| Owner | Filings | Most Recent |
|---|---|---|
| MACK REAL ESTATE GROUP | 61 | 09/15/2026 |
| TRI BOROUGH SCAFFOLDING | 6 | 07/08/2026 |
| CHARTER | 1 | 03/22/2026 |
| 19 INDIA FEE OWNER LLC | 5 | 03/22/2026 |
| MP 145 WS OWNER | 35 | 03/21/2026 |
| 10 HURON FS CONDO | 5 | 03/21/2026 |
| 145WEST ST | 21 | 03/21/2026 |
| C O MACK REAL ESTATE GROUP | 11 | 03/21/2026 |
| MP 145 WS OWNER LLC C O MACK | 20 | 03/21/2026 |
| 235 PARK AVENUE | 6 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| GGA STUDIOS, DPC | 20 | 09/02/2026 |
| INTEGRATED ENERGY CONCEPTS ENG | 2 | 04/04/2024 |
| WAVIC ENGINEERING PLLC | 1 | 11/30/2022 |
| STANTEC | 3 | 10/31/2022 |
| WSP | 1 | 02/02/2021 |
| KEVIN GALLEN PE LLC | 3 | 12/08/2019 |
| SCALAR ARCHITECTURE PC | 2 | 10/09/2019 |
| ISMAEL LEYVA ARCHITECT'S P.C. | 1 | 03/15/2019 |
| LOMBARDO PROFESSIONAL ENGINEERING | 1 | 03/16/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| DOMANI CONSULTING | 23 | 03/21/2026 |
| CHRISTOPHER TEETER RA | 6 | 03/21/2026 |
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| JM ZONING, LLC. | 2 | 03/21/2026 |
| DAVE RESTORATION | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NEPTUNE MECHANICAL INC | Plumbing | 11 | 07/08/2026 |
| NEPTUNE MECHANICAL INC | General Contractor | 8 | 07/08/2026 |
| TRI BOROUGH SCAFFOLDING | General Contractor | 7 | 07/08/2026 |
| NEPTUNE MECHANICAL INC | Fire Protection | 5 | 07/08/2026 |
| DESIMONE BUILDERS LLC | General Contractor | 4 | 07/08/2026 |
| STANDARD FIRE SUPP CORP | Fire Protection | 3 | 07/08/2026 |
| SAM'S AIRCONDITIONING INC | General Contractor | 3 | 03/21/2026 |
| ADDVANCE CONSTUCTION INC | General Contractor | 3 | 03/21/2026 |
| SOLUTION MECH CONTNG LLC | Plumbing | 2 | 07/08/2026 |
| FIVE BORO ASSOCIATES INC | Fire Protection | 2 | 07/08/2026 |
| PMM CRANES,LLC | General Contractor | 1 | 07/08/2026 |
| ARISTA PLBG & HTG CORP | Plumbing | 1 | 07/08/2026 |
| 303 CONSTRUCTION CORP | General Contractor | 1 | 07/08/2026 |
| L&B ELEC'L INTERNATIONAL | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| DOMANI INSPECTION SERVICE | 843 | 17 | 09/02/2026 |
| RICHMOND TESTING LAB | 263 | 7 | 04/04/2024 |
| WAVIC ENGINEERING PLLC | 1733 | 1 | 11/30/2022 |
| ASSURE PROFESSIONAL ENGIN | 6962 | 3 | 12/08/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | SOLUTION MECH CONTNG LLC | 06/02/2026 |
| DOB NOW | Sprinklers | Signed-off | FIVE BORO ASSOCIATES INC | 06/01/2026 |
| DOB NOW | Sprinklers | Signed-off | FIVE BORO ASSOCIATES INC | 06/01/2026 |
| DOB NOW | Plumbing | Signed-off | SOLUTION MECH CONTNG LLC | 06/01/2026 |
| DOB NOW | Mechanical Systems | Signed-off | DESIMONE BUILDERS LLC | 05/29/2026 |
| DOB NOW | Mechanical Systems | Signed-off | DESIMONE BUILDERS LLC | 05/28/2026 |
| DOB NOW | General Construction | Permit Issued | DESIMONE BUILDERS LLC | 05/28/2026 |
| DOB NOW | General Construction | Signed-off | DESIMONE BUILDERS LLC | 05/28/2026 |
| DOB NOW | Sprinklers | Permit Issued | NEPTUNE MECHANICAL INC | 04/07/2025 |
| DOB NOW | Mechanical Systems | Signed-off | NEPTUNE MECHANICAL INC | 06/03/2024 |
| DOB NOW | Plumbing | Permit Issued | NEPTUNE MECHANICAL INC | 05/06/2024 |
| DOB NOW | Plumbing | Permit Issued | NEPTUNE MECHANICAL INC | 02/22/2024 |
| DOB NOW | General Construction | Permit Issued | 303 CONSTRUCTION CORP | 01/11/2024 |
| DOB NOW | Sprinklers | Signed-off | NEPTUNE MECHANICAL INC | 08/15/2023 |
