← Back
Four families
104-25 115 STREET
QUEENS · South Ozone Park · BIN 4202773
💬 Discuss this project
1940Year Built
2.5Stories
C3Building Class
R4AZoning
4,025 sfGross Floor Area
4Units
Rent Stabilized0 Open ViolationsFDNY Report ↗
Four families · 3,887 sf lot · 1.04 FAR built · Flood zone X
Locations of Work
Architecture
Floor 32p · 2 filings · 20 docs
Floor 23p · 1 filing · 20 docs
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SD DESIGN STUDIO LLC903/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/09/2020$1.2M—Private party → Private party$289/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JIMENEZ BUILDING CONSULTING LLC601/05/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JRL SKYLINE1203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CUBE BUILDERS GROUP NYGeneral Contractor303/21/2026
PIPESTYLISTS, INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
M. INT'L ENGINEERING PLLC3129311/12/2021
Building Lifecycle
All (90)Filed (6)Permit Issued (2)Signed Off (2)Violation (25)Inspection (7)Objection (18)Special Inspection (30)
11/27/2023
Violation issued (HPD, closed)
I
03/28/2023
Violation issued (HPD, closed)
A
04/21/2022
Signed off — Alteration
PROPOSED INTERIOR RENOVATION ON CEL, 1ST THRU. 3RD FLOOR. CEILING, FLOORING & PARTITION WORKS AS PER PLAN. NO CHANGE IN USE, BULK, EGRESS OR OCCUPANCY.
Q00477579-I1
03/18/2022
Signed off — Alteration
PROPOSED INTERIOR RENOVATION ON CEL, 1ST THRU. 3RD FLOOR. PLUMBING & GAS WORKS AS PER PLAN. GENERAL CONSTRUCNTION WORK UNDER JOB #: Q00477579. NO CHANGE IN USE, BULK, EGRESS OR OCCUPANCY.
Q00528667-I1
03/04/2022
Violation issued (HPD, closed)
A
03/04/2022
Violation issued (HPD, closed)
I
02/22/2022
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
02/11/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/27/2022
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
01/24/2022
Inspection — No Access-Final PL - Up to 3 Requested Floors
No Access
View inspection ↗
01/06/2022
Special inspection requirement — HVAC-R and service water heating equipment
NANIK MASSAND
01/06/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
NANIK MASSAND
01/06/2022
Special inspection requirement — Energy Code Compliance Inspections
NANIK MASSAND
01/06/2022
Special inspection requirement — HVAC-R and service water heating system controls
NANIK MASSAND
01/06/2022
Special inspection requirement — Maintenance information
NANIK MASSAND
01/05/2022
Filed — Alteration
PROPOSED INTERIOR RENOVATION ON CEL, 1ST THRU. 3RD FLOOR. PLUMBING & GAS WORKS AS PER PLAN. GENERAL CONSTRUCNTION WORK UNDER JOB #: Q00477579. NO CHANGE IN USE, BULK, EGRESS OR OCCUPANCY.
Q00528667-P2
11/26/2021
Special inspection requirement — Energy Code Compliance Inspections
NANIK MASSAND
11/26/2021
Special inspection requirement — Interior lighting power
NANIK MASSAND
11/26/2021
Special inspection requirement — Maintenance information
NANIK MASSAND
11/26/2021
Special inspection requirement — Insulation placement and R values
NANIK MASSAND
11/26/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
NANIK MASSAND
11/26/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
NANIK MASSAND
11/26/2021
Special inspection requirement — Fire-Resistance Rated Construction
NANIK MASSAND
11/23/2021
Objection resolved — Addressed
11/17/2021
Objection raised — Scope
11/12/2021
Filed — Alteration
PROPOSED INTERIOR RENOVATION ON CEL, 1ST THRU. 3RD FLOOR. CEILING, FLOORING & PARTITION WORKS AS PER PLAN. NO CHANGE IN USE, BULK, EGRESS OR OCCUPANCY.
