| Owner | Filings | Most Recent |
|---|---|---|
| NYC HOUSING PRES DEVELOPMENT | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| AVID DESIGNS, INC | 10 | 08/20/2024 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| WAHLER PLACE,LLC | General Contractor | 5 | 07/08/2026 |
| A & R ELEC'L CONTR'G INC. | Electrical | 1 | 03/22/2026 |
| DV PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| FLOW-RIGHT PLBG & HTG COR | Plumbing | 1 | 07/08/2026 |
| QUALITY PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AVID DESIGNS, INC. | 453 | 8 | 08/20/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | DV PLUMBING INC | 03/01/2024 |
| DOB NOW | Curb Cut | Signed-off | WAHLER PLACE,LLC | 01/30/2024 |
| DOB NOW | Plumbing | Signed-off | FLOW-RIGHT PLBG & HTG COR | 07/21/2023 |
| DOB NOW | Plumbing | Signed-off | QUALITY PLUMBING, INC | 07/21/2023 |
| DOB NOW | Earth Work | Permit Issued | WAHLER PLACE,LLC | 03/28/2023 |
| DOB NOW | Construction Fence | Signed-off | WAHLER PLACE,LLC | 03/10/2023 |
| BIS | — | ISSUED | PAUL TOTH EXCAVATION, INC. | 06/22/2017 |
| BIS | EQ | ISSUED | GATEWAY DEMO/CIVIL CORP | 03/15/2006 |
| BIS | — | ISSUED | GATEWAY DEMO/CIVIL CORP | 03/15/2006 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/20/2024 | Permit Issued | WAHLER PLACE,LLC | Heating and Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/20/2023 | Complete | A & R ELEC'L CONTR'G INC. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/20/2024 | Permit Issued | WAHLER PLACE,LLC | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/16/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/01/2024 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 05/10/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 03/27/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/22/2024 | Certified Sprinkler (PL)-Sprinkler-Hydro | Certified | View ↗ |
| 03/22/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/13/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/18/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/31/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| 08/30/2023 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 08/25/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/18/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/29/2024 | Mechanical Systems | Jeffrey Geary | special |
| 08/29/2024 | Subgrade Inspections | Jeffrey Geary | special |
| 08/29/2024 | Fire-Resistant Penetrations and Joints | Jeffrey Geary | special |
| 08/29/2024 | Concrete - Cast-In-Place | Jeffrey Geary | special |
| 08/29/2024 | Fire-Resistance Rated Construction | Jeffrey Geary | progress |
| 08/29/2024 | Structural Wood Frame | Jeffrey Geary | progress |
| 08/29/2024 | Final | Jeffrey Geary | progress |
| 08/29/2024 | Energy Code Compliance Inspections | Jeffrey Geary | progress |
| 08/29/2024 | Footing and Foundation | Jeffrey Geary | progress |
| 08/29/2024 | Lowest Floor Elevation | Jeffrey Geary | progress |
| 08/29/2024 | Air barrier — testing | Jeffrey Geary | energy_progress |
| 08/29/2024 | Permanent certificate | Jeffrey Geary | energy_progress |
| 08/29/2024 | Interior lighting power | Jeffrey Geary | energy_progress |
| 08/29/2024 | HVAC-R and service water piping design and insulation | Jeffrey Geary | energy_progress |
| 08/29/2024 | Metering | Jeffrey Geary | energy_progress |
| 08/29/2024 | HVAC-R and service water heating system controls | Jeffrey Geary | energy_progress |
| 08/29/2024 | Fenestration air leakage | Jeffrey Geary | energy_progress |
| 08/29/2024 | Fenestration areas | Jeffrey Geary | energy_progress |
| 08/29/2024 | Duct leakage testing, insulation and design | Jeffrey Geary | energy_progress |
| 08/29/2024 | Air barrier - visual inspection | Jeffrey Geary | energy_progress |
| 08/29/2024 | Fenestration and door U-factor and product ratings | Jeffrey Geary | energy_progress |
| 08/29/2024 | Ventilation and air distribution system | Jeffrey Geary | energy_progress |
| 08/29/2024 | HVAC-R and service water heating equipment | Jeffrey Geary | energy_progress |
| 08/29/2024 | Electric vehicle service equipment requirements | Jeffrey Geary | energy_progress |
| 08/29/2024 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | Jeffrey Geary | special |