1927Year Built
6Stories
D7Building Class
R8Zoning
76,822 sfGross Floor Area
90Units
LL97 CoveredRent Stabilized74 Open Violations 68 unresolved · 6 paperwork only ▸FISP: SWARMP
Elevator apt, semi-fireproof with stores · Owner of record: 1027 WALLCO, L.L.C. · 16,789 sf lot · 4.58 FAR built · Flood zone X
Locations of Work
Architecture
Floor 12p · 1 filing · 9 docs
Cellar3p · 1 filing
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
KAJ NY CONSTRUCTION1007/08/2026
TRYAX REALTY MANAGEMENT1207/08/2026
BARBARA DELI FOOD CORP703/22/2026
1027 WALLCO2603/22/2026
1027 WALCO LLC103/22/2026
1027 WALTON LLC103/22/2026
FRYAX REALTY INC 1027 WAL103/22/2026
TRIAD MANAGEMENT103/22/2026
HPD 806103/22/2026
GREATER VILLAGE CORP.103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ANDREW FREDMAN ARCHITECT LLC107/17/2025
NEW YORK ENGINEERING ASSOC., P.C.108/02/2021
KDV DESIGNS ARCHITECTS LLC107/15/2021
GREEN DESIGN207/24/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ATLANTIC BUILDING SUPPLY INC.403/21/2026
CONVERSANO ASSOCIATES, INC.203/21/2026
TBC & ASSOC.203/21/2026
NEW YORK ENGINEERING ASSOCIATES P203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
KAJ NY CONSTRUCTION INCGeneral Contractor707/08/2026
2260 MAG CORPGeneral Contractor603/21/2026
ALEXANDRINI, VINCENTElectrical103/21/2026
BAIN, GElectrical103/21/2026
MERCURY PLBG & HTG COElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NEW YORK ENGINEERING ASSO851108/02/2021
SY ENGINEERING PLLC5149107/15/2021
Building Lifecycle
All (133)Filed (5)Permit Issued (6)Signed Off (2)Facade (FISP) (17)Violation (60)Inspection (1)Objection (25)Special Inspection (17)
08/18/2026
Violation issued (HPD, open)
A
08/18/2026
Violation issued (HPD, open)
C
08/18/2026
Violation issued (HPD, open)
A
07/10/2026
Violation issued (HPD, closed)
B
07/10/2026
Violation issued (HPD, closed)
B
07/10/2026
Violation issued (HPD, open)
B
07/10/2026
Violation issued (HPD, closed)
A
07/04/2026
Violation issued (HPD, closed)
C
07/04/2026
Violation issued (HPD, closed)
C
06/27/2026
Violation issued (HPD, closed)
B
06/27/2026
Violation issued (HPD, closed)
B
06/27/2026
Violation issued (HPD, open)
B
06/27/2026
Violation issued (HPD, open)
C
06/27/2026
Violation issued (HPD, closed)
B
06/27/2026
Violation issued (HPD, open)
C
06/27/2026
Violation issued (HPD, closed)
B
06/27/2026
Violation issued (HPD, open)
A
06/27/2026
Violation issued (HPD, closed)
B
06/27/2026
Violation issued (HPD, closed)
B
06/27/2026
Violation issued (HPD, open)
B
06/27/2026
Violation issued (HPD, closed)
B
06/27/2026
Violation issued (HPD, closed)
B
06/24/2026
Violation issued (HPD, open)
B
06/17/2026
Violation issued (HPD, open)
B
06/17/2026
Violation issued (HPD, closed)
B
06/16/2026
Violation issued (HPD, open)
C
06/09/2026
Violation issued (HPD, closed)
C
06/09/2026
Violation issued (HPD, closed)
B
06/09/2026
Violation issued (HPD, closed)
C
06/09/2026
Violation issued (HPD, closed)
C
06/08/2026
Violation issued (HPD, open)
B
06/07/2026
Violation issued (HPD, closed)
B
06/07/2026
Violation issued (HPD, closed)
B
06/07/2026
Violation issued (HPD, closed)
B
06/07/2026
Violation issued (HPD, closed)
B
06/07/2026
Violation issued (HPD, closed)
B
06/07/2026
Violation issued (HPD, closed)
B
06/07/2026
Violation issued (HPD, closed)
B
06/07/2026
Violation issued (HPD, closed)
B
06/07/2026
Violation issued (HPD, closed)
B
06/07/2026
Violation issued (HPD, closed)
B
05/11/2026
Violation issued (HPD, open)
B
05/11/2026
Violation issued (HPD, closed)
B
05/11/2026
Violation issued (HPD, open)
B
05/11/2026
Violation issued (HPD, closed)
B
05/11/2026
Violation issued (HPD, open)
B
05/11/2026
Violation issued (HPD, closed)
B
05/11/2026
Violation issued (HPD, closed)
B
05/11/2026
Violation issued (HPD, closed)
A
05/11/2026
