← Back
BuildNYC
Elevator cooperative
1001 PARK AVENUE
MANHATTAN · BIN 1047668
💬 Discuss this project
1929Year Built
14Stories
D4Building Class
R10Zoning
68,569 sfGross Floor Area
23Units
LL97 CoveredRent Stabilized0 Active Violations 1 old, status unconfirmed ▸FISP: SWARMP
Elevator cooperative · 5,823 sf lot · 11.78 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Whole building & multi-floor projectsBooster pump installation2 filings
RoofExterior masonry facade repairs and partial chimney reconstr1p · 1 filing · 12 docs
PenthouseUnit PH2 filings · 20 docs
Floor 172p · 2 filings · 20 docs
Floor 162p · 2 filings · 20 docs
Floor 15Plumbing modifications for apartment 6K2 filings · 16 docs
Floor 14
Floor 13
Floor 12
Floor 11
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6Core Development Group LLC1 filing · 8 docs
Floor 5
Floor 42 filings · 8 docs
Floor 3Unit 3N, Unit 4N3 filings · 8 docs
Floor 2Exterior masonry facade repairs and partial chimney reconstr1p · 1 filing · 12 docs
Floor 1Tenant amenity fitness roomUnder Construction4p · 1 filing · 20 docs
Site & exteriorExterior masonry facade repairs and partial chimney reconstr4 filings · 16 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
1001 Tenants5803/21/2026
Core Development Group1207/08/2026
NYC Department of Housing Preservation and Development103/21/2026
Matthew Adams Properties103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Rmba603/21/2026
Synergy Building Consultants203/21/2026
AE Design Solution1003/21/2026
Boyd Consulting403/21/2026
J Callahan Consulting803/21/2026
Outsource Consultants603/21/2026
Rip CC203/21/2026
Blanco Design1003/21/2026
Sol Building Consulting Services103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Nova Construction ServiceScaffold1607/08/2026
Alphacraft Construction*General Contractor707/08/2026
Velocity Plumbing & HeatingPlumbing607/08/2026
Nova Construction ServiceGeneral Contractor603/21/2026
FanukaGeneral Contractor307/08/2026
A to Z Construction GroupGeneral Contractor303/21/2026
Donato PlumbingPlumbing207/08/2026
McCormack ContractingGeneral Contractor209/23/2026
K & G Electric CoElectrical103/22/2026
DPH Plumbing & HeatingPlumbing107/08/2026
Metrotech MechanicalPlumbing110/03/2026
Gary ElectricElectrical103/21/2026
Norlin Electrical ContractorsElectrical103/21/2026
Banner ElectricElectrical103/22/2026
RG Decorating & Paintingspecialty_contractor104/09/2026
Ceprine ConstructionScaffold107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ALLEN+KILLCOYNE Architect2697409/03/2026
Jack Green Associates422108/04/2026
PSI Agency254106/09/2026
ADS Special Inspections1270105/12/2025
Hyke Engineering & Management2422503/21/2024
CES Engineering1277105/12/2021
TSF Engineering1274104/15/2020
William Madden Engineering4423503/23/2020
Outsource Special Inspection2827112/06/2019
Building Lifecycle
02/20/2029
Facade inspection report due (FISP Cycle 9, sub-cycle C)
The filing window opened 02/21/2027. No Cycle 9 filing on record yet
10/02/2026
Permit issued — Plumbing
M01411021-S1-PL
09/22/2026
Permit issued — Mechanical Systems
M01411021-S2-MS
09/21/2026
Permit issued — General Construction
M01411021-I1-GC
09/11/2026
Objection resolved — Addressed
214 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedMetrotech Mechanical10/02/2026
DOB NOWMechanical SystemsPermit IssuedMcCormack Contracting09/22/2026
DOB NOWGeneral ConstructionPermit IssuedMcCormack Contracting09/21/2026
DOB NOWGeneral ConstructionPermit IssuedRG Decorating & Painting08/20/2025
DOB NOWProtection and Mechanical MethodsSigned-offNova Construction Service07/05/2023
DOB NOWGeneral ConstructionSigned-offNova Construction Service07/05/2023
DOB NOWSupported ScaffoldSigned-offNova Construction Service07/01/2023
DOB NOWSidewalk ShedSigned-offNova Construction Service06/23/2023
DOB NOWPlumbingSigned-offVelocity Plumbing & Heating02/16/2023
DOB NOWProtection and Mechanical MethodsSigned-offNova Construction Service07/22/2022
DOB NOWGeneral ConstructionSigned-offNova Construction Service07/15/2022
DOB NOWSupported ScaffoldSigned-offNova Construction Service07/12/2022
DOB NOWSidewalk ShedSigned-offNova Construction Service07/01/2022
DOB NOWPlumbingSigned-offVelocity Plumbing & Heating04/19/2022
DOB NOWMechanical SystemsSigned-offAlphacraft Construction*02/21/2022
DOB NOWMechanical SystemsSigned-offAlphacraft Construction*11/10/2021