| DOB NOW | Plumbing | Signed-off | NEPTUNE MECHANICAL INC | 04/17/2023 |
| DOB NOW | Mechanical Systems | Signed-off | NEPTUNE MECHANICAL INC | 04/17/2023 |
| DOB NOW | General Construction | Signed-off | NEPTUNE MECHANICAL INC | 04/13/2023 |
| DOB NOW | Standpipe | Signed-off | NEPTUNE MECHANICAL INC | 12/07/2022 |
| DOB NOW | Sprinklers | Signed-off | NEPTUNE MECHANICAL INC | 12/16/2021 |
| DOB NOW | Plumbing | Signed-off | NEPTUNE MECHANICAL INC | 12/16/2021 |
| DOB NOW | Mechanical Systems | Signed-off | NEPTUNE MECHANICAL INC | 12/16/2021 |
| DOB NOW | Sprinklers | Signed-off | NEPTUNE MECHANICAL INC | 09/09/2021 |
| DOB NOW | Sprinklers | Signed-off | NEPTUNE MECHANICAL INC | 09/09/2021 |
| DOB NOW | Structural | Signed-off | ADDVANCE CONSTUCTION INC | 09/08/2021 |
| DOB NOW | Sprinklers | Signed-off | STANDARD FIRE SUPP CORP | 07/16/2021 |
| DOB NOW | Sprinklers | Signed-off | STANDARD FIRE SUPP CORP | 03/25/2021 |
| DOB NOW | Mechanical Systems | Signed-off | NEPTUNE MECHANICAL INC | 08/27/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | TRI BOROUGH SCAFFOLDING | 04/01/2020 |
| DOB NOW | Mechanical Systems | Signed-off | SAM'S AIRCONDITIONING INC | 02/06/2020 |
| DOB NOW | Plumbing | Signed-off | ARISTA PLBG & HTG CORP | 12/18/2019 |
| DOB NOW | Sprinklers | Signed-off | STANDARD FIRE SUPP CORP | 12/09/2019 |
| DOB NOW | Supported Scaffold | Signed-off | TRI BOROUGH SCAFFOLDING | 10/09/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | TRI BOROUGH SCAFFOLDING | 10/07/2019 |
| DOB NOW | Supported Scaffold | Signed-off | PMM CRANES,LLC | 03/19/2018 |
| BIS | OT | ISSUED | NEPTUNE MECHANICAL INC | 03/04/2022 |
| BIS | OT | ISSUED | NEPTUNE MECHANICAL INC | 12/15/2021 |
| BIS | PL | ISSUED | PACE PLUMBING CORP | 11/22/2021 |
| BIS | SP | ISSUED | WNW & SONS PLUMBING & HTG | 02/12/2021 |
| BIS | PL | ISSUED | PACE PLUMBING CORP | 01/21/2021 |
| BIS | — | ISSUED | NOBLE CONSTRUCTION GR LLC | 07/08/2020 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/02/2026 | Signed-off | DESIMONE BUILDERS LLC | Heating and Air Conditioning Systems | Heat / Cool Daikin WSMH060 58,516 BTU · Heat Pump Outdoor ×1 |
| 08/12/2026 | Signed-off | DESIMONE BUILDERS LLC | Heating and Air Conditioning Systems | Heat / Cool Daikin WSMH060 58,516 BTU · Wshp ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/02/2026 | Signed-off | FIVE BORO ASSOCIATES INC | Sprinkler System |
| 08/12/2026 | Signed-off | FIVE BORO ASSOCIATES INC | Sprinkler System |
| 09/30/2024 | Permit Issued | NEPTUNE MECHANICAL INC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/02/2026 | Signed-off | SOLUTION MECH CONTNG LLC | Water/Sanitary |
| 08/12/2026 | Signed-off | SOLUTION MECH CONTNG LLC | Water/Sanitary |
| 09/30/2024 | Permit Issued | NEPTUNE MECHANICAL INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/26/2026 | Permit Issued | D&D ELECTL CONST CO INC | General Wiring |
| 09/11/2023 | Complete | LIPPOLIS ELECTRIC, INC. | General Wiring |
| 06/24/2021 | Complete | LIPPOLIS ELECTRIC, INC. | General Wiring |
| 05/03/2021 | Complete | LEONE ELECTRIC CO. INC | General Wiring |
