| Owner | Filings | Most Recent |
|---|---|---|
| HSD CONSTRUCTION | 3 | 09/13/2026 |
| GALAXY DEVELOPERS | 34 | 09/01/2026 |
| MNK ENTERPRISES | 3 | 08/28/2026 |
| CANADIAN ARTIC BUILDERS | 5 | 03/22/2026 |
| THE OWNER OF 100 RUTLEDGE | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/04/2026 | $3.5M | — | 100 RUTLEDGE LLC → 100 RUT LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| ALWAYS FAST SERVICES CORP | 2 | 08/26/2026 |
| R & O ENGINEERING | 4 | 07/02/2026 |
| DIEGO AGUILERA ARCHITECTS P.C. | 3 | 03/31/2026 |
| VASILIOS ARTEMIOU PE | 3 | 10/20/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GALAXY DEVELOPERS LLC | General Contractor | 14 | 09/01/2026 |
| MNK ENTERPRISES LLC | General Contractor | 2 | 08/27/2026 |
| M.R. ELEC'L SERVICE LLC | Electrical | 1 | 03/22/2026 |
| JOSEPH DI GIACOMO | Electrical | 1 | 03/21/2026 |
| BEST MECHANICAL SVCS INC | Plumbing | 1 | 07/08/2026 |
| MPI PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| QMB PLUMBING & HEATING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TECNICO SPECIAL INSPECTIO | 5939 | 9 | 07/02/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Foundation | Permit Issued | GALAXY DEVELOPERS LLC | 08/31/2026 |
| DOB NOW | Support of Excavation | Signed-off | GALAXY DEVELOPERS LLC | 08/31/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | MNK ENTERPRISES LLC | 08/26/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | MNK ENTERPRISES LLC | 08/24/2026 |
| DOB NOW | Structural | Permit Issued | GALAXY DEVELOPERS LLC | 07/07/2026 |
| DOB NOW | Foundation | Permit Issued | GALAXY DEVELOPERS LLC | 07/07/2026 |
| DOB NOW | General Construction | Permit Issued | GALAXY DEVELOPERS LLC | 06/03/2026 |
| DOB NOW | Structural | Permit Issued | GALAXY DEVELOPERS LLC | 06/03/2026 |
| DOB NOW | Construction Fence | Permit Issued | GALAXY DEVELOPERS LLC | 06/03/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | GALAXY DEVELOPERS LLC | 06/02/2026 |
| DOB NOW | Foundation | Permit Issued | GALAXY DEVELOPERS LLC | 06/02/2026 |
| DOB NOW | Plumbing | Permit Issued | QMB PLUMBING & HEATING INC | 05/19/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | GALAXY DEVELOPERS LLC | 12/29/2025 |
| DOB NOW | Plumbing | Permit Issued | YG SERVICES INC | 12/29/2025 |
| DOB NOW | Foundation | Permit Issued | GALAXY DEVELOPERS LLC | 12/22/2025 |
| DOB NOW | Sprinklers | Permit Issued | BEST MECHANICAL SVCS INC | 12/18/2025 |
| DOB NOW | Structural | Permit Issued | GALAXY DEVELOPERS LLC | 12/18/2025 |
| DOB NOW | General Construction | Permit Issued | GALAXY DEVELOPERS LLC | 12/17/2025 |
| DOB NOW | Construction Fence | Permit Issued | GALAXY DEVELOPERS LLC | 08/18/2025 |
| BIS | OT | ISSUED | CANADIAN ARTIC BUILDERS | 03/08/2005 |
| BIS | OT | ISSUED | ABGG CONST INC | 02/25/2004 |
| BIS | — | ISSUED | ABGG CONSTRUCTION INC. | 10/09/2003 |
| BIS | EQ | ISSUED | ABGG CONSTRUCTION INC. | 07/10/2003 |
| BIS | — | ISSUED | ABGG CONSTRUCTION INC. | 07/10/2003 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/02/2026 | Signed-off | GALAXY DEVELOPERS LLC | Heating and Air Conditioning Systems, Heating Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/02/2026 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/02/2026 | Permit Issued | MPI PLUMBING CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/02/2026 | Permit Issued | ABZ ELECTRIC INC | General Wiring |
| 08/22/2026 | Permit Issued | RICHARD NEU | — |
| 11/10/2025 | Permit Issued | M.R. ELEC'L SERVICE LLC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/02/2026 | Signed-off | GALAXY DEVELOPERS LLC | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/02/2026 | Permit Issued | GALAXY DEVELOPERS LLC | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/02/2026 | Signed-off | GALAXY DEVELOPERS LLC | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/02/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/27/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 08/07/2026 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 08/07/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/06/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/06/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 07/24/2026 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 07/20/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 06/12/2026 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 10/15/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/15/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/31/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 06/10/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/01/2026 | Excavations - Sheeting, Shoring, and Bracing | Jose Lockhart | special |
| 07/01/2026 | Deep Foundation Elements | — | special |
| 07/01/2026 | Post-installed Anchors | Jose Lockhart | special |
| 07/01/2026 | Construction Operations Influencing Adjacent Structures | Jose Lockhart | special |
| 07/01/2026 | Subsurface Investigations (Borings/Test Pits) | FERAS AYOUB | special |
| 07/01/2026 | Subgrade Inspections | Jose Lockhart | special |
| 06/18/2026 | Subsurface Conditions – Fill Placement & In-Place Density | Jose Lockhart | special |
| 06/18/2026 | Footing and Foundation | Jose Lockhart | progress |
| 06/18/2026 | Final | Jose Lockhart | progress |
| 06/18/2026 | Subsurface Investigations (Borings/Test Pits) | FERAS AYOUB | special |
| 06/18/2026 | Concrete - Cast-In-Place | Jose Lockhart | special |
| 06/18/2026 | Subgrade Inspections | Jose Lockhart | special |
| 03/25/2026 | Insulation placement and R values | Jose Lockhart | energy_progress |
| 03/25/2026 | Electrical motors and elevators | Jose Lockhart | energy_progress |
| 03/25/2026 | Air barrier — testing | Jose Lockhart | energy_progress |
| 03/25/2026 | Fire-Resistance Rated Construction | Jose Lockhart | progress |
| 03/25/2026 | Energy Code Compliance Inspections | Jose Lockhart | progress |
| 03/25/2026 | Fire-Resistant Penetrations and Joints | Jose Lockhart | special |
| 03/25/2026 | Exterior Insulation and Finish Systems (EIFS) | Jose Lockhart | special |
| 03/25/2026 | Air barrier - visual inspection | Jose Lockhart | energy_progress |
| 03/25/2026 | Fenestration areas | Jose Lockhart | energy_progress |
| 03/25/2026 | Permanent certificate | Jose Lockhart | energy_progress |
| 03/25/2026 | Fenestration and door U-factor and product ratings | Jose Lockhart | energy_progress |
| 03/25/2026 | Metering | Jose Lockhart | energy_progress |
| 03/25/2026 | Lighting controls | Jose Lockhart | energy_progress |