DOB NOWPlumbingSigned-offVelocity Plumbing & Heating07/21/2021
DOB NOWMechanical SystemsSigned-offAlphacraft Construction*05/28/2021
DOB NOWPlumbingSigned-offVelocity Plumbing & Heating05/27/2021
DOB NOWPlumbingSigned-offVelocity Plumbing & Heating04/08/2021
DOB NOWMechanical SystemsSigned-offAlphacraft Construction*02/11/2021
DOB NOWPlumbingSigned-offDonato Plumbing01/25/2021
DOB NOWMechanical SystemsSigned-offFanuka11/20/2020
DOB NOWMechanical SystemsSigned-offA to Z Construction Group06/08/2020
DOB NOWMechanical SystemsSigned-offAlphacraft Construction*02/14/2020
DOB NOWMechanical SystemsSigned-offFanuka02/13/2020
DOB NOWPlumbingSigned-offVelocity Plumbing & Heating02/13/2020
DOB NOWPlumbingSigned-offDonato Plumbing01/21/2020
DOB NOWPlumbingPermit IssuedDPH Plumbing & Heating11/27/2019
DOB NOWSidewalk ShedSigned-offCeprine Construction03/09/2019
BISOTISSUEDAlphacraft Construction*02/24/2022
BISOTISSUEDAlphacraft Construction*02/08/2021
BISPLISSUEDPace Plumbing12/09/2020
BISOTISSUEDFanuka11/18/2020
BISOTISSUEDGDC Contracting08/27/2020
BISMHISSUEDGDC Contracting08/27/2020
BISOTISSUEDRoyal Renovation03/03/2020
BISOTISSUEDAlphacraft Construction*02/11/2020
BISOTISSUEDAlphacraft Construction*02/07/2020
BISPLISSUEDWalter J.grande P & H01/24/2020
+ 40 more permits on file
1 project · most recent 03/23/2020
Air Conditioning Systems Heating Systems
FiledStatusContractorScope
03/23/2020——Air Conditioning Systems, Heating Systems
2 projects · most recent 09/03/2026
Gas Water/Sanitary
FiledStatusContractorScope
09/03/2026Permit IssuedMetrotech MechanicalGas, Water/Sanitary
03/23/2020Permit IssuedDPH Plumbing & HeatingGas, Water/Sanitary
19 projects · most recent 08/27/2026
General Wiring Lighting
FiledStatusContractorScope
08/27/2026CompleteP.S. Marcato Elev. Co—
06/02/2025CompleteJ.G.C. ElectricGeneral Wiring
03/14/2025CompleteK & G Electric CoGeneral Wiring
11/26/2024Permit IssuedK & G Electric CoGeneral Wiring
08/05/2024CompleteL.J.F. & Sons Electrical ContsGeneral Wiring
08/03/2022Permit IssuedK & G Electric CoGeneral Wiring
07/18/2022CompleteAbilene Electric—
05/28/2021CompleteBanner ElectricGeneral Wiring
06/24/2020CompleteAccurate ElectricalGeneral Wiring
02/14/2020CompleteK & G Electric Co—
02/10/2020CompleteAster ElectricGeneral Wiring
02/05/2020CompleteBanner ElectricGeneral Wiring
01/08/2020CompleteAmra ElectricalGeneral Wiring
11/12/2019CompleteApollo ElectricGeneral Wiring, Lighting
11/07/2019CompleteRome Electrical ContsGeneral Wiring
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
05/02/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/07/2021Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
10/06/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/24/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 66
DateRequirementInspectorRole
09/08/2026Lighting controlsDaniel Allenenergy_progress
09/08/2026Fire-Resistant Penetrations and JointsDaniel Allenspecial
09/08/2026Post-installed AnchorsMAURICIO ANDRADEspecial
09/08/2026Energy Code Compliance InspectionsDaniel Allenprogress
09/08/2026Interior lighting powerDaniel Allenenergy_progress
09/03/2026Post-installed Anchors—special
09/03/2026Fire-Resistant Penetrations and JointsDaniel Allenspecial
09/03/2026Lighting controlsDaniel Allenenergy_progress
09/03/2026Interior lighting powerDaniel Allenenergy_progress
09/03/2026Energy Code Compliance InspectionsDaniel Allenprogress
07/27/2026Maintenance information—energy_progress
07/27/2026HVAC-R and service water heating equipment—energy_progress
07/27/2026HVAC-R and service water heating system controls—energy_progress
07/27/2026Duct leakage testing, insulation and design—energy_progress
07/27/2026HVAC-R and service water piping design and insulation—energy_progress
07/27/2026Energy Code Compliance Inspections—progress
07/27/2026Shutoff dampers—energy_progress
07/21/2026Fire-Resistant Penetrations and Joints—special
07/15/2026Fire-Resistant Penetrations and JointsDaniel Allenspecial
07/14/2026Final—progress
07/14/2026Mechanical Systems—special
01/22/2025Fire-Resistant Penetrations and JointsBRIAN O'ROURKEspecial
01/22/2025Tenant Protection Plan ComplianceBRIAN O'ROURKEspecial
01/22/2025Fire-Resistance Rated Constructionjamal tahaprogress
01/22/2025Finaljamal tahaprogress
Latest 25 of 66.
690 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account