| Owner | Filings | Most Recent |
|---|---|---|
| PLATINUM SERVICES NY | 11 | 07/08/2026 |
| DORIA, INC | 5 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/09/2021 | $1.6M | — | Private party → PRESIDENT LOFTS 2 LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| ADVANCED ENGINEERING & INSPECT. PLL | 10 | 07/26/2023 |
| SKYLINE RIGGING | 1 | 02/13/2023 |
| ASHRAF CORP | 4 | 12/13/2022 |
| TITAN ENGINEERS PC | 2 | 11/15/2022 |
| S. WIEDER ARCHITECT P.C. | 2 | 10/27/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPEDITING 4 U | 14 | 03/21/2026 |
| PLATINUM SERVICES NY | 6 | 03/21/2026 |
| GREEN STUDIO | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PARK MANAGEMENT USA CORP | General Contractor | 13 | 07/08/2026 |
| DORIA, INC | General Contractor | 2 | 03/21/2026 |
| PIPE SOLUTIONS ADVIS INC | Plumbing | 2 | 07/08/2026 |
| PLATINUM SERVICES NY LLC | General Contractor | 2 | 07/08/2026 |
| TOVIA WERZBERGER | Electrical | 1 | 03/21/2026 |
| POWER DIRECT ELECTRIC INC 005103 | General Contractor | 1 | 03/22/2026 |
| S WIEDER ARCHITECT P C | General Contractor | 1 | 03/22/2026 |
| PIPING & PLUMBING SOLUTIO | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 12 | 07/26/2023 |
| SKYLINE RIGGING | 7880 | 1 | 02/13/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | PARK MANAGEMENT USA CORP | 07/10/2023 |
| DOB NOW | Mechanical Systems | Signed-off | PARK MANAGEMENT USA CORP | 06/07/2023 |
| DOB NOW | Structural | Signed-off | PARK MANAGEMENT USA CORP | 05/01/2023 |
| DOB NOW | Plumbing | Signed-off | PIPE SOLUTIONS ADVIS INC | 04/26/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | DORIA, INC | 02/13/2023 |
| DOB NOW | Sprinklers | Signed-off | EMPIRE PLUMBING INC | 01/26/2023 |
| DOB NOW | Construction Fence | Signed-off | PARK MANAGEMENT USA CORP | 01/20/2023 |
| DOB NOW | Supported Scaffold | Signed-off | PLATINUM SERVICES NY LLC | 12/14/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | PLATINUM SERVICES NY LLC | 09/30/2022 |
| DOB NOW | Plumbing | Signed-off | PIPE SOLUTIONS ADVIS INC | 09/14/2022 |
| DOB NOW | Structural | Signed-off | PARK MANAGEMENT USA CORP | 05/03/2022 |
| DOB NOW | Construction Fence | Signed-off | PARK MANAGEMENT USA CORP | 12/23/2021 |
| BIS | — | ISSUED | PARK MANAGEMENT USA CORP | 05/01/2023 |
| BIS | — | ISSUED | PARK MANAGEMENT USA CORP | 03/31/2023 |
| BIS | — | ISSUED | PARK MANAGEMENT USA CORP | 03/30/2022 |
| BIS | — | ISSUED | PARK MANAGEMENT USA CORP | 01/18/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/25/2023 | Complete | POWER DIRECT ELECTRIC INC | General Wiring |
| 10/18/2022 | Complete | STAR ELEC'L CONTRACTORS C | — |
| 03/25/2022 | Complete | POWER DIRECT ELECTRIC INC | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/20/2023 | Certified Sprinkler (SP) - Booster Pump Test | Certified | View ↗ |
| 07/19/2023 | Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test | Certified | View ↗ |
| 07/19/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/18/2023 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 07/17/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/11/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 05/04/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 04/21/2023 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 03/21/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 09/20/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/02/2023 | Post-installed Anchors | FAHAD FATEH | special |
| 08/02/2023 | Sprinkler Systems | FAHAD FATEH | special |
| 08/02/2023 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 07/23/2023 | Post-installed Anchors | FAHAD FATEH | special |
| 07/23/2023 | Sprinkler Systems | FAHAD FATEH | special |
| 07/23/2023 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 06/14/2023 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 06/14/2023 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | FAHAD FATEH | special |
| 06/14/2023 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 06/14/2023 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 06/14/2023 | Maintenance information | FAHAD FATEH | energy_progress |
| 06/14/2023 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 06/14/2023 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 06/13/2023 | Post-installed Anchors | FAHAD FATEH | special |
| 06/13/2023 | Sprinkler Systems | FAHAD FATEH | special |
| 06/13/2023 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 05/19/2023 | Maintenance information | FAHAD FATEH | energy_progress |
| 05/19/2023 | Heating Systems | FAHAD FATEH | special |
| 05/19/2023 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 05/19/2023 | Mechanical Systems | FAHAD FATEH | special |
| 05/19/2023 | Final | FAHAD FATEH | progress |
| 05/19/2023 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 05/19/2023 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 05/19/2023 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 05/19/2023 | Shutoff dampers | FAHAD FATEH | energy_progress |