1992Year Built
1Stories
I5Building Class
R5Zoning
2,500 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Health center, child center, clinic · Owner of record: PICASSO REALTY, CORP. · 2,500 sf lot · 1 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalMechanicalPlumbing
Permit Issued — active, not yet Signed-off
Floor 1Under Construction15p · 3 filings · 20 docs
Cellar1p · 1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
PICASSO REALTY1003/22/2026
PICASSO REALTY CORP,RENAI103/22/2026
CAPRI REALTY103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
FRANK PETRUSORA AOL COM203/21/2026
ARC-HI-TECT ASSOCIATE203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ZH RESTORATION INCGeneral Contractor303/21/2026
XH&RC PLBG AND HTG INCPlumbing307/08/2026
KALE CONSTRUCTION INCGeneral Contractor204/09/2026
CLEAN AIR GROUP INCGeneral Contractor103/22/2026
PAUL COMMDORE & SONS LTDPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CHANDA ENG. CONSULTANT PC6842501/06/2026
ARC-HI-TECH ASSOCIATES IN6963107/03/2024
FRANK PETRUSO ARCHITECT,P993101/09/2020
Building Lifecycle
All (67)Filed (9)Permit Issued (5)Signed Off (2)Violation (13)Inspection (3)Objection (13)Special Inspection (22)
06/10/2026
Signed off — Alteration CO
Existing mechanical system (BIS Job#321461752) ductwork diffuser relocates as per new floor plan. Reuse existing roof mounted HVAC unit.
B01194283-S1
04/02/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
03/30/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
03/27/2026
Permit issued — Mechanical Systems
B01194283-S1-MS
02/03/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/08/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
KARTIK CHANDA
01/06/2026
Filed — Alteration
APPLICATION FILE TO RENOVATE EXISTING COMMERCIAL SPACE ON FIRST FLOOR. INSTALL NEW PLUMBING FIXTURES, TOILET, HAND WASH SINK, FLOOR DRAIN, AREA DRAIN AS PER PLAN.
B01294116-P2
01/06/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
KARTIK CHANDA
12/17/2025
Permit issued — Plumbing
B01294116-I1-PL
11/17/2025
Special inspection requirement — Maintenance information
KARTIK CHANDA
11/17/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
KARTIK CHANDA
11/17/2025
Special inspection requirement — Energy Code Compliance Inspections
KARTIK CHANDA
11/17/2025
Special inspection requirement — Fire-Resistance Rated Construction
KARTIK CHANDA
11/17/2025
Special inspection requirement — Lighting controls
KARTIK CHANDA
11/17/2025
Special inspection requirement — Interior lighting power
KARTIK CHANDA
11/07/2025
Filed — Alteration CO
Existing mechanical system (BIS Job#321461752) ductwork diffuser relocates as per new floor plan. Reuse existing roof mounted HVAC unit.
B01194283-S1
11/07/2025
Filed — Alteration
APPLICATION FILE TO RENOVATE EXISTING COMMERCIAL SPACE ON FIRST FLOOR. INSTALL NEW PLUMBING FIXTURES, TOILET, HAND WASH SINK, FLOOR DRAIN, AREA DRAIN AS PER PLAN.
B01294116-P1
11/07/2025
Objection resolved — Addressed
11/07/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
KARTIK CHANDA
11/07/2025
Special inspection requirement — HVAC-R and service water heating system controls
KARTIK CHANDA
11/07/2025
Special inspection requirement — Maintenance information
KARTIK CHANDA
11/07/2025
Special inspection requirement — HVAC-R and service water heating equipment
KARTIK CHANDA
11/07/2025
Special inspection requirement — Permanent certificate
KARTIK CHANDA
11/04/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
10/23/2025
Special inspection requirement — Final
KARTIK CHANDA
10/23/2025
Special inspection requirement — Mechanical Systems
KARTIK CHANDA
10/02/2025
Objection raised — Scope
09/27/2025
Filed — Alteration
APPLICATION FILE TO RENOVATE EXISTING COMMERCIAL SPACE ON FIRST FLOOR. INSTALL NEW PLUMBING FIXTURES, TOILET, HAND WASH SINK, FLOOR DRAIN, AREA DRAIN AS PER PLAN.
B01294116-I1
09/21/2025
Filed — Alteration CO
Existing mechanical system (BIS Job#321461752) ductwork diffuser relocates as per new floor plan. Reuse existing roof mounted HVAC unit.
