1935Year Built
2Stories
B1Building Class
R4Zoning
1,200 sfGross Floor Area
2Units
2 Open Violations ▸
Two family brick · 2,000 sf lot · 0.6 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/05/2023$740K—START 2 FINISH REHABS LLC → Private party$617/sf building
06/27/2022$375K—— → —$312/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC109/16/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854109/16/2026
Building Lifecycle
All (8)Filed (1)Violation (2)Special Inspection (5)
09/16/2026
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEING APPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.
Q01460243-I1
09/15/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
09/15/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
09/15/2026
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
09/15/2026
Special inspection requirement — Final
TOM PETERSEN
09/15/2026
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
06/24/2002
Violation issued (HPD, open)
B
06/24/2002
Violation issued (HPD, open)
B
Nothing on file for this building.
2 projects · most recent 09/16/2026
FiledStatusContractorScope
09/16/2026Permit IssuedSOLAR ELEC CONTRACTNG LLC2 meters
09/16/2026Permit IssuedSOLAR ELEC CONTRACTNG LLC2 meters
1 project · most recent 09/16/2026
FiledStatusContractorScope
09/16/2026——26 panels, 11.4 kw, 609.84 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
09/15/2026Fire-Resistant Penetrations and JointsTOM PETERSENspecial
09/15/2026Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
09/15/2026Energy Code Compliance InspectionsTOM PETERSENprogress
09/15/2026FinalTOM PETERSENprogress
09/15/2026Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
09/23/2026Q01460243-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
09/27/2026Q01460243-I1Open ↗
09/27/2026Q01460243-I1Open ↗
09/27/2026Q01460243-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/27/2026Q01460243-I1Open ↗
09/27/2026Q01460243-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
09/23/2026Q01460243-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1