| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/23/2023 | Complete | BERGER QUALITY ELEC'L CON | General Wiring |
| 02/07/2023 | Complete | RICHARD NEU | — |
| 07/27/2022 | Complete | RICHARD NEU | — |
| Owner | Filings | Most Recent |
|---|---|---|
| J G CONSTRUCTION SRVCS | 7 | 07/08/2026 |
| 103 BERKELEY PLACE HOUSING | 7 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MJ ENGINEERING & DESIGN | 2 | 08/23/2023 |
| DRD STUDIO | 3 | 01/03/2023 |
| MOHAMMAD AHEAD, PE | 1 | 07/22/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| ARSENAL BUILDING CONSULTANTS LLC | 2 | 03/21/2026 |
| ZEN CONSTRUCTION CONSULTING | 5 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AXIOS DEVELOPMENT CORP | General Contractor | 7 | 07/08/2026 |
| J & G CONSTRUCTION SVCS | General Contractor | 4 | 07/08/2026 |
| CEGF & G PLUMBING CORP | Plumbing | 2 | 07/08/2026 |
| BONHOMME GERBERT | Electrical | 1 | 03/21/2026 |
| GERBERT BONHOMME | Electrical | 1 | 03/21/2026 |
| RICHARD NEU | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MJ ENGINEERING & DESIGN | 5546 | 2 | 08/23/2023 |
| INTEGRITY CONSULTING SERV | 666 | 1 | 09/29/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | AXIOS DEVELOPMENT CORP | 10/05/2023 |
| DOB NOW | Mechanical Systems | Signed-off | AXIOS DEVELOPMENT CORP | 10/05/2023 |
| DOB NOW | Plumbing | Signed-off | BELL CONST SERV INC | 01/11/2023 |
| DOB NOW | Plumbing | Signed-off | BELL CONST SERV INC | 11/15/2022 |
| DOB NOW | General Construction | Signed-off | AXIOS DEVELOPMENT CORP | 11/03/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | J & G CONSTRUCTION SVCS | 07/22/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | J & G CONSTRUCTION SVCS | 07/22/2022 |
| BIS | PL | ISSUED | FLYTIGER P & H LTD | 09/02/2014 |
| BIS | OT | ISSUED | TBRO'S RENOVATION INC | 08/25/2014 |
| BIS | PL | ISSUED | ORBIT PLBG & HTG INC | 12/05/2013 |
| BIS | OT | ISSUED | LEADER CONSTRUCTION | 10/29/2013 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/15/2023 | Fire-Resistant Penetrations and Joints | Magdy Youssef | special |
| 08/15/2023 | Maintenance information | Magdy Youssef | energy_progress |
| 08/15/2023 | HVAC-R and service water piping design and insulation | Magdy Youssef | energy_progress |
| 08/15/2023 | Structural Stability – Alterations of existing buildings | Magdy Youssef | special |
| 08/15/2023 | Structural Steel - Details | Magdy Youssef | special |
| 08/15/2023 | Structural Steel - High Strength Bolting | Magdy Youssef | special |
| 08/15/2023 | Structural Steel - Welding | Magdy Youssef | special |
| 08/15/2023 | HVAC-R and service water heating system controls | Magdy Youssef | energy_progress |
| 08/15/2023 | HVAC-R and service water heating equipment | Magdy Youssef | energy_progress |
| 08/14/2023 | Final | Magdy Youssef | progress |
| 08/14/2023 | Mechanical Systems | Magdy Youssef | special |
| 08/14/2023 | Final | Magdy Youssef | progress |
| 09/27/2022 | Fire-Resistant Penetrations and Joints | ALEKSANDR LEVIN | special |
| 09/27/2022 | Lighting in dwelling units | DALE RIEDL | energy_progress |
| 09/27/2022 | Final | DALE RIEDL | progress |