← Back
Two family converted from one family
107-09 220 STREET
QUEENS · Queens Village · BIN 4241116
💬 Discuss this project
1925Year Built
2Stories
B3Building Class
R3-2Zoning
2,374 sfGross Floor Area
2Units
Rent Stabilized0 Open ViolationsFDNY Report ↗
Two family converted from one family · 4,000 sf lot · 0.59 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbingCivilGeneral
Roof1p · 1 filing · 18 docs
Attic4p · 1 filing · 20 docs
Floor 212p · 2 filings · 20 docs
Floor 112p · 3 filings · 20 docs
Cellar11p · 2 filings · 20 docs
Site & exterior5p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
TOB 6193108/29/2026
YLD CHAI LLC103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/25/2025$1.4M—TOB 619 LLC → Private party$580/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SION CONSULTING ENGINEERING PC1205/13/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SION CONSULTING ENGINEERING2003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
J&J DESIGNS INCGeneral Contractor603/21/2026
POWER SURGE ELECTRIC, INCElectrical103/22/2026
ARKENSTONE BUILDERS INCGeneral Contractor107/08/2026
INFINITI ESC PLUMBING CORPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA BUILDING & INSPECTION15191005/13/2026
Building Lifecycle
All (115)Filed (12)Permit Issued (4)Signed Off (4)Violation (19)Inspection (10)Objection (36)Special Inspection (30)
05/27/2026
Signed off — ALT-CO - New Building with Existing Elements to Remain
EXISTING ONE FAMILY PROPOSED A TWO-FAMILY HOUSE, HORIZONTAL EXTENSION, AND INTERIOR RENOVATION. APPLYING FOR A NEW CERTIFICATE OF OCCUPANCY DUE TO THE CHANGE OF METES AND BOUNDS.
Q00608886-I1
05/18/2026
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
05/18/2026
Special inspection requirement — Subgrade Inspections
Younes Abouyaala
05/18/2026
Special inspection requirement — Insulation placement and R values
Younes Abouyaala
05/18/2026
Special inspection requirement — Structural Wood Frame
Younes Abouyaala
05/18/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
Younes Abouyaala
05/18/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Younes Abouyaala
05/18/2026
Special inspection requirement — Protection of exposed foundation insulation
Younes Abouyaala
05/18/2026
Special inspection requirement — Interior lighting power
Younes Abouyaala
05/18/2026
Special inspection requirement — Fenestration air leakage
Younes Abouyaala
05/18/2026
Special inspection requirement — Fenestration areas
Younes Abouyaala
05/18/2026
Special inspection requirement — Final
NAVEEN KUMAR
05/18/2026
Special inspection requirement — Footing and Foundation
Younes Abouyaala
05/18/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
Rajasekhar Sakhamuri
05/18/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
05/18/2026
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
05/18/2026
Special inspection requirement — Maintenance information
Younes Abouyaala
05/18/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Younes Abouyaala
05/18/2026
Special inspection requirement — Air barrier - visual inspection
Younes Abouyaala
05/18/2026
Special inspection requirement — Permanent certificate
Younes Abouyaala
05/18/2026
Special inspection requirement — Concrete - Cast-In-Place
Younes Abouyaala
05/13/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
EXISTING ONE FAMILY PROPOSED A TWO-FAMILY HOUSE, HORIZONTAL EXTENSION, AND INTERIOR RENOVATION. APPLYING FOR A NEW CERTIFICATE OF OCCUPANCY DUE TO THE CHANGE OF METES AND BOUNDS.
Q00608886-P5
05/01/2026
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
05/01/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
Rajasekhar Sakhamuri
05/01/2026
Special inspection requirement — Final
NAVEEN KUMAR
05/01/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Younes Abouyaala
05/01/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
05/01/2026
Special inspection requirement — Subgrade Inspections
Younes Abouyaala
05/01/2026
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
05/01/2026
Special inspection requirement — Concrete - Cast-In-Place
Younes Abouyaala
05/01/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
Younes Abouyaala
05/01/2026
Special inspection requirement — Footing and Foundation
Younes Abouyaala
03/30/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
EXISTING ONE FAMILY PROPOSED A TWO-FAMILY HOUSE, HORIZONTAL EXTENSION, AND INTERIOR RENOVATION. APPLYING FOR A NEW CERTIFICATE OF OCCUPANCY DUE TO THE CHANGE OF METES AND BOUNDS.
Q00608886-P4
11/25/2025
Violation issued (HPD, closed)
I
08/15/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
EXISTING ONE FAMILY PROPOSED A TWO-FAMILY HOUSE, HORIZONTAL EXTENSION, AND INTERIOR RENOVATION. APPLYING FOR A NEW CERTIFICATE OF OCCUPANCY DUE TO THE CHANGE OF METES AND BOUNDS.
Q00608886-P3
08/11/2025
Signed off — Alteration
THIS APPLICATION IS BEING FILED FOR A NEW PAIRED CURB CUT TO BE INSTALLED.
Q00619112-I1
06/03/2025
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
05/21/2025
Inspection — Fail-Final Curb Cut Non-Directive 14
Fail
View inspection ↗
05/16/2025
Permit issued — Curb Cut
Q00619112-I1-CC
05/09/2025
Signed off — Alteration
This plumbing applications is conjunction with Q00608886-I1
Q00619161-I1
04/30/2025
Signed off — Alteration
this application is filed for temporary construction fence
Q00619061-I1
04/02/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
EXISTING ONE FAMILY PROPOSED A TWO-FAMILY HOUSE, HORIZONTAL EXTENSION, AND INTERIOR RENOVATION. APPLYING FOR A NEW CERTIFICATE OF OCCUPANCY DUE TO THE CHANGE OF METES AND BOUNDS.
