← Back
Public elementary, junior or senior high
P.S. 272 Curtis Estabrook
10102 SEAVIEW AVENUE · BIN 3235262
💬 Discuss this project
1955Year Built
3Stories
W1Building Class
R5Zoning
160,322 sfGross Floor Area
1Units
LL97 Covered4 Open Violations 0 unresolved · 4 paperwork only ▸FDNY Report ↗
Public elementary, junior or senior high · Owner of record: NYC DEPARTMENT OF EDUCATION · 72,446 sf lot · 2.21 FAR built · Flood zone X500
Locations of Work
ArchitectureElectricalPlumbing
Permit Issued — active, not yet Signed-off
RoofUnder Construction1 filing · 7 docs
Floor 2Under Construction10p · 1 filing · 20 docs
Floor 1
Sub-BasementUnder Construction1 filing · 7 docs
12 jobs · most recent 08/14/2026
General Wiring
FiledStatusContractorScope
08/14/2026Permit IssuedSUNRISE ELEC'L SERVICES—
07/06/2026CompleteRELLA ELECTRIC LLCGeneral Wiring
10/27/2025CompleteAUJLA ELECTRIC CORPGeneral Wiring
06/12/2023CompleteGEMINI ELECTRIC CO., INC.—
06/21/2022CompleteLAREDO ELECTRIC, INC.—
06/28/2021CompleteCHARAN ELEC'L ENTERP'S IN—
04/13/2021CompleteABM ELECTRIC, INC—
02/18/2021CompleteCHARAN ELEC'L ENTERP'S IN—
12/04/2019Permit IssuedA & S ELECTRIC INC.General Wiring
10/08/2019Permit IssuedCHARAN ELEC'L ENTERP'S INGeneral Wiring
08/07/2019CompleteLEKTRIC INSTALLATIONS CORGeneral Wiring
02/20/2019Permit IssuedA & S ELECTRIC INC.General Wiring
1 job · most recent 08/20/2026
FiledStatusContractorScope
08/20/2026Permit IssuedSUNRISE ELECTRICAL SRV926 panels, 555.6 kw, 11,575 roof_area_sqft
Building Lifecycle
All (107)Filed (6)Permit Issued (5)Signed Off (2)Violation (60)Inspection (10)Objection (6)Special Inspection (18)
08/20/2026
Filed — Alteration
INSTALLATION OF PHOTOVOLTAIC SOLAR ARRAY ON ROOF INCLUDING ALL RELATED STRUCTURAL WORK AS PER PLANS FILED HEREWITH. ELECTRICAL APP# B01446228-I1 FILED SEPARATELY. NO CHANGETO USE, EGRESS OR OCCUPANCY.
B01448062-I1
08/20/2026
Permit issued — Solar
B01448062-I1-SL
08/19/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
RAYMOND PANCHARI
08/19/2026
Special inspection requirement — Air barrier - visual inspection
RAYMOND PANCHARI
08/19/2026
Special inspection requirement — Final
RAYMOND PANCHARI
08/19/2026
Special inspection requirement — Energy Code Compliance Inspections
RAYMOND PANCHARI
08/19/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
RAYMOND PANCHARI
04/28/2026
Signed off — Alteration
RENOVATE EXISTING LIBRARY/CLASSROOM 203 - REPLACE EXISTING SUSPENDED CEILING - NO CHANGE IN USE - NO CHANGE IN OCCUPANCY - NO CHANGE IN EGRESS - NO CHANGE IN VENTILATION
B00908713-I1
04/28/2026
Signed off — Alteration
RENOVATE EXISTING LIBRARY/CLASSROOM 203 - REPLACE EXISTING SUSPENDED CEILING - NO CHANGE IN USE - NO CHANGE IN OCCUPANCY - NO CHANGE IN EGRESS - NO CHANGE IN VENTILATION
B00908713-S1
04/24/2026
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
03/05/2026
Filed — Alteration
RENOVATE EXISTING LIBRARY/CLASSROOM 203 - REPLACE EXISTING SUSPENDED CEILING - NO CHANGE IN USE - NO CHANGE IN OCCUPANCY - NO CHANGE IN EGRESS - NO CHANGE IN VENTILATION
B00908713-P6
01/21/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
01/16/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/23/2025
Violation issued (FDNY_ORDER, closed)
10/23/2025
Violation issued (FDNY_ORDER, closed)
10/23/2025
Violation issued (FDNY_ORDER, closed)
10/23/2025
Violation issued (FDNY_ORDER, closed)
10/23/2025
Violation issued (FDNY_ORDER, closed)
10/23/2025
