| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/16/2023 | $400K | — | Private party → THINKTECH ENTERPRISE LLC | $78/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Greenlite Consulting | 2 | 09/10/2023 |
| Node Architecture, Engineering | 10 | 06/26/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| Node Architecture Engineering | 18 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| New Line Construction | General Contractor | 15 | 07/08/2026 |
| New Line Construction | Scaffold | 5 | 07/08/2026 |
| AZ Contracting Group | Scaffold | 4 | 07/08/2026 |
| Go Pro Fire Protection | Fire Protection | 2 | 07/08/2026 |
| New Line Construction | specialty_contractor | 2 | 03/21/2026 |
| Infiniti Esc Plumbing | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| International Geotehcnica | 1795 | 5 | 06/26/2023 |
| Node Architecture, Engineering | 6799 | 8 | 06/26/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/26/2023 | Signed-off | New Line Construction | Heating and Air Conditioning Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/26/2023 | Signed-off | Infiniti Esc Plumbing | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/26/2023 | Signed-off | Go Pro Fire Protection | Concrete, Masonry |
| 05/20/2022 | Permit Issued | New Line Construction | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/26/2023 | HVAC-R and service water heating system controls | MICHAEL KARANTINIDIS, P.E. | energy_progress |
| 06/26/2023 | Maintenance information | MICHAEL KARANTINIDIS, P.E. | energy_progress |
| 06/26/2023 | Metering | MICHAEL KARANTINIDIS, P.E. | energy_progress |
| 06/26/2023 | HVAC-R and service water piping design and insulation | MICHAEL KARANTINIDIS, P.E. | energy_progress |
| 06/26/2023 | HVAC-R and service water heating equipment | MICHAEL KARANTINIDIS, P.E. | energy_progress |
| 06/26/2023 | Fire-Resistant Penetrations and Joints | Radomir Delic | special |
| 06/26/2023 | Fire-Resistant Penetrations and Joints | Radomir Delic | special |
| 06/26/2023 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | MICHAEL KARANTINIDIS, P.E. | special |
| 06/26/2023 | Energy Code Compliance Inspections | Radomir Delic | progress |
| 05/22/2023 | Concrete - Cast-In-Place | Radomir Delic | special |
| 05/22/2023 | Subsurface Conditions – Fill Placement & In-Place Density | MICHAEL KARANTINIDIS, P.E. | special |
| 05/22/2023 | Final | Radomir Delic | progress |
| 05/22/2023 | Footing and Foundation | Radomir Delic | progress |
| 05/22/2023 | Sprinkler Systems | MICHAEL KARANTINIDIS, P.E. | special |
| 05/22/2023 | Subgrade Inspections | Radomir Delic | special |
| 07/01/2022 | Concrete - Cast-In-Place | Radomir Delic | special |
| 07/01/2022 | Masonry | Radomir Delic | special |
| 07/01/2022 | Structural Cold-Formed Steel | Radomir Delic | special |
| 07/01/2022 | Final | Radomir Delic | progress |
| 05/05/2022 | Excavations - Sheeting, Shoring, and Bracing | Radomir Delic | special |