| Owner | Filings | Most Recent |
|---|---|---|
| PIONEER LAW GROUP | 28 | 07/08/2026 |
| ATMOSPHERE DESIGN GROUP, | 17 | 07/08/2026 |
| 101 EAST 63RD ST NY LLC WG S | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/15/2019 | $18.0M | — | Private party → 101 EAST 63RD STREET NYC LLC | $2,449/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| STEVE E BLATZ ARCHITECT PLLC | 10 | 12/30/2024 |
| E4P CONSULTING ENGINEERING PLLC | 7 | 02/01/2023 |
| URBAN INTEGRATIONS | 3 | 09/13/2021 |
| GILSANZ MURRAY STEFICEK LLP | 1 | 03/10/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| UNITED SAFETY CONSULTANTS | 3 | 03/21/2026 |
| OUTSOURCE CONSULTANTS, INC. | 8 | 03/21/2026 |
| AGOUTI CONSTRUCTION CONSULTING | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SHAWMUT WOODWORKING & SUPPLY | General Contractor | 10 | 07/08/2026 |
| SILVERLINING INTERIORS | General Contractor | 6 | 07/08/2026 |
| SPRING SCAFFOLDING LLC | General Contractor | 4 | 07/08/2026 |
| GOLDS PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| HUDSON PLMBING & MCH, LLC | Plumbing | 1 | 07/08/2026 |
| NEW MILLENNIUM P & H CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| STEVE E. BLATZ ARCHITECT | 3634 | 5 | 12/30/2024 |
| INTEGRITY CONSULTING SERV | 666 | 1 | 04/20/2023 |
| HT ENGINEERING, PLLC | 6274 | 2 | 03/19/2020 |
| GILSANZ MURRAY STEFICEK | 240 | 1 | 03/10/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | SILVERLINING INTERIORS | 12/28/2023 |
| DOB NOW | Construction Fence | Signed-off | SILVERLINING INTERIORS | 09/21/2023 |
| DOB NOW | Plumbing | Signed-off | NEW MILLENNIUM P & H CORP | 09/07/2023 |
| DOB NOW | Mechanical Systems | Signed-off | SILVERLINING INTERIORS | 07/24/2023 |
| DOB NOW | General Construction | Signed-off | SILVERLINING INTERIORS | 07/21/2023 |
| DOB NOW | Plumbing | Signed-off | HUDSON PLMBING & MCH, LLC | 10/27/2022 |
| DOB NOW | Mechanical Systems | Signed-off | SHAWMUT WOODWORKING & SUPPLY | 04/20/2022 |
| DOB NOW | Supported Scaffold | Signed-off | SPRING SCAFFOLDING LLC | 05/05/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 05/05/2021 |
| DOB NOW | Plumbing | Signed-off | GOLDS PLUMBING CORP | 02/01/2021 |
| DOB NOW | Structural | Signed-off | SHAWMUT WOODWORKING & SUPPLY | 01/27/2021 |
| DOB NOW | Mechanical Systems | Signed-off | SHAWMUT WOODWORKING & SUPPLY | 01/06/2021 |
| DOB NOW | Structural | Signed-off | SHAWMUT WOODWORKING & SUPPLY | 03/17/2020 |
| DOB NOW | Mechanical Systems | Signed-off | SHAWMUT WOODWORKING & SUPPLY | 10/23/2019 |
| DOB NOW | Mechanical Systems | Signed-off | SHAWMUT WOODWORKING & SUPPLY | 09/11/2019 |
| BIS | OT | ISSUED | SHAWMUT WOODWORKING & SUPPLY | 10/27/2022 |
| BIS | OT | ISSUED | SHAWMUT WOODWORKING & SUPPLY | 10/26/2021 |
| BIS | OT | ISSUED | SHAWMUT WOODWORKING & SUPPLY | 01/05/2021 |
| BIS | OT | ISSUED | SHAWMUT WOODWORKING & SUPPLY | 10/21/2019 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/09/2023 | Complete | AE ELECTRIC INC | — |
| 01/18/2023 | Complete | APOLLO ELECTRIC NYG, INC | General Wiring |
| 04/19/2021 | Complete | TOP SHELF ELECTRIC CORP | — |
| 01/07/2021 | Complete | APOLLO ELECTRIC NYG, INC | — |
| 12/27/2019 | Complete | APOLLO ELECTRIC INC. | General Wiring |
| 11/08/2019 | Complete | APOLLO ELECTRIC INC. | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/02/2025 | Fire-Resistant Penetrations and Joints | Stephen Blatz | special |
| 01/02/2025 | Fire-Resistant Penetrations and Joints | Stephen Blatz | special |
| 01/02/2025 | Final | Stephen Blatz | progress |
| 01/02/2025 | Final | — | progress |
| 12/04/2024 | Fire-Resistant Penetrations and Joints | Stephen Blatz | special |
| 12/04/2024 | Final | — | progress |
| 12/28/2023 | Fire-Resistant Penetrations and Joints | Stephen Blatz | special |
| 12/28/2023 | Final | Stephen Blatz | progress |
| 12/27/2023 | Final | Stephen Blatz | progress |
| 12/27/2023 | Fire-Resistant Penetrations and Joints | Stephen Blatz | special |
| 09/15/2021 | Final | DANNY TRUJILLO | progress |
| 03/19/2020 | Final | HENRY TORRES | progress |
| 03/19/2020 | Mechanical Systems | HENRY TORRES | special |
| 01/08/2020 | Structural Steel - Details | Philip Murray | special |
| 01/08/2020 | Structural Steel - Welding | Philip Murray | special |
| 12/13/2019 | Post-installed Anchors | Philip Murray | special |
| 12/13/2019 | Structural Stability – Alterations of existing buildings | Philip Murray | special |
| 12/13/2019 | Final | Philip Murray | progress |
| 12/06/2019 | Final | HENRY TORRES | progress |
| 12/06/2019 | Mechanical Systems | HENRY TORRES | special |