← Back
Public elementary, junior or senior high
Fannie Lou Hamer Middle School
1001 JENNINGS STREET · BIN 2010916
💬 Discuss this project
1924Year Built
5Stories
W1Building Class
R7-1Zoning
120,110 sfGross Floor Area
1Units
LL97 Covered26 Open Violations 2 unresolved · 24 paperwork only ▸
Public elementary, junior or senior high · Owner of record: NYC DEPARTMENT OF EDUCATION · 58,000 sf lot · 2.07 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Floor 47p · 1 filing · 19 docs
Floor 3
Floor 2
Floor 12p · 1 filing · 6 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NEW YORK CITY PUBLIC SCHOOL108/28/2026
NYC DEPARTMENT OF EDUCATION103/22/2026
DEPARTMENT OF EDUCATION1703/22/2026
D.O.E. 0203/22/2026
DEPT OF EDUCATION PS 166103/22/2026
DEPT OF EDUCATION P.S.066303/22/2026
DEPT OF EDUCATION P.S.66103/22/2026
DOE PS 66903/22/2026
P.S. 66 D.O.E.903/22/2026
P.S.86 D O E103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
EME GROUP/SALAS O'BRIEN206/17/2026
PAGNAMENTA TORRIANI ARCHITECTS PLAN210/11/2022
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NEW LOOK CONSTRUCTION*General Contractor503/26/2026
LITEHOUSE BUILDERS INCGeneral Contractor303/21/2026
OLYMPIC PLBG & HTG SVC INPlumbing307/08/2026
CHARAN ELEC'L ENTERP'S INElectrical203/22/2026
CRAIG GILSTONElectrical203/21/2026
THOMAS STONEElectrical203/21/2026
ROBERT PARCHMENT P&H.INCPlumbing207/08/2026
PARALLEL PLBG & HTG CO INElectrical103/21/2026
PANTELIDIS, ALEXANDERElectrical103/21/2026
RICHARDSON, WElectrical103/21/2026
HOLDER, ANCILElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
FUTURE TECH CONSULTANTS O589210/11/2022
Building Lifecycle
All (107)Filed (4)Permit Issued (6)Violation (60)Inspection (5)Objection (6)Special Inspection (26)
08/26/2026
Objection resolved — Resolved
08/25/2026
Objection raised — Other
07/15/2026
Violation issued (ECB, open)
Construction
07/15/2026
Violation issued (ECB, open)
Construction
07/15/2026
Violation issued (ECB, open)
Construction
07/15/2026
Violation issued (ECB, open)
Construction
07/15/2026
Objection resolved — Addressed
07/10/2026
Objection raised — Other
06/17/2026
Filed — Alteration
INSTALLATION OF NEW SUPPLEMENTAL AC SYSTEM IN FIRST FLOOR KITCHEN
X01374056-P1
05/27/2026
Special inspection requirement — HVAC-R and service water heating system controls
Asma Hashmi
05/27/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
05/27/2026
Special inspection requirement — Mechanical Systems
05/27/2026
Special inspection requirement — Post-installed Anchors
05/27/2026
Special inspection requirement — Energy Code Compliance Inspections
Asma Hashmi
05/27/2026
Special inspection requirement — Final
Asma Hashmi
05/27/2026
Special inspection requirement — HVAC-R and service water heating equipment
Asma Hashmi
05/27/2026
Special inspection requirement — Maintenance information
Asma Hashmi
05/27/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Asma Hashmi
03/27/2026
Filed — Alteration
INSTALLATION OF NEW SUPPLEMENTAL AC SYSTEM IN FIRST FLOOR KITCHEN
X01374056-I1
03/27/2026
Special inspection requirement — Maintenance information
Asma Hashmi
03/27/2026
Special inspection requirement — HVAC-R and service water heating system controls
Asma Hashmi
03/27/2026
Special inspection requirement — HVAC-R and service water heating equipment
Asma Hashmi
03/18/2026
Special inspection requirement — Mechanical Systems
03/18/2026
Special inspection requirement — Energy Code Compliance Inspections
Asma Hashmi
03/18/2026
Special inspection requirement — Final
Asma Hashmi
03/18/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Asma Hashmi
03/18/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
03/18/2026
