← Back
Two stories - detached, small or mid-size
1066 74 STREET
BROOKLYN · BIN 3148524
💬 Discuss this project
1920Year Built
2Stories
A1Building Class
R5BZoning
1,456 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 2,800 sf lot · 0.52 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Floor 13p · 1 filing · 15 docs
Basement1p · 1 filing · 15 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/15/2014$795K—Private party → Private party$546/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
OAMS ARCHITECTURAL DESIGN P.L.L.C.401/25/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
L L CONSULTING SERVICES403/21/2026
MARTINEZ SUAREZ CONSULTANTS403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ALI CONSTRUCTION 1 CORPGeneral Contractor203/21/2026
BLUEWATER PLBG& HTG INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SOCOTEC ENGINEERING4983104/06/2023
Building Lifecycle
All (42)Filed (4)Permit Issued (2)Signed Off (2)Inspection (3)Objection (22)Special Inspection (9)
01/06/2025
Signed off — Alteration
Alteration filed at first floor to renovate the existing kitchen. Minor alteration at the basement to add footing and posts. Plumbing work filed under DOB Now#: B00841217-S1. No change in use, occupancy, egress, or bulk
B00841217-S1
12/02/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/18/2024
Signed off — Alteration
Alteration filed at first floor to renovate the existing kitchen. Minor alteration at the basement to add footing and posts. Plumbing work filed under DOB Now#: B00841217-S1. No change in use, occupancy, egress, or bulk
B00841217-I1
03/19/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
03/19/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/28/2024
Permit issued — Plumbing
B00841217-S1-PL
02/10/2024
Objection resolved — Addressed
02/01/2024
Objection raised — Scope
01/25/2024
Filed — Alteration
Alteration filed at first floor to renovate the existing kitchen. Minor alteration at the basement to add footing and posts. Plumbing work filed under DOB Now#: B00841217-S1. No change in use, occupancy, egress, or bulk
B00841217-P2
01/19/2024
Permit issued — General Construction
B00841217-I1-GC-CX
04/28/2023
Special inspection requirement — Mechanical Systems
ALEXIS SCHLESSINGERMAN
04/28/2023
Special inspection requirement — Concrete - Cast-In-Place
ALEXIS SCHLESSINGERMAN
04/28/2023
Special inspection requirement — Subgrade Inspections
ALEXIS SCHLESSINGERMAN
04/28/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEXIS SCHLESSINGERMAN
04/28/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
ALEXIS SCHLESSINGERMAN
04/28/2023
Special inspection requirement — Footing and Foundation
ALEXIS SCHLESSINGERMAN
04/28/2023
Special inspection requirement — Final
ALEXIS SCHLESSINGERMAN
04/28/2023
Special inspection requirement — Energy Code Compliance Inspections
ALEXIS SCHLESSINGERMAN
04/28/2023
Special inspection requirement — Ventilation and air distribution system
ALEXIS SCHLESSINGERMAN
04/26/2023
Objection resolved — Addressed
04/19/2023
Objection raised — Scope
04/18/2023
Filed — Alteration
Alteration filed at first floor to renovate the existing kitchen. Minor alteration at the basement to add footing and posts. Plumbing work filed under DOB Now#: B00841217-S1. No change in use, occupancy, egress, or bulk
B00841217-P1
04/13/2023
Objection resolved — Addressed
04/11/2023
Filed — Alteration
Alteration filed at first floor to renovate the existing kitchen. Minor alteration at the basement to add footing and posts. Plumbing work filed under DOB Now#: B00841217-S1. No change in use, occupancy, egress, or bulk
B00841217-S1
04/11/2023
Objection resolved — Addressed
04/11/2023
Objection resolved — Addressed
04/11/2023
Objection resolved — Addressed
04/10/2023
Objection raised — Other
04/10/2023
Objection raised — Admin
04/10/2023
Objection raised — Scope
04/10/2023
Objection resolved — Addressed
04/10/2023
Objection raised — Scope
04/10/2023
Objection resolved — Addressed
04/10/2023
Objection raised — Scope
04/10/2023
Objection resolved — Addressed
04/10/2023
Objection raised — Structural
04/10/2023
Objection resolved — Addressed
04/10/2023
Objection raised — Admin
04/10/2023
Objection raised — Inspections
04/10/2023
Objection resolved — Addressed
04/10/2023
Objection raised — Other
04/06/2023
Filed — Alteration
Alteration filed at first floor to renovate the existing kitchen. Minor alteration at the basement to add footing and posts. Plumbing work filed under DOB Now#: B00841217-S1. No change in use, occupancy, egress, or bulk
B00841217-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offBLUEWATER PLBG& HTG INC02/28/2024
DOB NOWGeneral ConstructionSigned-offALI CONSTRUCTION 101/19/2024
Nothing on file for this building.
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
12/02/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/19/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
03/19/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 9
DateRequirementInspectorRole
04/28/2023Mechanical SystemsALEXIS SCHLESSINGERMANspecial
04/28/2023Concrete - Cast-In-PlaceALEXIS SCHLESSINGERMANspecial
04/28/2023Subgrade InspectionsALEXIS SCHLESSINGERMANspecial
04/28/2023Fire-Resistant Penetrations and JointsALEXIS SCHLESSINGERMANspecial
04/28/2023Structural Stability – Alterations of existing buildingsALEXIS SCHLESSINGERMANspecial
04/28/2023Footing and FoundationALEXIS SCHLESSINGERMANprogress
04/28/2023FinalALEXIS SCHLESSINGERMANprogress
04/28/2023Energy Code Compliance InspectionsALEXIS SCHLESSINGERMANprogress
04/28/2023Ventilation and air distribution systemALEXIS SCHLESSINGERMANenergy_progress
▾Documents — 15 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/27/2026B00841217-S1Request digital key ↗
08/15/2026B00841217-P2Request digital key ↗
08/15/2026B00841217-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications7
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/27/2026B00841217-I1Open ↗
08/27/2026B00841217-P2Open ↗
08/27/2026B00841217-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
08/24/2026B00841217-I1Open ↗
08/24/2026B00841217-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/24/2026B00841217-I1Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/27/2026B00841217-S1Open ↗
08/15/2026B00841217-P2Open ↗
08/15/2026B00841217-P1Open ↗
Showing 3 of 4 on file for this type