← Back
Two stories - detached, small or mid-size
104-84 113 STREET
QUEENS · BIN 4202564
💬 Discuss this project
1905Year Built
2Stories
A1Building Class
R4AZoning
1,216 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 2,500 sf lot · 0.49 FAR built · Flood zone X
Locations of Work
Architecture
Permit Issued — active, not yet Signed-off
CellarUnder Construction2p · 1 filing · 8 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/20/2017$522K—Private party → Private party$429/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
HANSA BUILDING ENGINEERING SERVICES206/08/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
GEREBUZZA CONSTRUCTION INGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ASKON ARCHITECT, P.C.3596103/06/2026
Building Lifecycle
All (10)Filed (2)Permit Issued (1)Objection (4)Special Inspection (3)
06/08/2026
Filed — Alteration
FILING TO LEGALIZE EXISTING 2-PIECE BATHROOM (WC,WB), AND LAUNDRY(WASHER & DRYER) AT CELLAR. FILING IN-ORDER TO RESOLVE RCA UNDER COMPLAINT # 4A15464.
Q01367021-S1
05/01/2026
Permit issued — General Construction
Q01367021-I1-GC
04/29/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
03/31/2026
Objection resolved — Addressed
03/31/2026
Objection resolved — Addressed
03/24/2026
Objection raised — Admin
03/24/2026
Objection raised — Scope
03/06/2026
Filed — Alteration
FILING TO LEGALIZE EXISTING 2-PIECE BATHROOM (WC,WB), AND LAUNDRY(WASHER & DRYER) AT CELLAR. FILING IN-ORDER TO RESOLVE RCA UNDER COMPLAINT # 4A15464.
Q01367021-I1
03/03/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Akeeb Shekoni
03/03/2026
Special inspection requirement — Fire-Resistance Rated Construction
HANSA PERSAUD
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedGEREBUZZA CONSTRUCTION IN05/01/2026
1 project · most recent 06/08/2026
Gas Water/Sanitary
FiledStatusContractorScope
06/08/2026——Gas, Water/Sanitary
1 project · most recent 02/19/2026
General Wiring
FiledStatusContractorScope
02/19/2026Permit IssuedSNB ELECTRICAL CONTNG CORGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 3
DateRequirementInspectorRole
04/29/2026Fire-Resistant Penetrations and Joints—special
03/03/2026Fire-Resistant Penetrations and JointsAkeeb Shekonispecial
03/03/2026Fire-Resistance Rated ConstructionHANSA PERSAUDprogress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/17/2026Q01367021-S1Request digital key ↗
08/17/2026Q01367021-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/17/2026Q01367021-S1Open ↗
08/13/2026Q01367021-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/31/2026Q01367021-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/31/2026Q01367021-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/17/2026Q01367021-S1Open ↗
08/13/2026Q01367021-I1Open ↗