| Owner | Filings | Most Recent |
|---|---|---|
| PARKVIEW MANAGEMENT GROUP | 4 | 09/13/2026 |
| TOTAL NY CONSTRUCTION | 4 | 07/08/2026 |
| 1001 FULTON ST LLC | 1 | 03/22/2026 |
| OWNER OF 1001 FULTON ST | 5 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/31/2019 | $1.9M | — | — → — | $309/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| HT ASSOCIATES | 4 | 08/10/2026 |
| ROYAL ENGINEERING, P.C | 1 | 03/22/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| HAOTIAN & ASSOCIATES INC. | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HT BUILDS LLC | General Contractor | 1 | 07/08/2026 |
| TOTAL NY CONSTRUCTION CORP | General Contractor | 1 | 07/08/2026 |
| VILLAGE P & H NY INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| FLUSHING ENGINEERING SERV | 4373 | 4 | 08/10/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | VILLAGE P & H NY INC | 06/08/2026 |
| DOB NOW | General Construction | Permit Issued | HT BUILDS LLC | 05/08/2026 |
| DOB NOW | Sidewalk Shed | Signed-off | TOTAL NY CONSTRUCTION COR | 03/23/2018 |
| BIS | FP | ISSUED | MEGA MECHANICAL INC | 12/20/2017 |
| BIS | PL | ISSUED | KATAN P & H INC | 08/04/2017 |
| BIS | OT | ISSUED | E&J ALL SEASONS CONSTRUCT | 07/26/2017 |
| BIS | PL | ISSUED | JOE TRUC_PLBG INC | 04/01/2002 |
| BIS | — | ISSUED | MEDITERRANEAN CONSTRUCTION CORP | 10/11/2001 |
| BIS | EQ | ISSUED | MEDITERRANEAN CONSTRUCTION CORP | 01/04/2001 |
| BIS | — | RE-ISSUED | MEDITERRANEAN CONSTRUCTION CORP | 01/04/2001 |
| BIS | EQ | ISSUED | N.B.I. EQUIPMENT CORP. | 05/21/1993 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/11/2026 | Permit Issued | R & T ELECTRICAL CORP | General Wiring |
| 03/23/2018 | Complete | MEO ELECTRIC CORP | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/20/2026 | Interior lighting power | KY FU | energy_progress |
| 08/20/2026 | Fire-Resistant Penetrations and Joints | KY FU | special |
| 08/20/2026 | Tenant Protection Plan Compliance | KY FU | special |
| 08/20/2026 | Energy Code Compliance Inspections | KY FU | progress |
| 08/20/2026 | Fire-Resistance Rated Construction | KY FU | progress |
| 08/20/2026 | Lighting controls | KY FU | energy_progress |
| 07/31/2026 | Interior lighting power | KY FU | energy_progress |
| 07/31/2026 | Fire-Resistant Penetrations and Joints | KY FU | special |
| 07/31/2026 | Tenant Protection Plan Compliance | KY FU | special |
| 07/31/2026 | Energy Code Compliance Inspections | KY FU | progress |
| 07/31/2026 | Fire-Resistance Rated Construction | KY FU | progress |
| 07/31/2026 | Lighting controls | KY FU | energy_progress |
| 05/20/2026 | Energy Code Compliance Inspections | KY FU | progress |
| 05/20/2026 | HVAC-R and service water piping design and insulation | KY FU | energy_progress |
| 05/20/2026 | Fire-Resistant Penetrations and Joints | KY FU | special |
| 05/20/2026 | Sprinkler Systems | KY FU | special |
| 05/14/2026 | Tenant Protection Plan Compliance | KY FU | special |
| 01/21/2026 | Tenant Protection Plan Compliance | KY FU | special |