← Back
Two family converted from one family
100-10 205 PLACE
QUEENS · Hollis · BIN 4232497
💬 Discuss this project
1925Year Built
2.5Stories
B3Building Class
R3AZoning
1,757 sfGross Floor Area
2Units
1 Open Violation ▸FDNY Report ↗
Two family converted from one family · 3,200 sf lot · 0.55 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Roof2p · 1 filing · 9 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC104/28/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
KAMTECH RESTORATION CORP203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
KAMTECH RESTORATION CORPGeneral Contractor203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854104/28/2025
Building Lifecycle
All (13)Filed (1)Permit Issued (1)Signed Off (1)Violation (5)Special Inspection (5)
07/10/2025
Signed off — Alteration
ROOFTOP SOLAR INSTALLATION. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
Q01217349-I1
05/01/2025
Permit issued — Solar
Q01217349-I1-SL
04/28/2025
Filed — Alteration
ROOFTOP SOLAR INSTALLATION. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
Q01217349-I1
04/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
04/28/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
04/28/2025
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
04/28/2025
Special inspection requirement — Final
TOM PETERSEN
04/28/2025
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
09/10/2024
Violation issued (HPD, closed)
I
09/03/2024
Violation issued (HPD, closed)
B
09/03/2024
Violation issued (HPD, closed)
B
09/03/2024
Violation issued (HPD, closed)
B
09/03/2024
Violation issued (ECB, open)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offKAMTECH RESTORATION CORP05/01/2025
1 project · most recent 04/23/2025
FiledStatusContractorScope
04/23/2025CompleteBERGER QUALITY ELEC'L CON—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
04/28/2025Fire-Resistant Penetrations and JointsTOM PETERSENspecial
04/28/2025Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
04/28/2025Energy Code Compliance InspectionsTOM PETERSENprogress
04/28/2025FinalTOM PETERSENprogress
04/28/2025Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/20/2026Q01217349-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/27/2026Q01217349-I1Open ↗
08/27/2026Q01217349-I1Open ↗
08/27/2026Q01217349-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/27/2026Q01217349-I1Open ↗
08/27/2026Q01217349-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01217349-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01217349-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01217349-I1Open ↗