← Back
Zoned residential, not Manhattan
1010 UNIVERSITY AVENUE
BRONX · Highbridge · BIN 2816401
💬 Discuss this project
0Year Built
—Stories
V0Building Class
R7-1Zoning
0 sfGross Floor Area
0Units
2 Open Violations 0 unresolved · 2 paperwork only ▸
Zoned residential, not Manhattan · Owner of record: UNIVERS SI LLC · 2,075 sf lot · 0 FAR built · Flood zone X
Locations of Work
StructuralCivil
Permit Issued — active, not yet Signed-off
Floor 2Under Construction32p · 1 filing · 20 docs
Floor 1
Site & exteriorUnder Construction1p · 1 filing · 2 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
DIAMOND DEV GROUP2009/19/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/11/2025$375K—Private party → UNIVERS SI LLC— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ARC ARCHITECTURE + DESIGN STUDIO707/13/2026
TECC SOLUTIONS303/18/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
UGB DESIGN BUILDGeneral Contractor309/19/2026
UGB CONSTRUCTION INCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AMERICAN CONSTRUCTION TES9731703/18/2026
Building Lifecycle
All (60)Filed (10)Permit Issued (4)Violation (2)Objection (14)Special Inspection (30)
09/18/2026
Permit issued — Foundation
X01293919-S8-FO
09/15/2026
Permit issued — Foundation
X01293919-Z1-FO
09/14/2026
Permit issued — Support of Excavation
X01293919-S9-SE
08/31/2026
Objection resolved — Resolved
08/13/2026
Objection resolved — Resolved
08/13/2026
Objection resolved — Resolved
08/11/2026
Objection raised — Other
08/07/2026
Objection raised — Other
08/07/2026
Objection raised — Other
07/13/2026
Filed — New Building
STRUCTURAL WORK FOR 7 STORY RESIDENTIAL NEW BUILDING
X01293919-P3
07/13/2026
Special inspection requirement — Combustible Exterior Wall Coverings
07/13/2026
Special inspection requirement — Energy Code Compliance Inspections
07/13/2026
Special inspection requirement — Maintenance information
07/13/2026
Special inspection requirement — Metering
07/13/2026
Special inspection requirement — Insulation placement and R values
07/13/2026
Special inspection requirement — Air barrier — testing
07/13/2026
Special inspection requirement — Electrical motors and elevators
07/13/2026
Special inspection requirement — Protection of exposed foundation insulation
07/13/2026
Special inspection requirement — Air barrier - visual inspection
07/13/2026
Special inspection requirement — Fire-Resistance Rated Construction
07/13/2026
Special inspection requirement — Exterior lighting power
07/13/2026
Special inspection requirement — Fenestration air leakage
07/13/2026
Special inspection requirement — Interior lighting power
07/13/2026
Special inspection requirement — Fenestration areas
07/13/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
07/13/2026
Special inspection requirement — Lighting in dwelling units
07/13/2026
Special inspection requirement — Concrete - Cast-In-Place
07/13/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
07/13/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
07/13/2026
Special inspection requirement — Lighting controls
07/13/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
04/10/2026
Objection resolved — Addressed
04/09/2026
Objection raised — Admin
04/09/2026
Objection raised — Admin
03/18/2026
Filed — New Building
STRUCTURAL WORK FOR 7 STORY RESIDENTIAL NEW BUILDING
X01293919-S4
03/18/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
EDWIN HOPKINS
03/18/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
EDWIN HOPKINS
03/18/2026
Special inspection requirement — HVAC-R and service water heating system controls
EDWIN HOPKINS
03/18/2026
Special inspection requirement — Maintenance information
EDWIN HOPKINS
03/18/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
EDWIN HOPKINS
03/18/2026
Special inspection requirement — HVAC-R and service water heating equipment
EDWIN HOPKINS
03/16/2026
Filed — New Building
STRUCTURAL WORK FOR 7 STORY RESIDENTIAL NEW BUILDING
X01293919-S5
03/16/2026
Filed — New Building
STRUCTURAL WORK FOR 7 STORY RESIDENTIAL NEW BUILDING
X01293919-S6
03/16/2026
Special inspection requirement — HVAC-R and service water heating system controls
EDWIN HOPKINS
03/16/2026
Special inspection requirement — Ventilation and air distribution system
EDWIN HOPKINS
03/16/2026
Special inspection requirement — HVAC-R and service water heating equipment
EDWIN HOPKINS
02/16/2026
Objection raised — Other
01/28/2026
Filed — New Building
STRUCTURAL WORK FOR 7 STORY RESIDENTIAL NEW BUILDING
X01293919-Z1
01/28/2026
Filed — New Building
STRUCTURAL WORK FOR 7 STORY RESIDENTIAL NEW BUILDING
X01293919-S7
01/28/2026
Filed — New Building
STRUCTURAL WORK FOR 7 STORY RESIDENTIAL NEW BUILDING
X01293919-S8
01/28/2026
Filed — New Building
STRUCTURAL WORK FOR 7 STORY RESIDENTIAL NEW BUILDING
X01293919-S9
01/27/2026
Filed — New Building
STRUCTURAL WORK FOR 7 STORY RESIDENTIAL NEW BUILDING
X01293919-I1
11/12/2025
Permit issued — Construction Fence
X01296147-I1-FN
