← Back
Single or multiple dwelling with stores or offices
1000 MORRIS PARK AVENUE
BRONX · Morris Park · BIN 2093137
💬 Discuss this project
1937Year Built
2Stories
S9Building Class
R4Zoning
9,000 sfGross Floor Area
9Units
Rent Stabilized13 Open Violations ▸
Single or multiple dwelling with stores or offices · Owner of record: MPGRETTY REALTY LLC · 10,000 sf lot · 0.9 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Permit Issued — active, not yet Signed-off
RoofUnder Construction5p · 1 filing · 14 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
1018 MORRIS PARK AVE REALTY403/21/2026
MPGRETTY REALTY203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NY BUILDING ASSOCIATES INC203/23/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
S R SOLAR DESIGN203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JOE MIDDLETONElectrical103/21/2026
SOLAR ONE INCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NKM ENGINEERING PLLC6244403/23/2026
Building Lifecycle
All (59)Filed (2)Permit Issued (1)Violation (34)Objection (12)Special Inspection (10)
04/30/2026
Violation issued (HPD, open)
A
04/13/2026
Permit issued — Solar
X01209023-I1-SL
04/09/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
04/09/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
NARESH MAHANGU
04/09/2026
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
04/09/2026
Special inspection requirement — Final
NARESH MAHANGU
04/09/2026
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
03/23/2026
Filed — Alteration
INSTALLATION OF SOLAR PANELS ON EXISTING ROOF. NO CHANGE IN USE, OCCUPANCY, OR EGRESS. NO CHANGE IN BULK. WORK IS BEING PAID FOR UNDER JOB # X01208892-I1
X01209023-P1
03/02/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
03/02/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
NARESH MAHANGU
03/02/2026
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
03/02/2026
Special inspection requirement — Final
NARESH MAHANGU
03/02/2026
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
12/24/2025
Objection raised — Cost
12/24/2025
Objection resolved — Addressed
12/16/2025
Objection resolved — Addressed
12/16/2025
Objection resolved — Addressed
12/16/2025
Objection resolved — Addressed
12/16/2025
Objection resolved — Addressed
12/16/2025
Objection resolved — Addressed
12/01/2025
Objection raised — Fire_Protection
11/28/2025
Objection raised — Scope
11/28/2025
Objection raised — Fire_Protection
11/28/2025
Objection raised — Other
11/28/2025
Objection raised — Other
11/11/2025
Filed — Alteration
INSTALLATION OF SOLAR PANELS ON EXISTING ROOF. NO CHANGE IN USE, OCCUPANCY, OR EGRESS. NO CHANGE IN BULK. WORK IS BEING PAID FOR UNDER JOB # X01208892-I1
X01209023-I1
06/05/2025
Violation issued (HPD, closed)
A
04/03/2024
Violation issued (HPD, closed)
A
11/16/2023
Violation issued (HPD, closed)
I
03/17/2023
Violation issued (HPD, closed)
A
11/03/2022
Violation issued (HPD, closed)
I
02/17/2022
Violation issued (HPD, closed)
A
02/17/2022
Violation issued (HPD, closed)
I
04/05/2021
Violation issued (HPD, closed)
A
12/23/2019
Violation issued (HPD, closed)
A
12/23/2019
Violation issued (HPD, closed)
A
12/23/2019
Violation issued (HPD, closed)
A
12/23/2019
Violation issued (HPD, closed)
A
12/23/2019
Violation issued (HPD, closed)
A
12/23/2019
Violation issued (HPD, closed)
A
12/23/2019
Violation issued (HPD, open)
C
06/13/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/15/2018
Violation issued (ECB, closed)
Construction
03/15/2018
Violation issued (ECB, closed)
Construction
10/31/2016
Violation issued (HPD, closed)
I
10/05/2015
Violation issued (HPD, closed)
I
02/04/2015
Violation issued (HPD, closed)
I
02/18/2009
Violation issued (HPD, open)
B
02/18/2009
Violation issued (HPD, open)
B
06/20/2005
Violation issued (HPD, open)
B
06/20/2005
Violation issued (HPD, open)
A
06/20/2005
Violation issued (HPD, open)
B
06/20/2005
Violation issued (HPD, open)
B
06/20/2005
Violation issued (HPD, open)
B
06/20/2005
Violation issued (HPD, open)
B
06/20/2005
Violation issued (HPD, open)
B
11/14/2000
Violation issued (HPD, open)
B
11/14/2000
Violation issued (HPD, open)
B
06/28/2000
Violation issued (ECB, closed)
Quality of Life
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedSOLAR ONE INC04/13/2026
BISFPISSUEDMASTER FIRE SYSTEMS, INC02/27/2007
BISPLISSUEDLEFKES WATER WORKS INC02/23/2007
BISPLISSUEDHUDSON RIVER MECH GROUP I08/02/2001
BIS—ISSUED1018 MORRIS PARK AVENUE REALEY11/08/2000
BISFPISSUEDMASTER FIRE PREVENTION SYSTEMS01/06/1992
BISOTISSUEDCASSETTA CONTRACTING CORP01/18/1990
1 project · most recent 03/23/2026
FiledStatusContractorScope
03/23/2026CompleteNEWGRANGE ELECTRIC, INC—
1 project · most recent 03/23/2026
FiledStatusContractorScope
03/23/2026Permit IssuedSOLAR ONE INC500 panels, 297.5 kw, 14,795 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
04/09/2026Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
04/09/2026Structural Stability – Alterations of existing buildingsNARESH MAHANGUspecial
04/09/2026Energy Code Compliance InspectionsNARESH MAHANGUprogress
04/09/2026FinalNARESH MAHANGUprogress
04/09/2026Air barrier - visual inspectionNARESH MAHANGUenergy_progress
03/02/2026Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
03/02/2026Structural Stability – Alterations of existing buildingsNARESH MAHANGUspecial
03/02/2026Energy Code Compliance InspectionsNARESH MAHANGUprogress
03/02/2026FinalNARESH MAHANGUprogress
03/02/2026Air barrier - visual inspectionNARESH MAHANGUenergy_progress
▾Documents — 27 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/17/2026X01209023-I1Request digital key ↗
08/17/2026X01209023-P1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
08/01/2016220532788Open ↗
▸BISWORK PERMIT APPLICATION1
07/19/2016220532788Open ↗
▸Seals & Professional Certifications14
▸DOB NOWProgress Inspector Seal & Signature4
09/01/2026X01209023-I1Open ↗
09/01/2026X01209023-I1Open ↗
08/22/2026X01209023-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/01/2026X01209023-I1Open ↗
09/01/2026X01209023-I1Open ↗
08/22/2026X01209023-P1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
03/08/2018220532788Open ↗
06/22/2016220532788Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/13/2026X01209023-I1Open ↗
08/13/2026X01209023-P1Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
06/22/2016220532788Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
06/22/2016220532788Open ↗
▸Trade Schedules & Equipment2
▸BISFA - FDNY APPROVAL : FD-FAA2
03/08/2018220532788Open ↗
08/01/2016220532788Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026X01209023-P1Open ↗
08/13/2026X01209023-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
03/08/2018220532788Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
03/08/2018220532788Open ↗
06/22/2016220532788Open ↗
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET1
08/01/2016220532788Open ↗
▸BISBOROUGH INTAKE FORM1
03/08/2018220532788Open ↗