Special inspection requirement — Post-installed Anchors
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/19/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
09/10/2025
Violation issued (ECB, closed)
Construction
09/10/2025
Violation issued (ECB, open)
Construction
09/10/2025
Violation issued (ECB, open)
Construction
09/10/2025
Violation issued (ECB, open)
Construction
06/30/2025
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
05/14/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/13/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
05/08/2025
Permit issued — Plumbing
X08016221-S1-PL
02/07/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
09/11/2024
Violation issued (ECB, open)
Construction
09/11/2024
Violation issued (ECB, closed)
Construction
09/11/2024
Violation issued (ECB, open)
Construction
08/06/2024
Permit issued — General Construction
X08016221-I1-GC
03/21/2024
Permit issued — Plumbing
X08016221-S1-PL
11/30/2023
Permit issued — General Construction
X08016221-I1-GC
09/15/2023
Permit issued — Plumbing
X08016221-S1-PL
08/07/2023
Permit issued — General Construction
X08016221-I1-GC
02/01/2023
Violation issued (ECB, open)
Construction
10/20/2022
Objection raised — Other
10/20/2022
Objection resolved — Addressed
10/11/2022
Filed — Alteration
Replace 2 existing fountain with 1 new drinking fountain and 2 ADA compliant drinking fountains and and related plumbing lines at Fourth Floor Corridor. - NO CHANGE IN USE - NO CHANGE IN OCCUPANCY - NO CHANGE IN EGRESS - NO CHANGE IN VENTILATION
X08016221-S1
10/11/2022
Filed — Alteration
Replace 2 existing fountain with 1 new drinking fountain and 2 ADA compliant drinking fountains and and related plumbing lines at Fourth Floor Corridor. - NO CHANGE IN USE - NO CHANGE IN OCCUPANCY - NO CHANGE IN EGRESS - NO CHANGE IN VENTILATION
X08016221-I1
10/11/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Noel Tolentino
10/05/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Noel Tolentino
10/05/2022
Special inspection requirement — Post-installed Anchors
Noel Tolentino
10/05/2022
Special inspection requirement — Energy Code Compliance Inspections
Michael Marchese
10/05/2022
Special inspection requirement — Fire-Resistance Rated Construction
Michael Marchese
10/05/2022
Special inspection requirement — Exterior lighting power
Michael Marchese
10/05/2022
Special inspection requirement — Lighting controls
Michael Marchese
Latest 60 of 107 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offOLYMPIC PLBG & HTG SVC IN05/08/2025
DOB NOWGeneral ConstructionPermit IssuedLITEHOUSE BUILDERS INC08/06/2024
DOB NOWPlumbingSigned-offROBERT PARCHMENT P&H.INC03/21/2024
DOB NOWGeneral ConstructionPermit IssuedNEW LOOK CONSTRUCTION*11/30/2023
DOB NOWPlumbingSigned-offROBERT PARCHMENT P&H.INC09/15/2023
DOB NOWGeneral ConstructionPermit IssuedNEW LOOK CONSTRUCTION*08/07/2023
BISMHISSUEDTAMEER INC01/08/2020
BISPLISSUEDVARSITY PLBG AND HTG INC03/23/2017
BISOTISSUED2 SAAB CONSTRUCTION INC01/13/2017
BISOTISSUEDFIVE STAR ELECTRIC CORP06/26/2014
BISMHISSUEDMIDTOWN HVAC ENTERPRISES05/09/2012
BISMHISSUEDMIDTOWN HVAC ENTERPRISES12/09/2011
BISOTISSUEDGAZEBO CONTRACTING INC04/26/2011
BISPLISSUEDWITTMANN PLBG ASSOC INC03/29/2011
BISOTISSUEDWHITESTONE CONSTRUCTION CORP02/04/2011
BISOTISSUEDGAZEBO CONTRACTING INC03/19/2010
BISPLISSUEDVARSITY PLBG AND HTG INC08/07/2009
BISOTISSUEDWHITESTONE CONSTRUCTION CORP07/17/2009
BISEQISSUEDWHITESTONE CONSTRUCTION CORP04/02/2009
BISEQISSUEDWHITESTONE CONSTRUCTION CORP04/02/2009
BISEQISSUEDWHITESTONE CONSTRUCTION CORP04/02/2009
BISEQISSUEDWHITESTONE CONSTRUCTION CORP12/15/2008
BISEQISSUEDWHITESTONE CONSTRUCTION CORP12/15/2008
