← Back
Two family frame
10524 AVENUE N
BROOKLYN · Canarsie · BIN 3234942
💬 Discuss this project
1960Year Built
1Stories
B2Building Class
R3XZoning
2,288 sfGross Floor Area
2Units
Two family frame · 5,000 sf lot · 0.46 FAR built · Flood zone X500
Locations of Work
ElectricalOther
Roof2p · 2 filings · 15 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR203/11/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281203/11/2026
Building Lifecycle
All (19)Filed (2)Permit Issued (2)Signed Off (2)Objection (2)Special Inspection (11)
08/07/2026
Signed off — Alteration
installation of solar panels, rooftop, railed, grid-tied, 4 modules, 1.64 KW
B01369958-I1
05/19/2026
Signed off — Alteration
Installation of solar panels, rooftop, grid tied, RAILED (9.6KW)(24MODULES)
B00974295-I1
03/13/2026
Permit issued — Solar
B01369958-I1-SL
03/11/2026
Filed — Alteration
installation of solar panels, rooftop, railed, grid-tied, 4 modules, 1.64 KW
B01369958-I1
03/10/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
03/10/2026
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
Mina Makar
03/10/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
03/10/2026
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
03/10/2026
Special inspection requirement — Final
Mina Makar
03/10/2026
Special inspection requirement — Air barrier - visual inspection
Mina Makar
12/29/2023
Permit issued — Solar
B00974295-I1-SL
12/19/2023
Objection resolved — Addressed
12/14/2023
Objection raised — Scope
12/08/2023
Filed — Alteration
Installation of solar panels, rooftop, grid tied, RAILED (9.6KW)(24MODULES)
B00974295-I1
12/08/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
12/08/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
12/08/2023
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
12/08/2023
Special inspection requirement — Final
Mina Makar
12/08/2023
Special inspection requirement — Air barrier - visual inspection
Mina Makar
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR03/13/2026
DOB NOWSolarSigned-offMOMENTUM SOLAR12/29/2023
2 projects · most recent 06/10/2026
FiledStatusContractorScope
06/10/2026CompleteISLAND ELECTRIC CORP—
12/08/2023CompleteISLAND ELECTRIC CORP—
2 projects · most recent 03/11/2026
FiledStatusContractorScope
03/11/2026Signed-offMOMENTUM SOLAR8 panels, 3.28 kw, 70 roof_area_sqft
12/08/2023Signed-offMOMENTUM SOLAR24 panels, 9.6 kw, 422 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 11
DateRequirementInspectorRole
03/10/2026Fire-Resistant Penetrations and JointsMina Makarspecial
03/10/2026Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)Mina Makarspecial
03/10/2026Structural Stability – Alterations of existing buildingsMina Makarspecial
03/10/2026Energy Code Compliance InspectionsMina Makarprogress
03/10/2026FinalMina Makarprogress
03/10/2026Air barrier - visual inspectionMina Makarenergy_progress
12/08/2023Fire-Resistant Penetrations and JointsMina Makarspecial
12/08/2023Structural Stability – Alterations of existing buildingsMina Makarspecial
12/08/2023Energy Code Compliance InspectionsMina Makarprogress
12/08/2023FinalMina Makarprogress
12/08/2023Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 15 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/26/2026B00974295-I1Request digital key ↗
08/18/2026B01369958-I1Request digital key ↗
▸Seals & Professional Certifications9
▸DOB NOWProgress Inspector Seal & Signature4
08/26/2026B01369958-I1Open ↗
08/26/2026B01369958-I1Open ↗
08/24/2026B00974295-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/26/2026B01369958-I1Open ↗
08/26/2026B01369958-I1Open ↗
08/24/2026B00974295-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/26/2026B00974295-I1Open ↗
08/13/2026B01369958-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/26/2026B00974295-I1Open ↗
08/13/2026B01369958-I1Open ↗
▸Approvals, Objections & Sign-offs2
▸DOB NOWUtility Company Final Acceptance Letter2
08/18/2026B01369958-I1Open ↗
08/13/2026B00974295-I1Open ↗