10/17/2025
Objection resolved — Addressed
10/17/2025
Objection resolved — Addressed
10/16/2025
Objection raised — Admin
10/16/2025
Objection raised — Structural
10/03/2025
Filed — Alteration
CONSTRUCTION FENCE IN CONJUNCTION WITH NB# X01293919-I1
X01296147-I1
06/11/2024
Violation issued (ECB, open)
Construction
06/11/2024
Violation issued (ECB, open)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWFoundationPermit IssuedUGB DESIGN & BUILD INC09/18/2026
DOB NOWFoundationPermit IssuedUGB DESIGN & BUILD INC09/15/2026
DOB NOWSupport of ExcavationPermit IssuedUGB DESIGN & BUILD INC09/14/2026
DOB NOWConstruction FencePermit IssuedUGB CONSTRUCTION INC11/12/2025
1 project · most recent 07/13/2026
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
07/13/2026Permit IssuedUGB DESIGN & BUILD INCHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Klimaire PTHP12H352-KC-3 1 tons · Ptac ×42
PTHP15H502-KC-3 14,700 BTU · Ptac ×42
Lg ARUN048GSS4 4 tons · Vrf Outdoor ×2
RX24BXVJU 2 tons · Vrf Outdoor ×1
Ventilation
Greenheck ERVe-20-30H 2,600 CFM · Erv ×1
1 project · most recent 09/22/2026
General Wiring
FiledStatusContractorScope
09/22/2026Permit IssuedCOUNTY ELECL CONTRACTOR IGeneral Wiring
1 project · most recent 07/13/2026
Concrete
FiledStatusContractorScope
07/13/2026Permit IssuedUGB DESIGN & BUILD INCConcrete
2 projects · most recent 07/13/2026
Fence
FiledStatusContractorScope
07/13/2026Permit IssuedUGB DESIGN & BUILD INCFence
10/03/2025Permit IssuedUGB CONSTRUCTION INCFence
▾Special Inspection Requirements (DOB NOW) — 78
DateRequirementInspectorRole
07/13/2026Exterior Insulation and Finish Systems (EIFS)—special
07/13/2026Concrete - Cast-In-Place—special
07/13/2026Combustible Exterior Wall Coverings—special
07/13/2026Interior lighting power—energy_progress
07/13/2026Insulation placement and R values—energy_progress
07/13/2026Fenestration and door U-factor and product ratings—energy_progress
07/13/2026Fenestration air leakage—energy_progress
07/13/2026Metering—energy_progress
07/13/2026Air barrier - visual inspection—energy_progress
07/13/2026Maintenance information—energy_progress
07/13/2026Fenestration areas—energy_progress
07/13/2026Exterior lighting power—energy_progress
07/13/2026Air barrier — testing —energy_progress
07/13/2026Lighting in dwelling units—energy_progress
07/13/2026Lighting controls—energy_progress
07/13/2026Fire-Resistance Rated Construction—progress
07/13/2026Energy Code Compliance Inspections—progress
07/13/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation—special
07/13/2026Fire-Resistant Penetrations and Joints—special
07/13/2026Protection of exposed foundation insulation—energy_progress
07/13/2026Electrical motors and elevators—energy_progress
03/18/2026Fire-Resistant Penetrations and JointsEDWIN HOPKINSspecial
03/18/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationEDWIN HOPKINSspecial
03/18/2026HVAC-R and service water heating equipmentEDWIN HOPKINSenergy_progress
03/18/2026HVAC-R and service water piping design and insulationEDWIN HOPKINSenergy_progress
Latest 25 of 78.
▾Documents — 60 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch12
08/18/2026X01296147-I1Request digital key ↗
08/17/2026X01293919-S6Request digital key ↗
08/17/2026X01293919-S5Request digital key ↗
Showing 3 of 12 on file for this type
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram2
08/17/2026X01293919-I1Open ↗
08/14/2026X01293919-P3Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/17/2026X01293919-I1Open ↗
08/14/2026X01293919-P3Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/17/2026X01293919-I1Open ↗
▸Seals & Professional Certifications27
▸DOB NOWDPL-1: Design Professional Seal & Signature12
08/18/2026X01296147-I1Open ↗
08/17/2026X01293919-S5Open ↗
08/17/2026X01293919-S4Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/26/2026X01293919-S4Open ↗
09/02/2026X01293919-S9Open ↗
09/02/2026X01293919-S9Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWProgress Inspector Seal & Signature6
09/26/2026X01293919-S4Open ↗
08/28/2026X01293919-S8Open ↗
08/28/2026X01293919-S6Open ↗
Showing 3 of 6 on file for this type
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist2
08/17/2026X01293919-I1Open ↗
08/14/2026X01293919-P3Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/17/2026X01293919-I1Open ↗
▸Inspections & Test Reports6
▸DOB NOWTR4 Test Report and Plot Diagram3
08/17/2026X01293919-Z1Open ↗
08/17/2026X01293919-S9Open ↗
08/17/2026X01293919-S8Open ↗
▸DOB NOWSOIL REPORT3
08/17/2026X01293919-Z1Open ↗
08/17/2026X01293919-S9Open ↗
08/17/2026X01293919-S8Open ↗
▸Other Documents7
▸DOB NOWSite Survey: Initial2
08/17/2026X01293919-I1Open ↗
08/14/2026X01293919-P3Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/17/2026X01293919-I1Open ↗
08/14/2026X01293919-P3Open ↗
▸DOB NOWProperty Ownership Certification2
08/17/2026X01293919-I1Open ↗
08/14/2026X01293919-P3Open ↗
▸DOB NOWFinal Survey1
08/17/2026X01293919-I1Open ↗