Violation issued (FDNY_ORDER, closed)
09/17/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
09/17/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/17/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
04/21/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/02/2025
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
03/28/2025
Permit issued — General Construction
B00908713-I1-GC
03/20/2025
Violation issued (ECB, closed)
Construction
03/03/2025
Permit issued — Plumbing
B00908713-S1-PL
01/27/2025
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
12/30/2024
Permit issued — Plumbing
B00908713-S1-PL
12/13/2024
Filed — Alteration
RENOVATE EXISTING LIBRARY/CLASSROOM 203 - REPLACE EXISTING SUSPENDED CEILING - NO CHANGE IN USE - NO CHANGE IN OCCUPANCY - NO CHANGE IN EGRESS - NO CHANGE IN VENTILATION
B00908713-P5
12/05/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
MIKHAIL ZEYGMAN
11/25/2024
Permit issued — General Construction
B00908713-I1-GC
11/21/2024
Special inspection requirement — Lighting controls
MAXIM KORNGOLD
11/21/2024
Special inspection requirement — Maintenance information
MAXIM KORNGOLD
11/21/2024
Special inspection requirement — Interior lighting power
MAXIM KORNGOLD
11/21/2024
Special inspection requirement — Energy Code Compliance Inspections
MAXIM KORNGOLD
11/21/2024
Special inspection requirement — Post-installed Anchors
MAXIM KORNGOLD
11/21/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
MAXIM KORNGOLD
11/14/2024
Objection resolved — Addressed
10/16/2024
Objection raised — Other
10/08/2024
Filed — Alteration
RENOVATE EXISTING LIBRARY/CLASSROOM 203 - REPLACE EXISTING SUSPENDED CEILING - NO CHANGE IN USE - NO CHANGE IN OCCUPANCY - NO CHANGE IN EGRESS - NO CHANGE IN VENTILATION
B00908713-P3
09/23/2024
Special inspection requirement — Maintenance information
MIKHAIL ZEYGMAN
09/23/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
MIKHAIL ZEYGMAN
09/23/2024
Special inspection requirement — Post-installed Anchors
MIKHAIL ZEYGMAN
09/23/2024
Special inspection requirement — Energy Code Compliance Inspections
MIKHAIL ZEYGMAN
09/23/2024
Special inspection requirement — Interior lighting power
MIKHAIL ZEYGMAN
09/23/2024
Special inspection requirement — Lighting controls
MIKHAIL ZEYGMAN
08/26/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/22/2024
Violation issued (ECB, closed)
Construction
04/22/2024
Violation issued (ECB, closed)
Construction
04/22/2024
Violation issued (ECB, closed)
Construction
09/12/2023
Objection resolved — Addressed
09/12/2023
Objection resolved — Addressed
08/11/2023
Objection raised — Other
08/11/2023
Objection raised — Other
08/07/2023
Filed — Alteration
RENOVATE EXISTING LIBRARY/CLASSROOM 203 - REPLACE EXISTING SUSPENDED CEILING - NO CHANGE IN USE - NO CHANGE IN OCCUPANCY - NO CHANGE IN EGRESS - NO CHANGE IN VENTILATION
B00908713-S1
07/25/2023
Filed — Alteration
RENOVATE EXISTING LIBRARY/CLASSROOM 203 - REPLACE EXISTING SUSPENDED CEILING - NO CHANGE IN USE - NO CHANGE IN OCCUPANCY - NO CHANGE IN EGRESS - NO CHANGE IN VENTILATION
B00908713-I1
03/01/2023
Violation issued (ECB, closed)
Construction
03/01/2023
Violation issued (ECB, closed)
Construction
03/01/2023
Violation issued (ECB, closed)
Construction
Latest 60 of 107 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
AMERESCO108/21/2026
NYC SCHOOL CONSTRUCTION AUTHORITY1407/08/2026
NYC DEPARTMENT OF EDUCATION103/22/2026
