Elevator apt, miscellaneous
1000 WOODYCREST AVENUE
BRONX · BIN 2130588
💬 Discuss this project
2021Year Built
7Stories
D9Building Class
R7-1Zoning
22,431 sfGross Floor Area
27Units
Rent Stabilized124 Active Violations ▸
Elevator apt, miscellaneous · Owner of record: Woodycrest Realty Holdings · 5,000 sf lot · 4.49 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofInstall fire sprinkler system in entire building54p · 5 filings · 20 docs
BulkheadMechanical systems installation3p · 2 filings · 16 docs
Floor 7Install fire sprinkler system in entire building50p · 4 filings · 20 docs
Floor 6Install fire sprinkler system in entire building52p · 4 filings · 20 docs
Floor 5Install fire sprinkler system in entire building51p · 4 filings · 20 docs
Floor 4Install fire sprinkler system in entire building44p · 4 filings · 20 docs
Floor 3Install fire sprinkler system in entire building49p · 4 filings · 20 docs
Floor 2Install fire sprinkler system in entire building50p · 4 filings · 20 docs
Floor 1Steel curb facing installation52p · 5 filings · 20 docs
Site & exteriorInstall fire sprinkler system in entire building52p · 5 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
1000 Woodycrest Realty1503/21/2026
H-O Realty203/22/2026
Woodycrest Realty Holdings103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/30/2019$1.1M—1000 WOODYCREST, LLC → 1000 WOODYCREST REALTY LLC— not available
10/31/2018$1.2M—Private party → 1000 WOODYCREST LLC— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Advanced Engineering & Inspection PLL601/26/2022
Ashraf510/22/2021
Titan Engineers109/23/2020
South Bay Engineering108/21/2020
Sander Williams Architect108/18/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Speedy Expediting1603/21/2026
Rigid Structural Design503/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Manhattan D EnterprisesScaffold707/08/2026
S R Electrical MechanicalsGeneral Contractor503/22/2026
S&R Electrical & MechanicalsElectrical503/21/2026
Skyward DevelopersGeneral Contractor407/08/2026
Skyward DevelopersScaffold303/21/2026
Cresco ElectricalElectrical203/22/2026
Prime Piping HeatingGeneral Contractor103/22/2026
S&R Electrical & MechanicalsElectrical103/22/2026
Prime Piping & HeatingPlumbing107/08/2026
Prime Piping & HeatingFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF Services5616601/24/2022
Building Lifecycle
07/01/2026
§ 27-2005, 27-2007, 27-2041.1 HMC, §238, § 309; § 107 (2) ( C) MDL AND 28 RCNY §25-171: REPLACE OR REPAIR THE SELF-CLOSING DOORS THAT IS MISSING OR…
HPD violation · closed
06/11/2026
§ 27-2005 HMC: PROPERLY REPAIR OR REPLACE THE BROKEN OR DEFECTIVE DOORS AT SINK BASE CABINET IN THE KITCHENETTE LOCATED AT APT 4E, 4th STORY, 2nd…
HPD violation · closed
06/11/2026
§ 27-2005 HMC: PROPERLY REPAIR OR REPLACE THE BROKEN OR DEFECTIVE LATCH SET AT ENTRANCE DOOR IN THE 3rd ROOM FROM NORTH LOCATED AT APT 4E, 4th…
HPD violation · closed
06/07/2026
HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF ROACHES IN THE ENTIRE APARTMENT LOCATED AT APT 6C, 6th STORY, 2nd APARTMENT FROM EAST…
HPD violation · closed
06/07/2026
HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF MICE IN THE ENTIRE APARTMENT LOCATED AT APT 4C, 4th STORY, 2nd APARTMENT FROM NORTH…
HPD violation · open
288 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offSkyward Developers12/31/2021
DOB NOWSprinklersSigned-offAmb Mechanical08/27/2021
DOB NOWMechanical SystemsSigned-offSkyward Developers08/19/2021
DOB NOWStructuralSigned-offSkyward Developers08/19/2021
DOB NOWProtection and Mechanical MethodsSigned-offManhattan D Enterprises07/30/2021
DOB NOWPlumbingSigned-offPrime Piping & Heating07/28/2021
DOB NOWSupported ScaffoldSigned-offManhattan D Enterprises07/23/2021
DOB NOWSidewalk ShedSigned-offManhattan D Enterprises07/19/2021
DOB NOWConstruction FenceSigned-offSkyward Developers07/16/2021
BIS—ISSUEDSkyward Developers01/26/2022
BIS—ISSUEDSkyward Developers02/05/2021
BIS—ISSUEDSkyward Developers02/05/2021
5 projects · most recent 08/23/2022
General Wiring
FiledStatusContractorScope
08/23/2022CompleteStar Electrical Contractors—
02/28/2022CompleteS&R Electrical & MechanicalsGeneral Wiring
07/15/2021CompleteV. Vass Electric—
07/15/2021CompleteS&R Electrical & Mechanicals—
10/13/2019CancelledCresco Electrical—
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
02/14/2022Pass-Final Curb Cut Non-Directive 14PassView ↗
02/11/2022Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve TestCertifiedView ↗
02/11/2022Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
02/09/2022Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
11/05/2021Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
08/26/2021Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/23/2021No Access-Final PL - Up to 3 Requested FloorsNo AccessView ↗
▾Special Inspection Requirements (DOB NOW) — 41
DateRequirementInspectorRole
02/27/2022Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
02/27/2022Heating SystemsFAHAD FATEHspecial
02/27/2022Mechanical SystemsFAHAD FATEHspecial
02/27/2022Energy Code Compliance InspectionsFAHAD FATEHprogress
02/27/2022FinalFAHAD FATEHprogress
02/27/2022HVAC and service water heating system controls FAHAD FATEHenergy_progress
02/27/2022Maintenance informationFAHAD FATEHenergy_progress
02/27/2022HVAC insulation and sealing FAHAD FATEHenergy_progress
02/27/2022HVAC and service water heating equipment FAHAD FATEHenergy_progress
02/27/2022Shutoff dampersFAHAD FATEHenergy_progress
02/27/2022Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
02/27/2022Maintenance informationFAHAD FATEHenergy_progress
02/27/2022HVAC insulation and sealing FAHAD FATEHenergy_progress
02/27/2022HVAC and service water heating equipment FAHAD FATEHenergy_progress
02/27/2022HVAC and service water heating system controls FAHAD FATEHenergy_progress
02/27/2022Energy Code Compliance InspectionsFAHAD FATEHprogress
02/27/2022Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationFAHAD FATEHspecial
01/20/2022Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationFAHAD FATEHspecial
01/20/2022Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
01/20/2022Sprinkler SystemsFAHAD FATEHspecial
01/20/2022Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
01/20/2022Energy Code Compliance InspectionsFAHAD FATEHprogress
01/20/2022HVAC and service water heating equipment FAHAD FATEHenergy_progress
01/20/2022Maintenance informationFAHAD FATEHenergy_progress
01/20/2022HVAC and service water heating system controls FAHAD FATEHenergy_progress
Latest 25 of 41.
173 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account