| Owner | Filings | Most Recent |
|---|---|---|
| WMC ASSOCIATES | 129 | 09/02/2026 |
| A RODRIGUEZ CONSTRUCTION LLC | 8 | 07/08/2026 |
| WMC ASSOCI | 7 | 03/21/2026 |
| RODCON GROUP | 4 | 04/09/2026 |
| WMDC ASSOCIATES L P | 4 | 03/22/2026 |
| W MW C ASSOCIATES L P | 2 | 03/21/2026 |
| QUANTUM DESIGN | 2 | 03/21/2026 |
| WMDC PROPERTIES | 2 | 03/21/2026 |
| NEW YORK CITY PUBLIC SCHOOL | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| PCS ENGINEERING | 1 | 01/09/2025 |
| MSM ENGINEERING SERVICES, PLLC | 3 | 08/21/2024 |
| BUILDING CONSULTING ENGINEERING | 2 | 05/11/2024 |
| ALWAYS FAST SERVICES CORP | 1 | 03/25/2024 |
| STRUCTURAL ENGINEERING TECHNOLOGIES | 1 | 08/02/2023 |
| ENTHINK ENGINEERS LLC | 1 | 04/10/2023 |
| WELLWORTH CONSULTING LLC | 1 | 02/03/2023 |
| KOSSAR + GARRY ARCHITECTS, LLP | 7 | 09/23/2022 |
| DAGHER ENGINEERING PLLC | 1 | 06/24/2022 |
| COLLADO ENGINEERING | 1 | 03/15/2022 |
| PINNACLE ENGINEERS PC | 3 | 08/13/2021 |
| PETRVS | 1 | 03/26/2021 |
| GREEN DESIGN | 3 | 10/05/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| JAMM DESIGN SAFETY | 2 | 03/21/2026 |
| BOHLER ENGINEERING | 4 | 03/21/2026 |
| PREEMPTIVE SOLUTIONS & CONSULTING L | 2 | 03/21/2026 |
| JOHN PATRICK BOHAN ARCHITECT | 1 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 2 | 03/21/2026 |
| NYCER | 1 | 03/21/2026 |
| RIGGING CONSULTANTS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ANDAMIO SCAFFOLDING LLC | General Contractor | 19 | 09/02/2026 |
| A.RODRIGUEZ CONS LLC | General Contractor | 7 | 07/08/2026 |
| ECC GROUP INC | General Contractor | 4 | 07/08/2026 |
| EVEREST SCAFFOLDING INC | General Contractor | 3 | 07/08/2026 |
| GEMINI ELECTRIC CO., INC. | Electrical | 3 | 03/22/2026 |
| ANDREW DRAZIC | Electrical | 2 | 03/21/2026 |
| WINICK PRODUCTIONS, LLC | General Contractor | 2 | 03/21/2026 |
| SKINNER PLUMBING & HEATING | Plumbing | 2 | 07/08/2026 |
| SPEEDWAY PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| GREGORY PAPANTONIOU | Electrical | 1 | 03/21/2026 |
| CHARAN ELEC'L ENTERP'S IN | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PCS ENGINEERING | 3745 | 1 | 01/09/2025 |
| COLLADO ENGINEERING, DPC | 3432 | 1 | 03/15/2022 |
| ROYAL CONSTRUCTION P.E. S | 462 | 1 | 03/26/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | ANDAMIO SCAFFOLDING LLC | 09/01/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | ANDAMIO SCAFFOLDING LLC | 06/11/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | ANDAMIO SCAFFOLDING LLC | 03/16/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | SPD CONSTRUCTION CORP | 12/11/2025 |
| DOB NOW | Supported Scaffold | Signed-off | ANDAMIO SCAFFOLDING LLC | 08/01/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | ANDAMIO SCAFFOLDING LLC | 03/18/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | SPD CONSTRUCTION CORP | 01/09/2025 |
| DOB NOW | Supported Scaffold | Signed-off | ANDAMIO SCAFFOLDING LLC | 08/05/2024 |
| DOB NOW | Sidewalk Shed | Permit Issued | ANDAMIO SCAFFOLDING LLC | 03/26/2024 |
| DOB NOW | Supported Scaffold | Signed-off | RODCON GROUP LLC | 03/14/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 09/21/2023 |
| DOB NOW | Supported Scaffold | Signed-off | RODCON GROUP LLC | 04/10/2023 |
| DOB NOW | Supported Scaffold | Signed-off | ANDAMIO SCAFFOLDING LLC | 02/04/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 09/27/2022 |
| DOB NOW | Plumbing | Signed-off | SPEEDWAY PLUMBING CORP | 09/08/2022 |
| DOB NOW | Plumbing | Signed-off | SKINNER PLUMBING & HEATIN | 04/11/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | ANDAMIO SCAFFOLDING LLC | 10/07/2021 |
