| Firm | Filings | Most Recent |
|---|---|---|
| Sotir Associates | 3 | 12/05/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DD&G Electrical | Electrical | 1 | 03/22/2026 |
| WCK Electric | Electrical | 1 | 03/21/2026 |
| Stern Abraham | Electrical | 1 | 03/21/2026 |
| Urena Construction & Design | General Contractor | 1 | 04/09/2026 |
| Infiniti Esc Plumbing | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Engineering Consulting SE | 2050 | 2 | 12/05/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | Infiniti Esc Plumbing | 07/18/2025 |
| DOB NOW | General Construction | Signed-off | Urena Construction & Design | 03/19/2025 |
| BIS | OT | ISSUED | Sea Bright Solar | 12/27/2013 |
| BIS | PL | ISSUED | Plumbing P & H | 09/10/2012 |
| BIS | OT | ISSUED | High Power Construction Corp* | 07/12/2012 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/05/2025 | Signed-off | Infiniti Esc Plumbing | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/05/2026 | Complete | DD&G Electrical | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/19/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 12/16/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/15/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/08/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 11/17/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/08/2025 | Fire-Resistant Penetrations and Joints | PAUL MARINO | special |
| 12/08/2025 | Structural Stability – Alterations of existing buildings | PAUL MARINO | special |
| 12/08/2025 | Energy Code Compliance Inspections | PAUL MARINO | progress |
| 12/08/2025 | Permanent certificate | PAUL MARINO | energy_progress |
| 12/08/2025 | Lighting in dwelling units | PAUL MARINO | energy_progress |
| 12/08/2025 | Fenestration and door U-factor and product ratings | PAUL MARINO | energy_progress |
| 12/08/2025 | Fenestration areas | PAUL MARINO | energy_progress |
| 12/08/2025 | Fenestration air leakage | PAUL MARINO | energy_progress |
| 12/05/2025 | Fire-Resistant Penetrations and Joints | PAUL MARINO | special |
| 12/05/2025 | Structural Stability – Alterations of existing buildings | PAUL MARINO | special |
| 12/05/2025 | Energy Code Compliance Inspections | PAUL MARINO | progress |
| 12/05/2025 | Fenestration air leakage | PAUL MARINO | energy_progress |
| 12/05/2025 | Fenestration areas | PAUL MARINO | energy_progress |
| 12/05/2025 | Lighting in dwelling units | PAUL MARINO | energy_progress |
| 12/05/2025 | Fenestration and door U-factor and product ratings | PAUL MARINO | energy_progress |
| 12/05/2025 | Permanent certificate | PAUL MARINO | energy_progress |
| 07/11/2025 | Energy Code Compliance Inspections | Hany Demetry | progress |