| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/04/2026 | Complete | K.A.B. ELECTRIC CORP | General Wiring |
| 02/20/2025 | Complete | K.A.B. ELECTRIC CORP | General Wiring |
| 10/25/2024 | Complete | RICHARD NEU | — |
| Owner | Filings | Most Recent |
|---|---|---|
| NEW AREA CONSTRUCTION | 16 | 07/08/2026 |
| ALPHA SCAFFOLDING INC | 5 | 03/22/2026 |
| J & K 116TH STREET LLC | 1 | 03/22/2026 |
| PRIME CONSTRUCTION USA | 15 | 03/22/2026 |
| OWNER OF 114-20 101 AVE | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/25/2015 | $571K | — | Private party → J & K 116TH STREET LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| PIROOZ ENGINEERING, P.C. | 6 | 05/16/2025 |
| ARQUITECTURA VARELA | 1 | 10/15/2024 |
| DAVID REYHAN PE | 1 | 06/03/2024 |
| ROYAL ENGINEERING, P.C | 1 | 08/12/2019 |
| MEHRABAN AHOURAIE | 1 | 08/12/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| PIROOZ ENGINEERING P C | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PRIME CONSTRUCTION USA | General Contractor | 14 | 07/08/2026 |
| ALPHA SCAFFOLDING INC | General Contractor | 3 | 03/21/2026 |
| NEW AREA CONSTRUCTION INC | General Contractor | 2 | 03/21/2026 |
| RICHARD NEU | Electrical | 1 | 03/22/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 1 | 07/08/2026 |
| ZONE PLUMBING & HEATING C | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AA BUILDING & INSPECTION | 1519 | 3 | 05/16/2025 |
| SJS INSPECTIONS AND CONSU | 8286 | 7 | 05/16/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | NEW AREA CONSTRUCTION INC | 08/07/2025 |
| DOB NOW | Plumbing | Signed-off | A M B MECHANICAL INC | 04/16/2025 |
| DOB NOW | General Construction | Permit Issued | PRIME CONSTRUCTION USA | 12/23/2024 |
| DOB NOW | Construction Fence | Signed-off | PRIME CONSTRUCTION USA | 12/23/2024 |
| DOB NOW | Structural | Signed-off | PRIME CONSTRUCTION USA | 12/20/2024 |
| DOB NOW | General Construction | Permit Issued | PRIME CONSTRUCTION USA | 12/12/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | ALPHA SCAFFOLDING INC | 10/28/2024 |
| DOB NOW | Plumbing | Signed-off | ZONE PLUMBING & HEATING C | 09/17/2024 |
| DOB NOW | Structural | Signed-off | PRIME CONSTRUCTION USA | 07/12/2024 |
| DOB NOW | General Construction | Permit Issued | PRIME CONSTRUCTION USA | 07/12/2024 |
| DOB NOW | Curb Cut | Permit Issued | PRIME CONSTRUCTION USA | 07/12/2024 |
| DOB NOW | Construction Fence | Signed-off | PRIME CONSTRUCTION USA | 02/29/2024 |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/22/2026 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 11/18/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 10/21/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 05/16/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/30/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/27/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/08/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 11/08/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 11/08/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/08/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/04/2025 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | Younes Abouyaala | special |
| 06/04/2025 | HVAC insulation and sealing | SERGEY BOLOTOV | energy_progress |
| 06/04/2025 | HVAC and service water heating equipment | SERGEY BOLOTOV | energy_progress |
| 06/04/2025 | Sprinkler Systems | SERGEY BOLOTOV | special |
| 06/04/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | SERGEY BOLOTOV | special |
| 06/04/2025 | HVAC and service water heating system controls | SERGEY BOLOTOV | energy_progress |
| 10/22/2024 | Subsurface Investigations (Borings/Test Pits) | Younes Abouyaala | special |
| 10/22/2024 | Energy Code Compliance Inspections | SERGEY BOLOTOV | progress |
| 10/22/2024 | Fire-Resistance Rated Construction | SERGEY BOLOTOV | progress |
| 10/22/2024 | Preliminary | SERGEY BOLOTOV | progress |
| 10/22/2024 | Air barrier — testing | SERGEY BOLOTOV | energy_progress |
| 10/22/2024 | Air barrier - visual inspection | SERGEY BOLOTOV | energy_progress |
| 10/22/2024 | Lighting in dwelling units | SERGEY BOLOTOV | energy_progress |
| 10/22/2024 | Fenestration and door U-factor and product ratings | SERGEY BOLOTOV | energy_progress |
| 10/22/2024 | Maintenance information | SERGEY BOLOTOV | energy_progress |
| 10/22/2024 | HVAC-R and service water piping design and insulation | SERGEY BOLOTOV | energy_progress |
| 10/22/2024 | Fenestration areas | SERGEY BOLOTOV | energy_progress |
| 10/22/2024 | Fenestration air leakage | SERGEY BOLOTOV | energy_progress |
| 10/22/2024 | Metering | SERGEY BOLOTOV | energy_progress |
| 10/22/2024 | HVAC-R and service water heating system controls | SERGEY BOLOTOV | energy_progress |
| 10/22/2024 | HVAC-R and service water heating equipment | SERGEY BOLOTOV | energy_progress |
| 10/22/2024 | Insulation placement and R values | SERGEY BOLOTOV | energy_progress |
| 10/22/2024 | Protection of exposed foundation insulation | SERGEY BOLOTOV | energy_progress |
| 10/22/2024 | Lighting controls | SERGEY BOLOTOV | energy_progress |
| 10/22/2024 | Interior lighting power | SERGEY BOLOTOV | energy_progress |