B01194283-P1
09/15/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
KARTIK CHANDA
09/15/2025
Special inspection requirement — Fire-Resistance Rated Construction
KARTIK CHANDA
09/15/2025
Special inspection requirement — Lighting controls
KARTIK CHANDA
09/15/2025
Special inspection requirement — Maintenance information
KARTIK CHANDA
09/15/2025
Special inspection requirement — Interior lighting power
KARTIK CHANDA
09/15/2025
Special inspection requirement — Energy Code Compliance Inspections
KARTIK CHANDA
09/12/2025
Permit issued — General Construction
B01194283-I1-GC
07/14/2025
Objection resolved — Addressed
05/30/2025
Objection raised — Energy
05/29/2025
Objection resolved — Addressed
04/25/2025
Objection resolved — Addressed
04/25/2025
Objection resolved — Addressed
04/21/2025
Objection raised — Structural
04/21/2025
Objection raised — Scope
04/21/2025
Objection raised — Scope
04/09/2025
Objection resolved — Addressed
03/25/2025
Objection raised — Cost
03/13/2025
Filed — Alteration CO
Existing mechanical system (BIS Job#321461752) ductwork diffuser relocates as per new floor plan. Reuse existing roof mounted HVAC unit.
B01194283-I1
08/20/2024
Permit issued — General Construction
B01096217-I1-GC
08/15/2024
Filed — Alteration
1st floor commercial space interior partition wall and ceiling, floor tiles removal. no change in use, egress and occupancy
B01096217-I1
07/10/2024
Objection raised — Scope
07/03/2024
Filed — Alteration CO
B01061842-I1
08/27/2020
Signed off — Alteration
B00289421-I1
08/11/2020
Permit issued — Plumbing
B00289421-I1-PL
01/09/2020
Filed — Alteration
B00289421-I1
08/16/2019
Violation issued (ECB, closed)
Construction
07/05/2019
Violation issued (ECB, closed)
Construction
05/03/2019
Violation issued (ECB, closed)
Construction
02/20/2019
Violation issued (ECB, closed)
Construction
12/19/2018
Violation issued (ECB, closed)
Construction
11/15/2018
Violation issued (ECB, closed)
Construction
Latest 60 of 67 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offKALE CONSTRUCTION INC03/27/2026
DOB NOWPlumbingPermit IssuedXH&RC PLBG AND HTG INC12/17/2025
DOB NOWGeneral ConstructionPermit IssuedKALE CONSTRUCTION INC09/12/2025
DOB NOWGeneral ConstructionPermit IssuedZH RESTORATION INC08/20/2024
DOB NOWPlumbingSigned-offPAUL COMMDORE & SONS LTD08/11/2020
BISPLISSUEDZARA PLUMBING CORP10/21/2016
BISMHISSUEDEAGLE BUILDING DESIGN COR10/14/2016
BISOTISSUEDUMANA DESIGNS INC07/15/2016
BISOTISSUEDUMANA DESIGNS INC03/10/2016
BISEQISSUEDMARTE DEVELOPMENT LLC11/28/2012
BISOTISSUEDMARTE DEVELOPMENT LLC11/28/2012
BISOTISSUEDS & L CONSTRUCTION08/26/1996
BISPLISSUEDBRANCH PLUMBING LLC08/05/1992
BIS—ISSUEDINTERIOR CONSTRUCTION CORP.06/26/1992
1 project · most recent 11/07/2025
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
11/07/2025Signed-offKALE CONSTRUCTION INCHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
York ZS12N24ATAAA5A 144 BTU · Rooftop Unit ×1
Ventilation
York ZS12N24ATAAA5A 12 tons · Rooftop Unit ×1
1 project · most recent 01/06/2026
Gas Water/Sanitary
FiledStatusContractorScope
01/06/2026Permit IssuedXH&RC PLBG AND HTG INCGas, Water/Sanitary
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
04/02/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/30/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/03/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 22
DateRequirementInspectorRole
01/08/2026Fire-Resistant Penetrations and JointsKARTIK CHANDAspecial
01/06/2026Fire-Resistant Penetrations and JointsKARTIK CHANDAspecial
11/17/2025Maintenance informationKARTIK CHANDAenergy_progress
11/17/2025Fire-Resistant Penetrations and JointsKARTIK CHANDAspecial
11/17/2025Energy Code Compliance InspectionsKARTIK CHANDAprogress
11/17/2025Fire-Resistance Rated ConstructionKARTIK CHANDAprogress
11/17/2025Lighting controlsKARTIK CHANDAenergy_progress
11/17/2025Interior lighting powerKARTIK CHANDAenergy_progress
11/07/2025HVAC-R and service water piping design and insulationKARTIK CHANDAenergy_progress
11/07/2025HVAC-R and service water heating system controlsKARTIK CHANDAenergy_progress
11/07/2025Maintenance informationKARTIK CHANDAenergy_progress
11/07/2025HVAC-R and service water heating equipmentKARTIK CHANDAenergy_progress
11/07/2025Permanent certificateKARTIK CHANDAenergy_progress
11/04/2025Fire-Resistant Penetrations and Joints—special