Q00477579-P4
11/12/2021
Special inspection requirement — Insulation placement and R values
NANIK MASSAND
11/12/2021
Special inspection requirement — Interior lighting power
NANIK MASSAND
11/12/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
NANIK MASSAND
11/12/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
NANIK MASSAND
11/12/2021
Special inspection requirement — Maintenance information
NANIK MASSAND
11/12/2021
Special inspection requirement — Energy Code Compliance Inspections
NANIK MASSAND
11/12/2021
Special inspection requirement — Fire-Resistance Rated Construction
NANIK MASSAND
09/03/2021
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
09/03/2021
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/03/2021
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
08/28/2021
Filed — Alteration
PROPOSED INTERIOR RENOVATION ON CEL, 1ST THRU. 3RD FLOOR. PLUMBING & GAS WORKS AS PER PLAN. GENERAL CONSTRUCNTION WORK UNDER JOB #: Q00477579. NO CHANGE IN USE, BULK, EGRESS OR OCCUPANCY.
Q00528667-P1
08/28/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
NANIK MASSAND
08/28/2021
Special inspection requirement — Energy Code Compliance Inspections
NANIK MASSAND
08/28/2021
Special inspection requirement — HVAC-R and service water heating system controls
NANIK MASSAND
08/28/2021
Special inspection requirement — Maintenance information
NANIK MASSAND
08/28/2021
Special inspection requirement — HVAC-R and service water heating equipment
NANIK MASSAND
08/11/2021
Objection resolved — Addressed
07/22/2021
Objection raised — Zoning
07/08/2021
Filed — Alteration
PROPOSED INTERIOR RENOVATION ON CEL, 1ST THRU. 3RD FLOOR. CEILING, FLOORING & PARTITION WORKS AS PER PLAN. NO CHANGE IN USE, BULK, EGRESS OR OCCUPANCY.
Q00477579-P3
07/08/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
NANIK MASSAND
07/08/2021
Special inspection requirement — Interior lighting power
NANIK MASSAND
07/08/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
NANIK MASSAND
07/08/2021
Special inspection requirement — Maintenance information
NANIK MASSAND
07/08/2021
Special inspection requirement — Insulation placement and R values
NANIK MASSAND
07/08/2021
Special inspection requirement — Fire-Resistance Rated Construction
NANIK MASSAND
06/15/2021
Permit issued — General Construction
Q00477579-I1-GC
06/10/2021
Permit issued — Plumbing
Q00528667-I1-PL
05/28/2021
Filed — Alteration
PROPOSED INTERIOR RENOVATION ON CEL, 1ST THRU. 3RD FLOOR. PLUMBING & GAS WORKS AS PER PLAN. GENERAL CONSTRUCNTION WORK UNDER JOB #: Q00477579. NO CHANGE IN USE, BULK, EGRESS OR OCCUPANCY.
Q00528667-I1
05/20/2021
Objection resolved — Addressed
05/20/2021
Objection resolved — Addressed
04/22/2021
Objection resolved — Addressed
04/15/2021
Violation issued (HPD, closed)
A
04/07/2021
Objection resolved — Addressed
03/24/2021
Objection resolved — Addressed
Latest 60 of 90 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offCUBE BUILDERS GROUP NY06/15/2021
DOB NOWPlumbingSigned-offT & T PLUMBING INC06/10/2021
BISFSISSUEDJ.J. JOHNSTON CO INC11/09/1995
2 projects · most recent 04/20/2021
General Wiring
FiledStatusContractorScope
04/20/2021CompleteERIC & NG ELEC'L, INC.General Wiring
03/17/2021CancelledJAMES LEWIS ELECT'L CORP5 meters
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
02/22/2022Pass-Final General Construction Non-Directive 14PassView ↗
02/11/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/27/2022Fail-Final General Construction Non-Directive 14FailView ↗
01/24/2022No Access-Final PL - Up to 3 Requested FloorsNo AccessView ↗
