Locations of Work
ArchitectureMechanicalPlumbingGeneral
Roof2p · 1 filing · 20 docs
Bulkhead1p · 1 filing · 20 docs
Floor 91p · 1 filing · 20 docs
Floor 8
Floor 71p · 1 filing · 20 docs
Floor 6
Floor 5
Floor 4
Floor 3
Floor 21p · 1 filing · 20 docs
Floor 12p · 1 filing · 20 docs
Cellar1p · 1 filing · 20 docs
Sub-Cellar2p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
METROPOLIS MANAGEMENT507/08/2026
METROPOLIS MANAGEMENT GROUP II1503/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/13/2021$2.5M—METROPOLIS MANAGEMENT GROUP II LLC → Private party$1,190/sf building
05/08/2015$425K—— → —$202/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
KM ENGINEERING, D.P.C202/11/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NEXUS CONSULTING NYC, INC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
GIROLAMO RESTORATION CORPGeneral Contractor307/08/2026
SALVATORE CAMPISI & SONSElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
S&S ARCHITECTURTAL DESIGN2840202/11/2021
Building Lifecycle
All (28)Filed (2)Permit Issued (2)Signed Off (1)Violation (1)Special Inspection (22)
03/08/2021
Signed off — Alteration
INSTALLATION OF THE SPLIT AIR CONDITIONING SYSTEM WITH ASSOCIATED PIPING AND DUCTS.
B00201132-I1
02/17/2021
Special inspection requirement — Maintenance information
SHAWN STILES
02/17/2021
Special inspection requirement — Mechanical Systems
SHAWN STILES
02/17/2021
Special inspection requirement — Energy Code Compliance Inspections
SHAWN STILES
02/17/2021
Special inspection requirement — Final
Luis Pichardo
02/17/2021
Special inspection requirement — Permanent certificate
SHAWN STILES
02/17/2021
Special inspection requirement — Electrical motors
SHAWN STILES
02/17/2021
Special inspection requirement — HVAC and service water heating equipment
SHAWN STILES
02/17/2021
Special inspection requirement — HVAC insulation and sealing
SHAWN STILES
02/17/2021
Special inspection requirement — HVAC and service water heating system controls
SHAWN STILES
02/17/2021
Special inspection requirement — Duct leakage testing
SHAWN STILES
02/17/2021
Special inspection requirement — Shutoff dampers
SHAWN STILES
02/11/2021
Filed — Alteration
INSTALLATION OF THE SPLIT AIR CONDITIONING SYSTEM WITH ASSOCIATED PIPING AND DUCTS.
B00201132-P1
02/11/2021
Special inspection requirement — Mechanical Systems
SHAWN STILES
02/11/2021
Special inspection requirement — Energy Code Compliance Inspections
SHAWN STILES
02/11/2021
Special inspection requirement — Final
Luis Pichardo
02/11/2021
Special inspection requirement — HVAC and service water heating equipment
SHAWN STILES
02/11/2021
Special inspection requirement — Permanent certificate
SHAWN STILES
02/11/2021
Special inspection requirement — Duct leakage testing
SHAWN STILES
02/11/2021
Special inspection requirement — HVAC insulation and sealing
SHAWN STILES
02/11/2021
Special inspection requirement — HVAC and service water heating system controls
SHAWN STILES
02/11/2021
Special inspection requirement — Shutoff dampers
SHAWN STILES
02/11/2021
Special inspection requirement — Electrical motors
SHAWN STILES
02/11/2021
Special inspection requirement — Maintenance information
SHAWN STILES
06/01/2020
Violation issued (ECB, closed)
Construction
05/11/2020
Permit issued — Mechanical Systems
B00201132-I1-MS
02/24/2020
Permit issued — Mechanical Systems
B00201132-I1-MS
11/04/2019
Filed — Alteration
INSTALLATION OF THE SPLIT AIR CONDITIONING SYSTEM WITH ASSOCIATED PIPING AND DUCTS.