DEPT OF EDUCATION P.S.272403/22/2026
DOE PS 272603/22/2026
DEPT OF EDUCATION P.S. 27103/22/2026
D.O.E. PS272 0103/22/2026
DOE 040503/22/2026
DEPT. OF EDUCATION P S 2103/22/2026
DEPARTMENT OF EDUCATION403/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
HOMERUN SOLAR108/20/2026
PAGNAMENTA TORRIANI ARCHITECTS PLAN503/05/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RIZVI BUILDERSGeneral Contractor207/08/2026
A & A PLUMBING SYSTEMS INPlumbing207/08/2026
CARUSO, VElectrical103/21/2026
DUARTE, LUIGIElectrical103/21/2026
GIOVANNI DITURIElectrical103/21/2026
AUJLA ELECTRIC CORPElectrical103/22/2026
WILLIAM NIEVESElectrical103/21/2026
SUNRISE ELECTRICAL SRVGeneral Contractor108/21/2026
NIEVES WILLIAMElectrical103/21/2026
BERNARD FARSKYElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HOMERUN SOLAR8772108/20/2026
TWIN PEAKS INC.317312/13/2024
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedSUNRISE ELECTRICAL SRV08/20/2026
DOB NOWGeneral ConstructionPermit IssuedRIZVI BUILDERS03/28/2025
DOB NOWPlumbingPermit IssuedA & A PLUMBING SYSTEMS IN03/03/2025
DOB NOWPlumbingSigned-offA & A PLUMBING SYSTEMS IN12/30/2024
DOB NOWGeneral ConstructionSigned-offRIZVI BUILDERS11/25/2024
BISPLISSUEDVARSITY PLBG AND HTG INC08/31/2017
BISPLISSUEDVARSITY PLBG AND HTG INC08/31/2017
BISPLISSUEDVARSITY PLBG AND HTG INC12/02/2016
BISOTISSUEDCOMMERCE ELECTRICAL CONTR09/29/2016
BISOTISSUEDVENUS GROUP INC09/09/2016
BISOTISSUEDVENUS GROUP INC09/08/2016
BISPLISSUEDVARSITY PLBG AND HTG INC09/08/2016
BISPLISSUEDVARSITY PLBG AND HTG INC09/08/2016
BISMHISSUEDU & I MECHANICAL CORP07/14/2016
BISEQISSUEDVENUS GROUP INC07/08/2016
BISOTISSUEDWHITESTONE CONSTRUCTION CORP04/28/2016
BISEQISSUEDWHITESTONE CONSTRUCTION CORP01/26/2016
BISEQISSUEDWHITESTONE CONSTRUCTION CORP01/26/2016
BISEQISSUEDWHITESTONE CONSTRUCTION CORP01/26/2016
BISPLISSUEDVARSITY PLBG AND HTG INC12/28/2015
BISOTISSUEDCOMMERCE ELECTRICAL CONTR10/16/2015
BISMHISSUEDU & I MECHANICAL CORP07/14/2015
BISOTISSUEDWHITESTONE CONSTRUCTION CORP03/27/2015
BISOTISSUEDWHITESTONE CONSTRUCTION CORP03/27/2015
BISPLISSUEDVARSITY PLBG AND HTG INC01/23/2015
BISMHISSUEDU & I MECHANICAL CORP01/23/2015
BISOTISSUEDWHITESTONE CONSTRUCTION CORP01/23/2015
BISEQISSUEDWHITESTONE CONSTRUCTION CORP01/23/2015
BISOTISSUEDWHITESTONE CONSTRUCTION CORP01/23/2015
BISEQISSUEDWHITESTONE CONSTRUCTION CORP01/21/2015
BISEQISSUEDWHITESTONE CONSTRUCTION CORP01/21/2015
BISMHISSUEDMIDTOWN HVAC ENTERPRISES05/07/2014
BISMHISSUEDMIDTOWN HVAC ENTERPRISES05/03/2013
BISMHISSUEDMIDTOWN HVAC ENTERPRISES02/08/2013
BISOTISSUEDPALENT ELECTRICAL CONTRA*06/21/2011
BISOTISSUEDABC CONSTRUCTION CONT INC07/08/2009
BISOTISSUEDKNC ELECTRIC, INC04/22/2008
BISEQISSUEDLIBERTY ARCHITECTURAL PRODUCTS12/21/2006
BISEQISSUEDLIBERTY ARCHITECTURAL PRODUCTS12/21/2006
BISEQISSUEDLIBERTY ARCHITECTURAL PRODUCTS12/21/2006
+ 15 more permits on file
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
04/24/2026Pass-Final General Construction Non-Directive 14PassView ↗
01/21/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/16/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/17/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
09/17/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/17/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
04/21/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/02/2025Pass-Final PL - Up to 9 Requested FloorsPassView ↗
01/27/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