| DOB NOW | General Construction | Signed-off | WINICK PRODUCTIONS, LLC | 08/17/2021 |
| DOB NOW | General Construction | Signed-off | ECC GROUP INC | 07/28/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | EVEREST SCAFFOLDING INC | 05/25/2021 |
| DOB NOW | Plumbing | Signed-off | SKINNER PLUMBING & HEATIN | 04/19/2021 |
| DOB NOW | General Construction | Signed-off | ECC GROUP INC | 04/07/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | EVEREST SCAFFOLDING INC | 06/03/2020 |
| BIS | OT | ISSUED | A.RODRIGUEZ CONS LLC | 11/12/2025 |
| BIS | OT | ISSUED | A.RODRIGUEZ CONS LLC | 11/10/2025 |
| BIS | OT | ISSUED | A.RODRIGUEZ CONS LLC | 10/16/2024 |
| BIS | OT | ISSUED | A.RODRIGUEZ CONS LLC | 05/02/2024 |
| BIS | OT | ISSUED | A.RODRIGUEZ CONS LLC | 10/12/2022 |
| BIS | OT | ISSUED | A.RODRIGUEZ CONS LLC | 10/25/2021 |
| BIS | OT | ISSUED | A.RODRIGUEZ CONS LLC | 01/20/2021 |
| BIS | OT | ISSUED | A.RODRIGUEZ CONS LLC | 07/08/2020 |
| BIS | SP | ISSUED | SKINNER PLMNG & HTG CORP | 01/22/2020 |
| BIS | OT | ISSUED | WINICK PRODUCTIONS, LLC | 09/10/2019 |
| BIS | OT | ISSUED | A.RODRIGUEZ CONS LLC | 09/05/2019 |
| BIS | OT | ISSUED | ECC GROUP INC | 07/25/2019 |
| BIS | PL | ISSUED | SPEEDWAY PLUMBING CORP | 02/20/2019 |
| BIS | SP | ISSUED | SKINNER PLMNG & HTG CORP | 09/21/2018 |
| BIS | SP | ISSUED | SKINNER PLMNG & HTG CORP | 09/21/2018 |
| BIS | PL | ISSUED | TERMINATOR PLBG & HTG INC | 11/06/2017 |
| BIS | BL | ISSUED | TERMINATOR PLBG & HTG INC | 11/06/2017 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/24/2022 | — | — | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/15/2026 | Permit Issued | ANCO ELECTL CONTCTNG INC | General Wiring |
| 10/17/2025 | Complete | GEMINI ELECTRIC CO., INC. | — |
| 08/07/2024 | Permit Issued | GEMINI ELECTRIC CO., INC. | General Wiring |
| 06/21/2024 | Complete | A.T.J. ELECTRICAL CO.INC. | General Wiring |
| 05/21/2024 | Permit Issued | A.T.J. ELECTRICAL CO.INC. | General Wiring |
| 04/03/2024 | Permit Issued | BOROWIDE ELECT'L CONTR'S | — |
| 01/09/2024 | Complete | GEMINI ELECTRIC CO., INC. | — |
| 08/23/2023 | Complete | GEMINI ELECTRIC CO., INC. | General Wiring |
| 09/30/2022 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 05/16/2022 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 04/20/2021 | Complete | A.S.K. ELECTRICAL CORP | General Wiring |
| 06/04/2020 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| 01/08/2020 | Complete | WCK ELECTRIC CORP. | General Wiring |
| 04/09/2019 | Permit Issued | TRANSEL ELEV. & ELEC. INC | General Wiring |
| 07/23/2018 | Complete | LASER ELEC'L CONSTR'G INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/02/2023 | — | — | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/21/2024 | Permit Issued | ANDAMIO SCAFFOLDING LLC | Sidewalk Shed |
| 11/02/2020 | — | — | Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/11/2024 | — | — | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/11/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 06/14/2023 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 10/28/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/25/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/20/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/14/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/18/2022 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | Elias Dagher | special |
| 03/10/2022 | Post-installed Anchors | Albert Collado | special |
| 03/10/2022 | Energy Code Compliance Inspections | Albert Collado | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| NEP Studios | Office | Floor 2 | Project M07997290 Project M00753878 |