BISOTISSUEDWHITESTONE CONSTRUCTION CORP07/31/2008
BISMHISSUEDACS SYSTEMS ASSOCIATES INC07/08/2008
BISEQRE-ISSUEDWHITESTONE CONSTRUCTION CORP.05/07/2008
BISEQISSUEDACE SCAFFOLD CO INC09/21/2006
BISCCISSUEDGAZEBO CONTRACTING CORP.09/21/2006
BISOTISSUEDGAZEBO CONTRACTING CORPORATION08/25/2006
BISOTISSUEDWHITESTONE CONSTRUCTION CORP12/14/2005
BISOTISSUEDRICKENS CONSTRUCTION, INC09/26/2005
BISMHISSUEDFORSYTHE PLUMBING & HEATING CORP09/14/2005
BISOTISSUEDWHITESTONE CONSTRUCTION CORP09/29/2004
BISOTISSUEDWHITESTONE CONSTRUCTION CORP09/23/2003
BISOTISSUEDALPS MECHANICAL INCORPORATED08/03/2001
BISFBISSUEDDENNIS LEDUC08/03/2001
BISOTISSUEDWHITESTONE CONSTRUCTION CORP07/25/2001
BISEQISSUEDROCKLEDGE SCAFFOLD CORP05/31/2001
BISPLISSUEDA BERWIND PLUMBING & HEATING COM11/20/2000
BISPLISSUEDALPS PLUMBING , INC.11/20/2000
+ 10 more permits on file
1 project · most recent 06/17/2026
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
06/17/2026——Air Conditioning Systems
Cooling
Lg LG ZRNU303SRAA 30,000 BTU · Vrf Indoor ×4
LG ZRNU363SRAA 35,000 BTU · Vrf Indoor ×1
LG ZRUM036GSS0 36,000 BTU · Vrf Outdoor ×1
LG ZRUM060GSSO 60,000 BTU · Vrf Outdoor ×2
1 project · most recent 10/11/2022
Water/Sanitary
FiledStatusContractorScope
10/11/2022Signed-offOLYMPIC PLBG & HTG SVC INWater/Sanitary
14 projects · most recent 09/24/2026
General Wiring
FiledStatusContractorScope
09/24/2026CompleteGEMINI ELECTRIC CO., INC.—
08/27/2026Permit IssuedA & S ELECTRIC INC.General Wiring
12/17/2025CompleteCHARAN ELEC'L ENTERP'S INGeneral Wiring
10/18/2024CompleteGILSTON ELEC'L CONTNG LLCGeneral Wiring
11/20/2023CompleteFALCON ELEC'L CONTR'G CORGeneral Wiring
08/30/2023CancelledMNBC ELECTRICAL CORPGeneral Wiring
02/12/2023CompleteGEMINI ELECTRIC CO., INC.—
03/16/2022CompleteCHARAN ELEC'L ENTERP'S IN—
12/10/2021CompleteCHARAN ELEC'L ENTERP'S IN—
04/07/2021CompleteG & F.A.ST ELECTRIC INCGeneral Wiring
03/20/2020CompleteCHARAN ELEC'L ENTERP'S IN—
07/10/2019CompleteCHARAN ELEC'L ENTERP'S IN—
04/15/2019CompleteCHARAN ELEC'L ENTERP'S IN—
05/10/2018CompletePRINCE ELECTRIC CORP.—
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
09/19/2025Pass-Final CND-Occupancy InspectionPassView ↗
06/30/2025Fail-Final CND-Occupancy InspectionFailView ↗
05/14/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/13/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/07/2025Pass-Final CND-Occupancy InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 26
DateRequirementInspectorRole
05/27/2026HVAC-R and service water heating system controlsAsma Hashmienergy_progress
05/27/2026Fire-Resistant Penetrations and Joints—special
05/27/2026Mechanical Systems—special
05/27/2026Post-installed Anchors—special
05/27/2026Energy Code Compliance InspectionsAsma Hashmiprogress
05/27/2026FinalAsma Hashmiprogress
05/27/2026HVAC-R and service water heating equipmentAsma Hashmienergy_progress
05/27/2026Maintenance informationAsma Hashmienergy_progress
05/27/2026HVAC-R and service water piping design and insulationAsma Hashmienergy_progress
03/27/2026Maintenance informationAsma Hashmienergy_progress
03/27/2026HVAC-R and service water heating system controlsAsma Hashmienergy_progress
03/27/2026HVAC-R and service water heating equipmentAsma Hashmienergy_progress
03/18/2026Mechanical Systems—special
03/18/2026Energy Code Compliance InspectionsAsma Hashmiprogress
03/18/2026FinalAsma Hashmiprogress
03/18/2026HVAC-R and service water piping design and insulationAsma Hashmienergy_progress
03/18/2026Fire-Resistant Penetrations and Joints—special
03/18/2026Post-installed Anchors—special
10/11/2022Fire-Resistant Penetrations and JointsNoel Tolentinospecial
10/05/2022Fire-Resistant Penetrations and JointsNoel Tolentinospecial
