/01/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/10/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/22/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/19/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/18/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/10/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/12/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/12/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/10/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/08/2023 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 01/23/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/14/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/14/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/14/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/12/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/12/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/04/2026 | Final | Israel Wertentheil | progress |
| 07/14/2026 | Tenant Protection Plan Compliance | Dave Wall | special |
| 06/05/2026 | Tenant Protection Plan Compliance | — | special |
| 06/04/2026 | Tenant Protection Plan Compliance | Dave Wall | special |
| 06/01/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/01/2026 | Final | — | progress |
| 05/05/2026 | Tenant Protection Plan Compliance | Dave Wall | special |
| 03/03/2026 | Tenant Protection Plan Compliance | Dave Wall | special |
| 03/03/2026 | Sprinkler Systems | Dave Wall | special |
| 01/25/2026 | Energy Code Compliance Inspections | ANA ACCETTA | progress |
| 01/25/2026 | Exterior lighting power | ANA ACCETTA | energy_progress |
| 12/08/2025 | Final | Robert Proffitt | progress |
| 12/08/2025 | Tenant Protection Plan Compliance | — | special |
| 10/30/2025 | Lighting in dwelling units | Young Suh | energy_progress |
| 10/30/2025 | Post-installed Anchors | Young Suh | special |
| 10/13/2025 | Final | Scott Sottile | progress |
| 10/07/2025 | Structural Steel - High Strength Bolting | ANA ACCETTA | special |
| 10/07/2025 | Structural Steel - Welding | ANA ACCETTA | special |
| 10/07/2025 | Fire-Resistant Penetrations and Joints | ANA ACCETTA | special |
| 10/07/2025 | Structural Steel - Details | ANA ACCETTA | special |
| 09/03/2025 | Final | ANA ACCETTA | progress |
| 04/24/2025 | Final | Randall Collins | progress |
| 04/24/2025 | Tenant Protection Plan Compliance | Christopher Drutjons | special |
| 08/28/2024 | Final | KEVIN SNEDEKER | progress |
| 08/28/2024 | Post-installed Anchors | KEVIN SNEDEKER | special |