← Back
One family attached or semi-detached
101-41 75 ROAD
QUEENS · BIN 4078476
💬 Discuss this project
1925Year Built
2.5Stories
A5Building Class
R3-1Zoning
1,568 sfGross Floor Area
1Units
1 Open Violation 0 unresolved · 1 paperwork only ▸
One family attached or semi-detached · 2,283 sf lot · 0.69 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
1 job · most recent 06/19/2025
Concrete Masonry
FiledStatusContractorScope
06/19/2025——Concrete, Masonry
Building Lifecycle
All (34)Filed (2)Violation (1)Objection (30)Special Inspection (1)
05/19/2026
Objection resolved — Addressed
05/19/2026
Objection resolved — Addressed
05/19/2026
Objection resolved — Addressed
03/24/2026
Objection resolved — Addressed
03/24/2026
Objection resolved — Addressed
03/24/2026
Objection resolved — Addressed
03/24/2026
Objection resolved — Addressed
02/06/2026
Objection raised — Zoning
02/06/2026
Objection raised — Scope
02/06/2026
Objection resolved — Resolved
12/30/2025
Objection resolved — Addressed
11/15/2025
Filed — Alteration
WORK FILED TO SHOW THE REMOVAL OF THE ENCLOSED PORCH/SUNROOM AT REAR OF THE BUILDING USING THE MANUAL OPERATIONS ONLY, NO MECHANICAL EQUIPMENT PROPOSED. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
Q01302403-I1
10/14/2025
Special inspection requirement — Final
CARL HAMANN
09/25/2025
Objection raised — Plumbing
09/25/2025
Objection raised — Zoning
09/04/2025
Objection resolved — Open
09/04/2025
Objection resolved — Resolved
09/04/2025
Objection resolved — Addressed
09/04/2025
Objection resolved — Addressed
09/03/2025
Objection resolved — Addressed
09/02/2025
Objection resolved — Addressed
07/13/2025
Objection raised — Zoning
07/13/2025
Objection raised — Admin
07/07/2025
Objection raised — Plumbing
07/07/2025
Objection raised — Zoning
07/07/2025
Objection raised — Structural
07/07/2025
Objection raised — Zoning
07/07/2025
Objection raised — Energy
07/07/2025
Objection raised — Admin
07/07/2025
Objection raised — Scope
07/07/2025
Objection raised — Scope
07/07/2025
Objection raised — Zoning
06/19/2025
Filed — Alteration
Work filed to show the addition of the 2 story extension in the rear of one family house as per plans filed, work proposed on first and second floor. No change in use, egress and occupancy.
Q01227588-I1
10/03/2016
Violation issued (ECB, open)
Construction
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
08/13/2015$325K—Private party → Private party$207/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
HAMANN ENGINEERING, PLLC211/15/2025
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 1
DateRequirementInspectorRole
10/14/2025FinalCARL HAMANNprogress
▾Documents — 13 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/19/2026Q01227588-I1Contact architect ↗
08/18/2026Q01302403-I1Contact architect ↗
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram2
08/19/2026Q01227588-I1Open ↗
08/13/2026Q01227588-I1Open ↗
▸DOB NOWRestrictive Declaration/Easement 11
08/13/2026Q01227588-I1Open ↗
▸Seals & Professional Certifications3
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/19/2026Q01227588-I1Open ↗
08/18/2026Q01302403-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/28/2026Q01302403-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/19/2026Q01227588-I1Open ↗
08/18/2026Q01302403-I1Open ↗
▸Other Documents3
▸DOB NOWSite Survey: Initial1
08/13/2026Q01227588-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026Q01227588-I1Open ↗
▸DOB NOWPlot Diagram1
08/13/2026Q01227588-I1Open ↗