| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/11/2021 | $2.8M | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| ZPROEKT ARCHITECTURE | 13 | 11/12/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| HM CONSULTING EXPEDITING | 26 | 03/21/2026 |
| AVALON DESIGN | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KADAR ELITE CONSTRUCTION | General Contractor | 15 | 07/08/2026 |
| SAPOL CONSTRUCTION LLC | General Contractor | 2 | 04/09/2026 |
| PFL MECHANICAL CORP | Plumbing | 2 | 07/08/2026 |
| CMY ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MACIA INSPECTION & TESTIN | 402 | 6 | 06/18/2024 |
| JSPECS,INC | 9429 | 2 | 07/14/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | KADAR ELITE CONSTRUCTION | 06/12/2024 |
| DOB NOW | Plumbing | Signed-off | PFL MECHANICAL CORP | 01/30/2024 |
| DOB NOW | Structural | Permit Issued | KADAR ELITE CONSTRUCTION | 10/26/2023 |
| DOB NOW | Structural | Permit Issued | KADAR ELITE CONSTRUCTION | 05/31/2023 |
| DOB NOW | Construction Fence | Signed-off | KADAR ELITE CONSTRUCTION | 05/31/2023 |
| DOB NOW | Construction Fence | Signed-off | KADAR ELITE CONSTRUCTION | 02/06/2023 |
| DOB NOW | Plumbing | Signed-off | PFL MECHANICAL CORP | 03/03/2022 |
| DOB NOW | Construction Fence | Signed-off | KADAR ELITE CONSTRUCTION | 02/26/2022 |
| DOB NOW | Curb Cut | Signed-off | KADAR ELITE CONSTRUCTION | 02/26/2022 |
| DOB NOW | Structural | Signed-off | KADAR ELITE CONSTRUCTION | 02/23/2022 |
| DOB NOW | General Construction | Permit Issued | KADAR ELITE CONSTRUCTION | 02/16/2022 |
| DOB NOW | Earth Work | Signed-off | KADAR ELITE CONSTRUCTION | 02/16/2022 |
| DOB NOW | Mechanical Systems | Signed-off | KADAR ELITE CONSTRUCTION | 02/16/2022 |
| DOB NOW | General Construction | Signed-off | KADAR ELITE CONSTRUCTION | 02/16/2022 |
| DOB NOW | Construction Fence | Signed-off | KADAR ELITE CONSTRUCTION | 02/01/2022 |
| DOB NOW | Construction Fence | Signed-off | LEON D. DEMATTEIS CONSTR | 06/01/2021 |
| DOB NOW | Construction Fence | Signed-off | LEON D. DEMATTEIS CONSTR | 04/07/2021 |
| BIS | — | ISSUED | DYNASTY CONTRACTING LLC | 10/21/2021 |
| BIS | — | ISSUED | HUSIC INC | 10/05/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 11/12/2024 | Permit Issued | KADAR ELITE CONSTRUCTION | Air Conditioning Systems, Associated Ducts and Piping, Heating Systems | Cooling Mitsubishi Electric MXZ−SM60NAM 60,000 BTU · Heat Pump Outdoor ×3 MXZ−4C36NAHZ 36,000 BTU · Heat Pump Outdoor ×16 Heating Ducts & Piping |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/12/2024 | Signed-off | PFL MECHANICAL CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/12/2025 | Complete | CMY ELECTRICAL CORP | General Wiring |
| 03/09/2022 | Complete | CMY ELECTRICAL CORP | 1 meters, 1 new_meters |
| 05/12/2021 | Complete | FALCO ELEC'L SERVICES INC | 1 meters |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/12/2024 | Signed-off | PFL MECHANICAL CORP | Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/12/2024 | Signed-off | PFL MECHANICAL CORP | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/12/2024 | Signed-off | PFL MECHANICAL CORP | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/07/2025 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 02/28/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 08/06/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/26/2024 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 06/25/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 06/10/2024 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 05/28/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/05/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/08/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 06/30/2022 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 05/19/2022 | Pass-Final House Connection | Pass | View ↗ |
| 03/11/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/11/2024 | Air barrier — testing | Jeffrey Stones | energy_progress |
| 11/11/2024 | Air barrier - visual inspection | Jeffrey Stones | energy_progress |
| 11/11/2024 | Permanent certificate | Jeffrey Stones | energy_progress |
| 11/11/2024 | Protection of exposed foundation insulation | Jeffrey Stones | energy_progress |
| 11/11/2024 | Ventilation and air distribution system | Jeffrey Stones | energy_progress |
| 11/11/2024 | Lighting controls | Jeffrey Stones | energy_progress |
| 11/11/2024 | HVAC-R and service water piping design and insulation | Jeffrey Stones | energy_progress |
| 11/11/2024 | Fireplaces | Jeffrey Stones | energy_progress |
| 11/11/2024 | Duct leakage testing, insulation and design | Jeffrey Stones | energy_progress |
| 11/11/2024 | Fenestration and door U-factor and product ratings | Jeffrey Stones | energy_progress |
| 11/11/2024 | Insulation placement and R values | Jeffrey Stones | energy_progress |
| 11/11/2024 | HVAC-R and service water heating equipment | Jeffrey Stones | energy_progress |
| 11/11/2024 | HVAC-R and service water heating system controls | Jeffrey Stones | energy_progress |
| 11/11/2024 | Fenestration areas | Jeffrey Stones | energy_progress |
| 11/11/2024 | Maintenance information | Jeffrey Stones | energy_progress |
| 11/11/2024 | Metering | Jeffrey Stones | energy_progress |
| 11/11/2024 | Fenestration air leakage | Jeffrey Stones | energy_progress |
| 11/11/2024 | Electric vehicle service equipment requirements | Jeffrey Stones | energy_progress |
| 11/11/2024 | Exterior lighting power | Jeffrey Stones | energy_progress |
| 11/11/2024 | Interior lighting power | Jeffrey Stones | energy_progress |
| 11/11/2024 | Lowest Floor Elevation | Jeffrey Stones | progress |
| 11/11/2024 | Footing and Foundation | Jeffrey Stones | progress |
| 11/11/2024 | Fire-Resistance Rated Construction | Jeffrey Stones | progress |
| 11/11/2024 | Final | Jeffrey Stones | progress |
| 11/11/2024 | Energy Code Compliance Inspections | Jeffrey Stones | progress |