Violation issued (HPD, closed)
B
05/11/2026
Violation issued (HPD, open)
B
05/11/2026
Violation issued (HPD, closed)
B
05/11/2026
Violation issued (HPD, closed)
B
05/11/2026
Violation issued (HPD, closed)
C
05/11/2026
Violation issued (HPD, closed)
B
05/11/2026
Violation issued (HPD, closed)
B
05/11/2026
Violation issued (HPD, closed)
B
05/11/2026
Violation issued (HPD, closed)
B
05/11/2026
Violation issued (HPD, closed)
B
05/11/2026
Violation issued (HPD, open)
B
Latest 60 of 133 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWBoiler EquipmentSigned-offG. BAUER, INC08/06/2021
DOB NOWGeneral ConstructionPermit Issued2260 MAG CORP07/26/2021
DOB NOWGeneral ConstructionPermit Issued2260 MAG CORP07/26/2021
DOB NOWSidewalk ShedPermit IssuedKAJ NY CONSTRUCTION INC07/25/2019
DOB NOWSidewalk ShedSigned-offKAJ NY CONSTRUCTION INC08/02/2018
DOB NOWSidewalk ShedSigned-offKAJ NY CONSTRUCTION INC06/19/2018
BISOTISSUEDBEST ENERGY POWER 2015 LL07/16/2020
BISOTISSUEDUNIVERSAL CONSTRUCTION IN07/10/2018
BISFSISSUEDG. BAUER, INC04/06/2012
BISPLISSUEDALAN E. ROSENBERG, INC.04/04/2012
BISOTISSUEDUNIVERSAL CONSTRUCTION IN06/03/2005
BISOTISSUEDSNR CONSTRUCTION INC02/01/2001
BISEQISSUEDEXCLUSIVELY YOURS/MRN INC04/21/1998
BISPLISSUEDC JAMES PLBG & HTG INC04/21/1998
BISOTISSUEDEXCLUSIVELY YOURS/MRN INC04/08/1998
BISPLISSUEDHARON PLUMBING & HEATING CORP.12/23/1993
BISOTISSUEDSTRIANO CONTRACTING CORP.11/10/1993
BISPLISSUEDST. MARKS PLUMBING CO.11/08/1990
BISOTISSUEDPOWERS CONTRACTING07/23/1990
1 project · most recent 07/15/2021
Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
07/15/2021Permit Issued2260 MAG CORPVentilation Systems
Ventilation
Captiveaire MODEL # NCA18HPFA 3,500 CFM · Kitchen Exhaust ×3
7 projects · most recent 05/19/2026
General Wiring Boiler Controls
FiledStatusContractorScope
05/19/2026Permit IssuedMAGNA ELECTRIC CORP89 meters
06/14/2023Permit IssuedLOUIS CORREAGeneral Wiring
06/27/2021CompleteCOUNTY ELECL CONTRACTOR IBoiler Controls
12/04/2019CompleteRJ RUSSO ELECTRIC CO.—
07/24/2019CompleteRICHARD NEU—
06/18/2018CompleteRICHARD NEU—
04/20/2018Complete247 ELECTRICAL CORP—
1 project · most recent 07/24/2019
Sidewalk Shed
FiledStatusContractorScope
07/24/2019Permit IssuedKAJ NY CONSTRUCTION INCSidewalk Shed
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
07/11/2022Pass-Final Boiler Equipment InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 17
DateRequirementInspectorRole
06/23/2025Tenant Protection Plan Compliance—special
06/23/2025Energy Code Compliance Inspections—progress
06/23/2025Metering—energy_progress
06/23/2025Fenestration and door U-factor and product ratings—energy_progress
06/23/2025Air barrier - visual inspection—energy_progress
06/23/2025Fenestration areas—energy_progress
06/23/2025Fenestration air leakage—energy_progress
06/24/2021Fire-Resistant Penetrations and JointsSUNGBOM YIspecial
06/24/2021Maintenance informationSUNGBOM YIenergy_progress
06/24/2021Electrical motors and elevatorsSUNGBOM YIenergy_progress
06/24/2021Duct leakage testing, insulation and designSUNGBOM YIenergy_progress
06/23/2021Mechanical SystemsSUNGBOM YIspecial
06/23/2021FinalDAVIDSON CHRISTMASprogress
05/25/2021Maintenance informationLOUIS ARENAenergy_progress
05/25/2021HVAC-R and service water heating system controlsLOUIS ARENAenergy_progress
05/25/2021Heating SystemsLOUIS ARENAspecial
05/25/2021HVAC-R and service water heating equipmentLOUIS ARENAenergy_progress
▾Documents — 90 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch3
08/26/2026X00054348-I1Request digital key ↗
08/25/2026X00545283-I1Request digital key ↗
08/25/2026X00528762-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
08/26/2026X00199296-I1Request digital key ↗
▸Applications & Permits9
▸BISWORK PERMIT APPLICATION5
12/27/2019240266724Open ↗