| 11/13/2019 | Permit Issued | L&B ELEC'L INTERNATIONAL | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/02/2026 | Signed-off | SOLUTION MECH CONTNG LLC | Steel |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/20/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/18/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/18/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/07/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/06/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/30/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/08/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/08/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 04/01/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/10/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/10/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/26/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/30/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/18/2023 | Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test | Certified | View ↗ |
| 07/20/2023 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 07/19/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/17/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/29/2023 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 06/01/2023 | Certified StandPipe-Fire Pump (SD)-Fire Pump Test | Certified | View ↗ |
| 05/01/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/26/2023 | Certified Sprinkler (PL)-Sprinkler-Hydro | Certified | View ↗ |
| 04/26/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/20/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/27/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/27/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/24/2026 | Fire-Resistance Rated Construction | JOHN MCMONAGLE | progress |
| 08/24/2026 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 08/24/2026 | Energy Code Compliance Inspections | JOHN MCMONAGLE | progress |
| 08/24/2026 | Final | JOHN MCMONAGLE | progress |
| 08/13/2026 | Sprinkler Systems | JOHN MCMONAGLE | special |
| 05/18/2026 | HVAC-R and service water heating equipment | JOHN MCMONAGLE | energy_progress |
| 05/18/2026 | HVAC-R and service water heating system controls | JOHN MCMONAGLE | energy_progress |
| 05/18/2026 | Interior lighting power | JOHN MCMONAGLE | energy_progress |
| 05/18/2026 | Lighting controls | JOHN MCMONAGLE | energy_progress |
| 05/18/2026 | HVAC-R and service water piping design and insulation | JOHN MCMONAGLE | energy_progress |
| 05/18/2026 | HVAC-R and service water heating equipment | JOHN MCMONAGLE | energy_progress |
| 05/18/2026 | HVAC-R and service water piping design and insulation | JOHN MCMONAGLE | energy_progress |
| 05/18/2026 | HVAC-R and service water heating system controls | JOHN MCMONAGLE | energy_progress |
| 05/12/2026 | Final | JOHN MCMONAGLE | progress |
| 05/12/2026 | Fire-Resistance Rated Construction | JOHN MCMONAGLE | progress |
| 05/12/2026 | Energy Code Compliance Inspections | JOHN MCMONAGLE | progress |
| 05/12/2026 | Final | JOHN MCMONAGLE | progress |
| 05/12/2026 | Structural Steel - Details | JOHN MCMONAGLE | special |
| 05/12/2026 | Structural Cold-Formed Steel | JOHN MCMONAGLE | special |
| 05/12/2026 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 05/12/2026 | Mechanical Systems | JOHN MCMONAGLE | special |
| 05/08/2026 | Mechanical Systems | JOHN MCMONAGLE | special |
| 05/08/2026 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 05/08/2026 | Final | JOHN MCMONAGLE | progress |
| 05/08/2026 | Energy Code Compliance Inspections | JOHN MCMONAGLE | progress |