← Back
Two family frame
10544 FLATLANDS 6 STREET
BROOKLYN · Canarsie · BIN 3233285
💬 Discuss this project
1970Year Built
1Stories
B2Building Class
R3XZoning
2,330 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family frame · 4,167 sf lot · 0.56 FAR built · Flood zone X500
Locations of Work
Electrical
Roof2p · 1 filing · 9 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC105/21/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNRUN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN INSTALLATION SVCGeneral Contractor203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272105/21/2024
Building Lifecycle
All (11)Filed (1)Permit Issued (1)Signed Off (1)Violation (3)Special Inspection (5)
12/09/2024
Signed off — Alteration
B01051090-I1
05/29/2024
Permit issued — Solar
B01051090-I1-SL
05/21/2024
Filed — Alteration
B01051090-I1
05/14/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
05/14/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
05/14/2024
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
05/14/2024
Special inspection requirement — Final
Walid Abdulla
05/14/2024
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
03/25/2022
Violation issued (ECB, closed)
Construction
08/11/2021
Violation issued (ECB, closed)
Zoning
09/16/2020
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC05/29/2024
1 project · most recent 06/26/2024
General Wiring
FiledStatusContractorScope
06/26/2024CompleteSUNRUN SOLAR ELECTL CORPGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
05/14/2024Fire-Resistant Penetrations and JointsWalid Abdullaspecial
05/14/2024Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
05/14/2024Energy Code Compliance InspectionsWalid Abdullaprogress
05/14/2024FinalWalid Abdullaprogress
05/14/2024Air barrier - visual inspectionWalid Abdullaenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/25/2026B01051090-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/30/2026B01051090-I1Open ↗
08/30/2026B01051090-I1Open ↗
08/30/2026B01051090-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/30/2026B01051090-I1Open ↗
08/30/2026B01051090-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/25/2026B01051090-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/25/2026B01051090-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026B01051090-I1Open ↗