1920Year Built
2.75Stories
C0Building Class
R4-1Zoning
2,953 sfGross Floor Area
3Units
Rent Stabilized2 Open Violations ▸FDNY Report ↗
Three families · 2,800 sf lot · 1.05 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbingGeneral
Floor 31p · 1 filing · 12 docs
Floor 22p · 2 filings · 18 docs
Floor 11p · 1 filing · 12 docs
Cellar7p · 2 filings · 18 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
08/19/2025$1.5M—Private party → Y&H REAL ESTATE SC LLC$522/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
FARHAD BASSIRI-TEHRANI602/09/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ECDESIGN STUDIO403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
KALE CONSTRUCTION INCGeneral Contractor104/09/2026
CATMAN PLUMBING INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BASSIRI8394302/09/2026
Building Lifecycle
All (35)Filed (6)Permit Issued (2)Signed Off (2)Violation (11)Inspection (5)Special Inspection (9)
05/01/2026
Violation issued (HPD, open)
A
03/30/2026
Signed off — Alteration
RENOVATION OF EXISTING CELLAR, 1ST, 2ND AND 3RD FLOOR WITH GENERAL CONSTRUCTION: NEW PARTITIONS, DOORS, FLOORING AND COSMETIC WORK; REPLACE CONCRETE STAIR AT FRONT YARD. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01279104-I1
03/30/2026
Signed off — Alteration
RENOVATION OF EXISTING CELLAR, 1ST, 2ND AND 3RD FLOOR WITH PLUMBING WORK:RELOCATE KITCHEN AND BATHROOM FIXTURES; NEW WASHER, DRYER, BOILERS AND HOT WATER HEATERS IN CELLAR; NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01279107-I1
03/27/2026
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
03/03/2026
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
02/10/2026
Special inspection requirement — Energy Code Compliance Inspections
FARHAD BASSIRI-TEHRANI
02/10/2026
Special inspection requirement — Fire-Resistance Rated Construction
FARHAD BASSIRI-TEHRANI
02/10/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
FARHAD BASSIRI-TEHRANI
02/09/2026
Filed — Alteration
RENOVATION OF EXISTING CELLAR, 1ST, 2ND AND 3RD FLOOR WITH PLUMBING WORK:RELOCATE KITCHEN AND BATHROOM FIXTURES; NEW WASHER, DRYER, BOILERS AND HOT WATER HEATERS IN CELLAR; NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01279107-P2
02/09/2026
Filed — Alteration
RENOVATION OF EXISTING CELLAR, 1ST, 2ND AND 3RD FLOOR WITH GENERAL CONSTRUCTION: NEW PARTITIONS, DOORS, FLOORING AND COSMETIC WORK; REPLACE CONCRETE STAIR AT FRONT YARD. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01279104-P2
02/09/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
FARHAD BASSIRI-TEHRANI
02/09/2026
Special inspection requirement — Energy Code Compliance Inspections
FARHAD BASSIRI-TEHRANI
02/09/2026
Special inspection requirement — Fire-Resistance Rated Construction
FARHAD BASSIRI-TEHRANI
12/09/2025
Filed — Alteration
RENOVATION OF EXISTING CELLAR, 1ST, 2ND AND 3RD FLOOR WITH PLUMBING WORK:RELOCATE KITCHEN AND BATHROOM FIXTURES; NEW WASHER, DRYER, BOILERS AND HOT WATER HEATERS IN CELLAR; NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01279107-P1
12/09/2025
Filed — Alteration
RENOVATION OF EXISTING CELLAR, 1ST, 2ND AND 3RD FLOOR WITH GENERAL CONSTRUCTION: NEW PARTITIONS, DOORS, FLOORING AND COSMETIC WORK; REPLACE CONCRETE STAIR AT FRONT YARD. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01279104-P1
12/08/2025
Special inspection requirement — Fire-Resistance Rated Construction
FARHAD BASSIRI-TEHRANI
12/08/2025
Special inspection requirement — Energy Code Compliance Inspections
FARHAD BASSIRI-TEHRANI
12/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FARHAD BASSIRI-TEHRANI
11/20/2025
Violation issued (HPD, open)
I
10/31/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
10/31/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/28/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
09/09/2025
Permit issued — General Construction
B01279104-I1-GC
09/08/2025
Permit issued — Plumbing
B01279107-I1-PL
09/05/2025
Filed — Alteration
RENOVATION OF EXISTING CELLAR, 1ST, 2ND AND 3RD FLOOR WITH GENERAL CONSTRUCTION: NEW PARTITIONS, DOORS, FLOORING AND COSMETIC WORK; REPLACE CONCRETE STAIR AT FRONT YARD. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01279104-I1
09/05/2025
Filed — Alteration
RENOVATION OF EXISTING CELLAR, 1ST, 2ND AND 3RD FLOOR WITH PLUMBING WORK:RELOCATE KITCHEN AND BATHROOM FIXTURES; NEW WASHER, DRYER, BOILERS AND HOT WATER HEATERS IN CELLAR; NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01279107-I1
06/06/2025
Violation issued (HPD, closed)
A
04/08/2024
Violation issued (HPD, closed)
A
11/21/2023
Violation issued (HPD, closed)
I
03/21/2023
Violation issued (HPD, closed)
A
02/22/2022
Violation issued (HPD, closed)
I
02/22/2022
Violation issued (HPD, closed)
A
04/06/2021
Violation issued (HPD, closed)
A
11/03/2016
Violation issued (HPD, closed)
I
10/07/2015
Violation issued (HPD, closed)
I
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offKALE CONSTRUCTION INC09/09/2025
DOB NOWPlumbingSigned-offCATMAN PLUMBING INC09/08/2025
Nothing on file for this building.
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
03/27/2026Pass-Final General Construction Non-Directive 14PassView ↗
03/03/2026Fail-Final General Construction Non-Directive 14FailView ↗
10/31/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
10/31/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/28/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 9
DateRequirementInspectorRole
02/10/2026Energy Code Compliance InspectionsFARHAD BASSIRI-TEHRANIprogress
02/10/2026Fire-Resistance Rated ConstructionFARHAD BASSIRI-TEHRANIprogress
02/10/2026Fire-Resistant Penetrations and JointsFARHAD BASSIRI-TEHRANIspecial
02/09/2026Fire-Resistant Penetrations and JointsFARHAD BASSIRI-TEHRANIspecial
02/09/2026Energy Code Compliance InspectionsFARHAD BASSIRI-TEHRANIprogress
02/09/2026Fire-Resistance Rated ConstructionFARHAD BASSIRI-TEHRANIprogress
12/08/2025Fire-Resistance Rated ConstructionFARHAD BASSIRI-TEHRANIprogress
12/08/2025Energy Code Compliance InspectionsFARHAD BASSIRI-TEHRANIprogress
12/08/2025Fire-Resistant Penetrations and JointsFARHAD BASSIRI-TEHRANIspecial
▾Documents — 18 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/19/2026B01279104-P2Request digital key ↗
08/19/2026B01279104-P1Request digital key ↗
08/19/2026B01279104-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸Seals & Professional Certifications12
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/19/2026B01279104-P1Open ↗
08/19/2026B01279104-I1Open ↗
08/18/2026B01279107-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
09/01/2026B01279104-P1Open ↗
08/31/2026B01279104-I1Open ↗
08/23/2026B01279104-P2Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
09/01/2026B01279104-P1Open ↗
08/31/2026B01279104-I1Open ↗
08/23/2026B01279104-P2Open ↗