10/05/2022Post-installed AnchorsNoel Tolentinospecial
10/05/2022Energy Code Compliance InspectionsMichael Marcheseprogress
10/05/2022Fire-Resistance Rated ConstructionMichael Marcheseprogress
10/05/2022Exterior lighting powerMichael Marcheseenergy_progress
10/05/2022Lighting controlsMichael Marcheseenergy_progress
Latest 25 of 26.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
P.S. 66 - School of Higher ExpectationsEducationFloor 1
Project X01374056 Alteration · Plan Examiner Review · 03/27/2026
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 75 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/23/2026X08016221-I1Request digital key ↗
08/17/2026X01374056-I1Request digital key ↗
08/15/2026X01374056-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits11
▸BISPLAN / WORK APPROVAL APPLICATION8
01/05/2026220531342Open ↗
07/17/2025220531342Open ↗
04/06/2020220531324Open ↗
Showing 3 of 8 on file for this type
▸BISWORK PERMIT APPLICATION3
01/08/2020220531324Open ↗
03/23/2017220531324Open ↗
01/17/2017220531324Open ↗
▸Seals & Professional Certifications19
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION6
01/09/2020220531324Open ↗
03/28/2019220659589Open ↗
01/12/2017220531324Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/17/2026X01374056-P1Open ↗
08/17/2026X01374056-I1Open ↗
08/13/2026X08016221-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
09/01/2026X08016221-I1Open ↗
09/01/2026X08016221-I1Open ↗
09/01/2026X08016221-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
03/28/2019220659589Open ↗
05/20/2016220531324Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
03/28/2019220659589Open ↗
05/20/2016220531324Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026X08016221-I1Open ↗
08/24/2026X08016221-S1Open ↗
▸Trade Schedules & Equipment2
▸BISFA - FDNY APPROVAL : FD-FAA1
01/10/2018220531342Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
05/20/2016220531324Open ↗
▸Environmental & Asbestos3
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)2
08/22/2025220531342Open ↗
01/17/2017220531324Open ↗
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
01/15/2020220531324Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
01/09/2020220531324Open ↗
01/09/2020220531324Open ↗
01/12/2017220531324Open ↗
Showing 3 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS1
01/09/2020220531324Open ↗
▸Approvals, Objections & Sign-offs12
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter4
08/17/2026X01374056-I1Open ↗
08/15/2026X01374056-P1Open ↗
08/13/2026X08016221-I1Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
01/13/2021220531324Open ↗
02/10/2020220531324Open ↗
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)2
08/13/2026X08016221-I1Open ↗
08/13/2026X08016221-S1Open ↗
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)2
08/13/2026X08016221-I1Open ↗
08/13/2026X08016221-S1Open ↗
▸DOB NOWDEP Variance (V5) letter2
08/13/2026X08016221-I1Open ↗
08/13/2026X08016221-S1Open ↗
▸Cost, Insurance & Ownership7
▸BISCOST AFFIDAVIT6
02/10/2020220531324Open ↗
01/09/2020220531324Open ↗
01/09/2020220531324Open ↗
Showing 3 of 6 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
04/24/2025220531342Open ↗
▸Filing & Intake Forms10
▸BISEFILING COVER SHEET5
04/06/2020220531324Open ↗
03/28/2019220659589Open ↗
05/20/2016220531324Open ↗
Showing 3 of 5 on file for this type
▸BISBOROUGH INTAKE FORM3
02/10/2020220531324Open ↗
01/15/2020220531324Open ↗
01/09/2020220531324Open ↗
▸BISADDITIONAL INFORMATION2
08/22/2025220531342Open ↗
11/18/2019220531324Open ↗
▸Other Documents2
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal2
08/13/2026X08016221-I1Open ↗
08/13/2026X08016221-S1Open ↗