08/26/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 18
DateRequirementInspectorRole
08/19/2026Fire-Resistant Penetrations and JointsRAYMOND PANCHARIspecial
08/19/2026Air barrier - visual inspectionRAYMOND PANCHARIenergy_progress
08/19/2026FinalRAYMOND PANCHARIprogress
08/19/2026Energy Code Compliance InspectionsRAYMOND PANCHARIprogress
08/19/2026Structural Stability – Alterations of existing buildingsRAYMOND PANCHARIspecial
12/05/2024Fire-Resistant Penetrations and JointsMIKHAIL ZEYGMANspecial
11/21/2024Lighting controlsMAXIM KORNGOLDenergy_progress
11/21/2024Maintenance informationMAXIM KORNGOLDenergy_progress
11/21/2024Interior lighting powerMAXIM KORNGOLDenergy_progress
11/21/2024Energy Code Compliance InspectionsMAXIM KORNGOLDprogress
11/21/2024Post-installed AnchorsMAXIM KORNGOLDspecial
11/21/2024Fire-Resistant Penetrations and JointsMAXIM KORNGOLDspecial
09/23/2024Maintenance informationMIKHAIL ZEYGMANenergy_progress
09/23/2024Fire-Resistant Penetrations and JointsMIKHAIL ZEYGMANspecial
09/23/2024Post-installed AnchorsMIKHAIL ZEYGMANspecial
09/23/2024Energy Code Compliance InspectionsMIKHAIL ZEYGMANprogress
09/23/2024Interior lighting powerMIKHAIL ZEYGMANenergy_progress
09/23/2024Lighting controlsMIKHAIL ZEYGMANenergy_progress
▾Documents — 56 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/27/2026B00908713-P3Request digital key ↗
08/27/2026B00908713-S1Request digital key ↗
08/27/2026B00908713-P6Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits1
▸BISPLAN / WORK APPROVAL APPLICATION1
09/14/2010320213318Open ↗
▸Seals & Professional Certifications22
▸DOB NOWProgress Inspector Seal & Signature8
08/26/2026B00908713-I1Open ↗
08/26/2026B00908713-I1Open ↗
08/23/2026B01448062-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/27/2026B00908713-S1Open ↗
08/27/2026B00908713-P3Open ↗
08/27/2026B00908713-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/01/2026B00908713-P5Open ↗
08/26/2026B00908713-I1Open ↗
08/23/2026B01448062-I1Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
09/21/2010320213318Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
09/14/2010320213318Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
09/17/2010320213318Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
08/27/2026B00908713-S1Open ↗
08/27/2026B00908713-I1Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
09/14/2010320213318Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/21/2026B01448062-I1Open ↗
▸Approvals, Objections & Sign-offs14
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter6
08/21/2026B01448062-I1Open ↗
08/13/2026B00908713-P5Open ↗
08/13/2026B00908713-S1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)5
08/13/2026B00908713-P3Open ↗
08/13/2026B00908713-P5Open ↗
08/13/2026B00908713-P6Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)2
08/13/2026B00908713-S1Open ↗
08/13/2026B00908713-I1Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
09/14/2010320213318Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
09/14/2010320213318Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
09/14/2010320213318Open ↗
▸Other Documents7
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal5
08/13/2026B00908713-P3Open ↗
08/13/2026B00908713-P6Open ↗
08/13/2026B00908713-S1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWNYCSCA Exhibit 22
08/27/2026B00908713-S1Open ↗
08/27/2026B00908713-I1Open ↗