09/03/2021Certified Gas-Gas-Piping-RoughingCertifiedView ↗
09/03/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/03/2021Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 31
DateRequirementInspectorRole
01/06/2022HVAC-R and service water heating equipmentNANIK MASSANDenergy_progress
01/06/2022HVAC-R and service water piping design and insulationNANIK MASSANDenergy_progress
01/06/2022Energy Code Compliance InspectionsNANIK MASSANDprogress
01/06/2022HVAC-R and service water heating system controlsNANIK MASSANDenergy_progress
01/06/2022Maintenance informationNANIK MASSANDenergy_progress
11/26/2021Energy Code Compliance InspectionsNANIK MASSANDprogress
11/26/2021Interior lighting powerNANIK MASSANDenergy_progress
11/26/2021Maintenance informationNANIK MASSANDenergy_progress
11/26/2021Insulation placement and R valuesNANIK MASSANDenergy_progress
11/26/2021HVAC-R and service water piping design and insulationNANIK MASSANDenergy_progress
11/26/2021Fire-Resistant Penetrations and JointsNANIK MASSANDspecial
11/26/2021Fire-Resistance Rated ConstructionNANIK MASSANDprogress
11/12/2021Insulation placement and R valuesNANIK MASSANDenergy_progress
11/12/2021Interior lighting powerNANIK MASSANDenergy_progress
11/12/2021HVAC-R and service water piping design and insulationNANIK MASSANDenergy_progress
11/12/2021Fire-Resistant Penetrations and JointsNANIK MASSANDspecial
11/12/2021Maintenance informationNANIK MASSANDenergy_progress
11/12/2021Energy Code Compliance InspectionsNANIK MASSANDprogress
11/12/2021Fire-Resistance Rated ConstructionNANIK MASSANDprogress
08/28/2021HVAC-R and service water piping design and insulationNANIK MASSANDenergy_progress
08/28/2021Energy Code Compliance InspectionsNANIK MASSANDprogress
08/28/2021HVAC-R and service water heating system controlsNANIK MASSANDenergy_progress
08/28/2021Maintenance informationNANIK MASSANDenergy_progress
08/28/2021HVAC-R and service water heating equipmentNANIK MASSANDenergy_progress
07/08/2021Fire-Resistant Penetrations and JointsNANIK MASSANDspecial
Latest 25 of 31.
▾Documents — 50 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/27/2026Q00528667-I1Request digital key ↗
08/27/2026Q00528667-P2Request digital key ↗
08/27/2026Q00528667-P1Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION3
04/21/2021400579897Open ↗
04/08/2021400579897Open ↗
02/11/2021400579897Open ↗
▸Seals & Professional Certifications26
▸DOB NOWProgress Inspector Seal & Signature17
08/28/2026Q00528667-P1Open ↗
08/28/2026Q00528667-P1Open ↗
08/26/2026Q00528667-I1Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/27/2026Q00477579-I1Open ↗
08/27/2026Q00477579-P4Open ↗
08/27/2026Q00477579-P3Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/24/2026Q00477579-I1Open ↗
08/23/2026Q00477579-P3Open ↗
08/22/2026Q00477579-P4Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/27/2026Q00528667-I1Open ↗
08/27/2026Q00528667-P2Open ↗
08/27/2026Q00528667-P1Open ↗
Showing 3 of 6 on file for this type
▸Energy Compliance2
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026Q00528667-I1Open ↗
08/13/2026Q00477579-I1Open ↗
▸Approvals, Objections & Sign-offs3
▸BISLETTERS - SUPPORTING DOCUMENTATION3
04/21/2021400579897Open ↗
02/11/2021400579897Open ↗
12/31/2020400579897Open ↗
▸Cost, Insurance & Ownership3
▸BISDEPT OF FINANCE VERIFICATION1
04/21/2021400579897Open ↗
▸DOB NOWCertification by Insurance Broker or Agency1
08/13/2026Q00477579-I1Open ↗
▸DOB NOWCertificate of Insurance1
08/13/2026Q00477579-I1Open ↗
▸Other Documents1
▸DOB NOWAdditional Insured Authorizations1
08/13/2026Q00477579-I1Open ↗