| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | TOM PETERSEN ARCHITECT, LLC | 09/25/2025 |
| DOB NOW | Solar | Signed-off | TOM PETERSEN ARCHITECT, LLC | 06/26/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/17/2024 | Complete | VENTURE HOME SOLAR LLC | — |
| 01/13/2022 | Complete | BERGER QUALITY ELEC'L CON | — |
| 01/17/2020 | Complete | STANCO SYSTEM ELEC'L CONT | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/10/2024 | — | — | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/10/2025 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | TOM PETERSEN | special |
| 03/10/2025 | Fire-Resistant Penetrations and Joints | TOM PETERSEN | special |
| 03/10/2025 | Structural Stability – Alterations of existing buildings | TOM PETERSEN | special |
| 03/10/2025 | Air barrier - visual inspection | TOM PETERSEN | energy_progress |
| 03/10/2025 | Energy Code Compliance Inspections | TOM PETERSEN | progress |
| 03/10/2025 | Final | TOM PETERSEN | progress |
| 12/13/2024 | Metering | MUZAFFAR JAMAL | energy_progress |
| 11/27/2024 | Subgrade Inspections | — | special |
| 11/27/2024 | Structural Stability – Alterations of existing buildings | — | special |
| 11/27/2024 | Final | — | progress |
| 11/27/2024 | Footing and Foundation | — | progress |
| 11/27/2024 | Energy Code Compliance Inspections | — | progress |
| 11/27/2024 | Fire-Resistance Rated Construction | — | progress |
| 11/27/2024 | Structural Wood Frame | — | progress |
| 11/27/2024 | Insulation placement and R values | — | energy_progress |
| 11/27/2024 | HVAC-R and service water heating system controls | — | energy_progress |
| 11/27/2024 | Interior lighting power | — | energy_progress |
| 11/27/2024 | Fenestration areas | — | energy_progress |
| 11/27/2024 | Ventilation and air distribution system | — | energy_progress |
| 11/27/2024 | Permanent certificate | — | energy_progress |
| 11/27/2024 | HVAC-R and service water heating equipment | — | energy_progress |
| 11/27/2024 | Electric vehicle service equipment requirements | — | energy_progress |
| 11/27/2024 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 11/27/2024 | Fenestration air leakage | — | energy_progress |
| 11/27/2024 | Air barrier - visual inspection | — | energy_progress |