B00201132-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offGIROLAMO RESTORATION CORP05/11/2020
DOB NOWMechanical SystemsSigned-offGIROLAMO RESTORATION CORP02/24/2020
BISPLISSUEDBOSCO PLUMBING & HTG INC10/09/2020
BISPLISSUEDBOSCO PLUMBING & HTG INC02/25/2020
BIS—ISSUEDGIROLAMO RESTORATION CORP02/24/2020
BISOTISSUEDGIROLAMO RESTORATION CORP02/21/2020
BISOTISSUEDGIROLAMO RESTORATION CORP02/03/2020
BIS—ISSUEDGIROLAMO RESTORATION CORP02/03/2020
BISSPISSUEDRRP PLUMBING CORP05/08/2019
BIS—ISSUEDGIROLAMO RESTORATION CORP01/29/2019
BISOTISSUEDGIROLAMO RESTORATION CORP01/29/2019
BISPLISSUEDBOSCO PLUMBING & HTG INC01/14/2019
BIS—ISSUEDGIROLAMO RESTORATION CORP02/13/2018
BISOTISSUEDGIROLAMO RESTORATION CORP02/13/2018
BIS—ISSUEDGIROLAMO RESTORATION CORP11/03/2017
BISOTISSUEDGIROLAMO RESTORATION CORP06/22/2017
BIS—ISSUEDGIROLAMO RESTORATION CORP08/15/2016
1 job · most recent 12/02/2020
General Wiring
FiledStatusContractorScope
12/02/2020CompleteSALVATORE CAMPISI & SONSGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 22
DateRequirementInspectorRole
02/17/2021Maintenance informationSHAWN STILESenergy_progress
02/17/2021Mechanical SystemsSHAWN STILESspecial
02/17/2021Energy Code Compliance InspectionsSHAWN STILESprogress
02/17/2021FinalLuis Pichardoprogress
02/17/2021Permanent certificateSHAWN STILESenergy_progress
02/17/2021Electrical motorsSHAWN STILESenergy_progress
02/17/2021HVAC and service water heating equipment SHAWN STILESenergy_progress
02/17/2021HVAC insulation and sealing SHAWN STILESenergy_progress
02/17/2021HVAC and service water heating system controls SHAWN STILESenergy_progress
02/17/2021Duct leakage testing SHAWN STILESenergy_progress
02/17/2021Shutoff dampersSHAWN STILESenergy_progress
02/11/2021Mechanical SystemsSHAWN STILESspecial
02/11/2021Energy Code Compliance InspectionsSHAWN STILESprogress
02/11/2021FinalLuis Pichardoprogress
02/11/2021HVAC and service water heating equipment SHAWN STILESenergy_progress
02/11/2021Permanent certificateSHAWN STILESenergy_progress
02/11/2021Duct leakage testing SHAWN STILESenergy_progress
02/11/2021HVAC insulation and sealing SHAWN STILESenergy_progress
02/11/2021HVAC and service water heating system controls SHAWN STILESenergy_progress
02/11/2021Shutoff dampersSHAWN STILESenergy_progress
02/11/2021Electrical motorsSHAWN STILESenergy_progress
02/11/2021Maintenance informationSHAWN STILESenergy_progress
▾Documents — 126 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch - Mechanical Systems2
09/02/2026B00201132-I1Request digital key ↗
08/15/2026B00201132-P1Request digital key ↗
▸Applications & Permits29
▸BISPLAN / WORK APPROVAL APPLICATION14
02/08/2021321309650Open ↗
12/24/2020321436077Open ↗
11/24/2020321141046Open ↗
Showing 3 of 14 on file for this type
▸BISWORK PERMIT APPLICATION13
10/09/2020321141046Open ↗
02/26/2020321309650Open ↗
02/24/2020321436077Open ↗
Showing 3 of 13 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
11/19/2020321309650Open ↗
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
02/11/2021321436077Open ↗
▸Zoning, Tax Lot & Property Records2
▸BISVERIFY TAX LOT1
05/12/2021321309650Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
05/12/2021321309650Open ↗
▸Seals & Professional Certifications35
▸DOB NOWProgress Inspector Seal & Signature20
09/30/2026B00201132-I1Open ↗
09/30/2026B00201132-I1Open ↗
09/30/2026B00201132-I1Open ↗
Showing 3 of 20 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION7
05/06/2019321141046Open ↗
06/23/2017321436077Open ↗
06/13/2017321436077Open ↗
Showing 3 of 7 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
05/06/2019321141046Open ↗
11/22/2016321065191Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
05/06/2019321141046Open ↗
11/22/2016321065191Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/13/2026B00201132-P1Open ↗
08/13/2026B00201132-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/30/2026B00201132-I1Open ↗
08/25/2026B00201132-P1Open ↗
▸Trade Schedules & Equipment8
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE5
03/04/2020321309650Open ↗
02/24/2020321309650Open ↗
05/06/2019321141046Open ↗
Showing 3 of 5 on file for this type
▸BISSCHEDULE B - PLUMBING3
11/19/2020321141046Open ↗
11/10/2020321309650Open ↗
09/24/2020321141046Open ↗
▸Safety & Tenant Protection4
▸BISTenant Protection Plan and Notes2
05/06/2019321141046Open ↗
06/13/2017321436077Open ↗
▸BISSTREET TREE CHECKLIST2
04/28/2021321309650Open ↗
08/15/2016321309650Open ↗
▸Environmental & Asbestos5
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
05/06/2019321141046Open ↗
06/13/2017321436077Open ↗
11/22/2016321065191Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026B00201132-I1Open ↗
08/13/2026B00201132-P1Open ↗
▸Energy Compliance9
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS5
06/23/2017321436077Open ↗
06/13/2017321436077Open ↗
08/15/2016321309650Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
02/11/2021321436077Open ↗
01/07/2021321309650Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
02/11/2021321436077Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
02/18/2021321309650Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY5
02/11/2021321436077Open ↗
01/14/2021321141046Open ↗
01/07/2021321309650Open ↗
Showing 3 of 5 on file for this type
▸Approvals, Objections & Sign-offs7
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
02/11/2021321436077Open ↗
01/14/2021321141046Open ↗
12/23/2020321309650Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE2
02/08/2021321309650Open ↗
02/24/2016321309650Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
08/02/2019321309650Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
02/24/2016321309650Open ↗
▸Cost, Insurance & Ownership7
▸BISCOST AFFIDAVIT5
02/11/2021321436077Open ↗
05/06/2019321141046Open ↗
06/13/2017321436077Open ↗
Showing 3 of 5 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
05/12/2021321309650Open ↗
01/14/2021321141046Open ↗
▸Filing & Intake Forms11
▸BISADDITIONAL INFORMATION6
01/25/2021321436077Open ↗
01/19/2021321436077Open ↗
12/31/2020321436077Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING COVER SHEET4
05/06/2019321141046Open ↗
06/13/2017321436077Open ↗
11/22/2016321065191Open ↗
Showing 3 of 4 on file for this type
▸BISAI1 W/STANDARD STATEMENT REQUIRED FORFINAL SURVEY RECEIVED1
05/12/2021321309650Open ↗
▸Other Documents2
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
08/11/2016321309650Open ↗
08/11/2016321309650Open ↗