← Back
Three families
1059 EAST 228 STREET
BRONX · Williamsbridge-Olinville · BIN 2065099
💬 Discuss this project
1960Year Built
2Stories
C0Building Class
R4Zoning
2,550 sfGross Floor Area
3Units
15 Open Violations ▸
Three families · 2,681 sf lot · 0.95 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Roof4p · 1 filing · 8 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/28/2016$530K—— → —$208/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC107/08/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SURF CLEAN ENERGY203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SURF CLEAN ENERGY INCGeneral Contractor303/21/2026
AMPACITY ELECTRICAL INCElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854107/08/2024
Building Lifecycle
All (28)Filed (1)Permit Issued (1)Violation (15)Objection (6)Special Inspection (5)
07/24/2026
Violation issued (HPD, open)
B
07/24/2026
Violation issued (HPD, open)
C
07/24/2026
Violation issued (HPD, open)
B
07/24/2026
Violation issued (HPD, open)
B
07/24/2026
Violation issued (HPD, open)
B
07/24/2026
Violation issued (HPD, open)
C
06/25/2026
Violation issued (HPD, open)
C
06/25/2026
Violation issued (HPD, open)
B
06/25/2026
Violation issued (HPD, open)
C
06/25/2026
Violation issued (HPD, open)
B
06/12/2026
Violation issued (HPD, open)
C
06/12/2026
Violation issued (HPD, open)
C
06/12/2026
Violation issued (HPD, open)
C
06/12/2026
Violation issued (HPD, open)
B
06/12/2026
Violation issued (HPD, open)
B
08/27/2024
Permit issued — Solar
X01077468-I1-SL
08/19/2024
Objection resolved — Addressed
07/25/2024
Objection resolved — Addressed
07/25/2024
Objection resolved — Addressed
07/23/2024
Objection raised — Other
07/12/2024
Objection raised — Zoning
07/12/2024
Objection raised — Structural
07/08/2024
Filed — Alteration
INSTALLATION OF SOLAR PANELS ON ROOF. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X01077468-I1
07/08/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
07/08/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
07/08/2024
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
07/08/2024
Special inspection requirement — Final
TOM PETERSEN
07/08/2024
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedSURF CLEAN ENERGY INC08/27/2024
1 project · most recent 10/06/2024
FiledStatusContractorScope
10/06/2024CompleteAMPACITY ELECTRICAL INC—
1 project · most recent 07/08/2024
FiledStatusContractorScope
07/08/2024Permit IssuedSURF CLEAN ENERGY INC14 panels, 5.67 kw, 843.03 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
07/08/2024Fire-Resistant Penetrations and JointsTOM PETERSENspecial
07/08/2024Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
07/08/2024Energy Code Compliance InspectionsTOM PETERSENprogress
07/08/2024FinalTOM PETERSENprogress
07/08/2024Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/21/2026X01077468-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
09/02/2026X01077468-I1Open ↗
09/02/2026X01077468-I1Open ↗
09/02/2026X01077468-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/02/2026X01077468-I1Open ↗
09/02/2026X01077468-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/21/2026X01077468-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/21/2026X01077468-I1Open ↗