← Back
Two family converted from one family
104-14 185 STREET
QUEENS · St. Albans · BIN 4220867
💬 Discuss this project
1950Year Built
1.67Stories
B3Building Class
R3AZoning
1,323 sfGross Floor Area
2Units
Two family converted from one family · 3,600 sf lot · 0.37 FAR built · Flood zone X
Locations of Work
StructuralElectricalGeneral
Roof4p · 1 filing · 9 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC108/15/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SOLAR CONTRACTING LLCGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854108/15/2025
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
01/06/2026
Signed off — Alteration
Q01270846-I1
10/09/2025
Permit issued — Solar
Q01270846-I1-SL
08/15/2025
Filed — Alteration
Q01270846-I1
08/13/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
08/13/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
08/13/2025
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
08/13/2025
Special inspection requirement — Final
TOM PETERSEN
08/13/2025
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSOLAR CONTRACTING LLC10/09/2025
1 project · most recent 08/13/2025
FiledStatusContractorScope
08/13/2025CompleteVILLAGE ELECTL CONTRS INC—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
08/13/2025Fire-Resistant Penetrations and JointsTOM PETERSENspecial
08/13/2025Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
08/13/2025Energy Code Compliance InspectionsTOM PETERSENprogress
08/13/2025FinalTOM PETERSENprogress
08/13/2025Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/19/2026Q01270846-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/26/2026Q01270846-I1Open ↗
08/26/2026Q01270846-I1Open ↗
08/26/2026Q01270846-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/26/2026Q01270846-I1Open ↗
08/26/2026Q01270846-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01270846-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01270846-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01270846-I1Open ↗