10/23/2025FinalKARTIK CHANDAprogress
10/23/2025Mechanical SystemsKARTIK CHANDAspecial
09/15/2025Fire-Resistant Penetrations and JointsKARTIK CHANDAspecial
09/15/2025Fire-Resistance Rated ConstructionKARTIK CHANDAprogress
09/15/2025Lighting controlsKARTIK CHANDAenergy_progress
09/15/2025Maintenance informationKARTIK CHANDAenergy_progress
09/15/2025Interior lighting powerKARTIK CHANDAenergy_progress
09/15/2025Energy Code Compliance InspectionsKARTIK CHANDAprogress
▾Documents — 122 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch8
08/24/2026B01061842-I1Request digital key ↗
08/24/2026B01096217-I1Request digital key ↗
08/22/2026B01194283-S1Request digital key ↗
Showing 3 of 8 on file for this type
▸DOB NOWPlans/Sketch - Plumbing Legalization1
09/02/2026B00289421-I1Request digital key ↗
▸Applications & Permits16
▸BISPLAN / WORK APPROVAL APPLICATION9
09/28/2021321459989Open ↗
09/27/2021321459989Open ↗
05/14/2021321439494Open ↗
Showing 3 of 9 on file for this type
▸BISWORK PERMIT APPLICATION5
12/12/2019321996845Open ↗
10/18/2016321461752Open ↗
07/18/2016320582776Open ↗
Showing 3 of 5 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION2
09/12/2017321439494Open ↗
09/12/2017321439494Open ↗
▸Zoning, Tax Lot & Property Records3
▸DOB NOWRestrictive Declaration/Easement 13
08/13/2026B01194283-I1Open ↗
08/13/2026B01194283-P1Open ↗
08/13/2026B01194283-S1Open ↗
▸Seals & Professional Certifications41
▸DOB NOWProgress Inspector Seal & Signature16
09/23/2026B01194283-S1Open ↗
09/23/2026B01194283-S1Open ↗
09/23/2026B01194283-S1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/22/2026B01194283-I1Open ↗
08/22/2026B01194283-S1Open ↗
08/22/2026B01194283-P1Open ↗
Showing 3 of 9 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION7
12/12/2019321996845Open ↗
09/27/2019321996845Open ↗
10/07/2016321461752Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/23/2026B01194283-S1Open ↗
08/26/2026B01194283-I1Open ↗
08/26/2026B01294116-I1Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
10/07/2016321461752Open ↗
10/05/2016321459989Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
10/07/2016321461752Open ↗
10/05/2016321459989Open ↗
▸Trade Schedules & Equipment4
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
10/07/2016321461752Open ↗
10/05/2016321459989Open ↗
08/25/2016321439494Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT1
09/30/2021321461752Open ↗
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist2
08/13/2026B01194283-P1Open ↗
08/13/2026B01194283-I1Open ↗
▸BISSTREET TREE CHECKLIST1
09/12/2012320582776Open ↗
▸Environmental & Asbestos11
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/22/2026B01194283-P1Open ↗
08/22/2026B01194283-S1Open ↗
08/22/2026B01194283-I1Open ↗
Showing 3 of 8 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
09/27/2019321996845Open ↗
10/07/2016321461752Open ↗
10/05/2016321459989Open ↗
▸Energy Compliance9
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS5
12/12/2019321996845Open ↗
10/07/2016321461752Open ↗
10/05/2016321459989Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
09/21/2021321461752Open ↗
09/21/2021321461752Open ↗
—321996845Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
09/21/2021321461752Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY5
09/30/2021321461752Open ↗
09/30/2021321461752Open ↗
09/21/2021321461752Open ↗
Showing 3 of 5 on file for this type
▸Approvals, Objections & Sign-offs5
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
10/15/2021321461752Open ↗
10/14/2020321996845Open ↗
▸BISSUPERSEDING LETTER1
03/14/2016320582776Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE1
08/25/2016321439494Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
10/14/2020321996845Open ↗
▸Cost, Insurance & Ownership7
▸BISCOST AFFIDAVIT6
09/24/2021321461752Open ↗
09/27/2019321996845Open ↗
10/07/2016321461752Open ↗
Showing 3 of 6 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
—321996845Open ↗
▸Filing & Intake Forms5
▸BISEFILING COVER SHEET5
09/27/2019321996845Open ↗
10/06/2016321461752Open ↗
10/05/2016321459989Open ↗
Showing 3 of 5 on file for this type
▸Other Documents4
▸DOB NOWProperty Ownership Certification2
08/22/2026B01194283-P1Open ↗
08/22/2026B01194283-I1Open ↗
▸BISPLOT DIAGRAM1
08/25/2016321439494Open ↗
▸DOB NOWFinal Survey1
08/13/2026B01061842-I1Open ↗