07/10/2018240226778Open ↗
04/06/2012220177626Open ↗
Showing 3 of 5 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION4
01/15/2019240226778Open ↗
01/08/2019240226778Open ↗
06/25/2018240226778Open ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications24
▸DOB NOWProgress Inspector Seal & Signature7
09/23/2026X00528762-I1Open ↗
09/23/2026X00528762-I1Open ↗
09/23/2026X00528762-I1Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION4
10/22/2018240226778Open ↗
12/02/2013220177626Open ↗
04/05/2012220177626Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/26/2026X00054348-I1Open ↗
08/25/2026X00545283-I1Open ↗
08/13/2026X00528762-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
09/23/2026X00528762-I1Open ↗
08/27/2026X00545283-I1Open ↗
08/27/2026X00545283-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
06/25/2018240226778Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
12/23/2019240266724Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
04/05/2012220177626Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
06/25/2018240226778Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
06/25/2018240226778Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
04/05/2012220177626Open ↗
▸Trade Schedules & Equipment4
▸BISSELF-CERT PLUMBING NOTICE2
03/26/2013220177626Open ↗
08/31/2012220177626Open ↗
▸BISSCHEDULE B - PLUMBING1
04/05/2012220177626Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
04/05/2012220177626Open ↗
▸Safety & Tenant Protection3
▸BISTENANT PROTECTION PLAN AND NOTES2
12/23/2019240266724Open ↗
06/25/2018240226778Open ↗
▸DOB NOWTenant Protection Plan1
08/13/2026X00199296-I1Open ↗
▸Environmental & Asbestos5
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
12/23/2019240266724Open ↗
06/25/2018240226778Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/25/2026X00545283-I1Open ↗
08/13/2026X00528762-I1Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
04/05/2012220177626Open ↗
▸Energy Compliance13
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
09/17/2020240266724Open ↗
12/23/2019240266724Open ↗
06/25/2018240226778Open ↗
▸BISAS-BUILT ENERGY ANALYSIS3
09/17/2020240266724Open ↗
10/22/2018240226778Open ↗
12/02/2013220177626Open ↗
▸BISTECHNICAL REPORT: ENERGY2
04/05/2012220177626Open ↗
04/05/2012220177626Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
12/23/2019240266724Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
09/23/2020240266724Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
12/02/2013220177626Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026X00528762-I1Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026X00528762-I1Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY3
09/17/2020240266724Open ↗
12/23/2019240266724Open ↗
06/25/2018240226778Open ↗
▸Approvals, Objections & Sign-offs10
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
12/02/2020240266724Open ↗
01/15/2019240226778Open ↗
01/02/2019240226778Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
09/17/2020240266724Open ↗
01/14/2019240226778Open ↗
12/02/2013220177626Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
09/17/2020240266724Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
04/05/2012220177626Open ↗
▸Cost, Insurance & Ownership6
▸BISCOST AFFIDAVIT6
09/23/2020240266724Open ↗
12/23/2019240266724Open ↗
10/22/2018240226778Open ↗
Showing 3 of 6 on file for this type
▸Filing & Intake Forms8
▸BISBOROUGH INTAKE FORM4
01/15/2019240226778Open ↗
01/08/2019240226778Open ↗
01/02/2019240226778Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET2
12/23/2019240266724Open ↗
06/25/2018240226778Open ↗
▸BISEFILING COVER SHEET1
04/05/2012220177626Open ↗
▸BISADDITIONAL INFORMATION1
11/09/2020240266724Open ↗
▸Other Documents1
▸BISTax Abatement Miscellaneous1
09/17/2020240266724Open ↗