← Back
Two family frame
1024 CRESCENT STREET
BROOKLYN · BIN 3394028
💬 Discuss this project
2006Year Built
3Stories
B2Building Class
R4Zoning
2,970 sfGross Floor Area
2Units
Two family frame · 2,200 sf lot · 1.35 FAR built · Flood zone AE
Locations of Work
Electrical
Roof5p · 1 filing · 15 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR201/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281201/21/2026
Building Lifecycle
All (16)Filed (2)Permit Issued (1)Objection (1)Special Inspection (12)
02/02/2026
Objection raised — Admin
01/21/2026
Filed — Alteration
Installation of solar panels, rooftop, grid tied, railed, 16 modules, 6.56 KW
B01309640-P1
01/21/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
01/21/2026
Special inspection requirement — Adhesive-Based Solar Pedestal Bonding Systems
Mina Makar
01/21/2026
Special inspection requirement — Post-installed Anchors
Mina Makar
01/21/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
01/21/2026
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
01/21/2026
Special inspection requirement — Final
Mina Makar
01/21/2026
Special inspection requirement — Air barrier - visual inspection
Mina Makar
11/12/2025
Permit issued — Solar
B01309640-I1-SL
10/28/2025
Filed — Alteration
Installation of solar panels, rooftop, grid tied, railed, 16 modules, 6.56 KW
B01309640-I1
10/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
10/28/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
10/28/2025
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
10/28/2025
Special inspection requirement — Final
Mina Makar
10/28/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedMOMENTUM SOLAR11/12/2025
1 project · most recent 11/19/2025
FiledStatusContractorScope
11/19/2025CompleteISLAND ELECTRIC CORP—
1 project · most recent 01/21/2026
FiledStatusContractorScope
01/21/2026Permit IssuedMOMENTUM SOLAR32 panels, 13.12 kw, 281 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 12
DateRequirementInspectorRole
01/21/2026Fire-Resistant Penetrations and JointsMina Makarspecial
01/21/2026Adhesive-Based Solar Pedestal Bonding SystemsMina Makarspecial
01/21/2026Post-installed AnchorsMina Makarspecial
01/21/2026Structural Stability – Alterations of existing buildingsMina Makarspecial
01/21/2026Energy Code Compliance InspectionsMina Makarprogress
01/21/2026FinalMina Makarprogress
01/21/2026Air barrier - visual inspectionMina Makarenergy_progress
10/28/2025Fire-Resistant Penetrations and JointsMina Makarspecial
10/28/2025Structural Stability – Alterations of existing buildingsMina Makarspecial
10/28/2025Energy Code Compliance InspectionsMina Makarprogress
10/28/2025FinalMina Makarprogress
10/28/2025Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 15 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/18/2026B01309640-I1Request digital key ↗
08/18/2026B01309640-P1Request digital key ↗
▸Seals & Professional Certifications11
▸DOB NOWSpecial Inspector Seal & Signature5
08/24/2026B01309640-P1Open ↗
08/24/2026B01309640-P1Open ↗
08/24/2026B01309640-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/24/2026B01309640-P1Open ↗
08/24/2026B01309640-P1Open ↗
08/24/2026B01309640-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/18/2026B01309640-I1Open ↗
08/13/2026B01309640-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/18/2026B01309640-I1Open ↗
08/13/2026B01309640-P1Open ↗