Q00608886-P2
04/01/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
03/25/2025
Filed — Alteration
This plumbing applications is conjunction with Q00608886-I1
Q00619161-P4
03/13/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
EXISTING ONE FAMILY PROPOSED A TWO-FAMILY HOUSE, HORIZONTAL EXTENSION, AND INTERIOR RENOVATION. APPLYING FOR A NEW CERTIFICATE OF OCCUPANCY DUE TO THE CHANGE OF METES AND BOUNDS.
Q00608886-P1
03/11/2025
Filed — Alteration
This plumbing applications is conjunction with Q00608886-I1
Q00619161-P3
03/03/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/28/2025
Objection resolved — Addressed
02/14/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/07/2025
Objection resolved — Addressed
02/06/2025
Objection raised — Zoning
02/06/2025
Objection raised — Scope
01/31/2025
Filed — Alteration
This plumbing applications is conjunction with Q00608886-I1
Q00619161-P2
12/05/2024
Violation issued (HPD, closed)
I
09/30/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
09/30/2024
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
09/30/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/30/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
09/25/2024
Permit issued — Plumbing
Q00619161-I1-PL
07/18/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
Latest 60 of 115 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offARKENSTONE BUILDERS INC05/16/2025
DOB NOWPlumbingSigned-offINFINITI ESC PLUMBING COR09/25/2024
DOB NOWFoundationPermit IssuedJ&J DESIGNS INC02/23/2024
DOB NOWConstruction FenceSigned-offJ&J DESIGNS INC02/08/2024
1 project · most recent 08/16/2024
General Wiring
FiledStatusContractorScope
08/16/2024CompletePOWER SURGE ELECTRIC, INCGeneral Wiring
1 project · most recent 05/13/2026
Concrete Wood
FiledStatusContractorScope
05/13/2026Permit IssuedJ&J DESIGNS INCConcrete, Wood
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
06/03/2025Pass-Final Curb Cut Non-Directive 14PassView ↗
05/21/2025Fail-Final Curb Cut Non-Directive 14FailView ↗
04/01/2025Pass-Final CND-Occupancy InspectionPassView ↗
03/03/2025Pass-Final CND-Occupancy InspectionPassView ↗
02/14/2025Pass-Final CND-Occupancy InspectionPassView ↗
09/30/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
09/30/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
09/30/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/30/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
07/18/2024Pass-Final CND-Occupancy InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 144
DateRequirementInspectorRole
05/18/2026Concrete - Cast-In-PlaceYounes Abouyaalaspecial
05/18/2026Fenestration areasYounes Abouyaalaenergy_progress
05/18/2026Fenestration air leakageYounes Abouyaalaenergy_progress
05/18/2026Permanent certificateYounes Abouyaalaenergy_progress
05/18/2026Insulation placement and R valuesYounes Abouyaalaenergy_progress
05/18/2026Interior lighting powerYounes Abouyaalaenergy_progress
05/18/2026Air barrier - visual inspectionYounes Abouyaalaenergy_progress
05/18/2026Fenestration and door U-factor and product ratingsYounes Abouyaalaenergy_progress
05/18/2026Protection of exposed foundation insulationYounes Abouyaalaenergy_progress
05/18/2026Maintenance informationYounes Abouyaalaenergy_progress
05/18/2026Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
05/18/2026Structural Wood FrameYounes Abouyaalaprogress
05/18/2026Energy Code Compliance InspectionsYounes Abouyaalaprogress
05/18/2026FinalNAVEEN KUMARprogress
05/18/2026Footing and FoundationYounes Abouyaalaprogress
05/18/2026Excavations - Sheeting, Shoring, and BracingYounes Abouyaalaspecial
05/18/2026Subsurface Investigations (Borings/Test Pits)Rajasekhar Sakhamurispecial
05/18/2026Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
05/18/2026Structural Stability – Alterations of existing buildingsYounes Abouyaalaspecial
05/18/2026Subgrade InspectionsYounes Abouyaalaspecial
05/01/2026Concrete - Cast-In-PlaceYounes Abouyaalaspecial
05/01/2026Interior lighting powerYounes Abouyaalaenergy_progress
05/01/2026Air barrier - visual inspectionYounes Abouyaalaenergy_progress
05/01/2026Fenestration air leakageYounes Abouyaalaenergy_progress
05/01/2026Insulation placement and R valuesYounes Abouyaalaenergy_progress
Latest 25 of 144.
▾Documents — 121 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch12
08/25/2026Q00619061-I1Request digital key ↗
08/25/2026Q00619112-I1Request digital key ↗
08/21/2026Q00619161-P4Request digital key ↗
Showing 3 of 12 on file for this type
▸Applications & Permits1
▸BISPLAN / WORK APPROVAL APPLICATION1
07/01/2021421789498Open ↗
▸Zoning, Tax Lot & Property Records12
▸DOB NOWZD1: DOB Zoning Diagram6
08/17/2026Q00608886-I1Open ↗
08/17/2026Q00608886-P2Open ↗
08/17/2026Q00608886-P5Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWZoning Exhibit form (1-5)4
08/17/2026Q00608886-I1Open ↗
08/17/2026Q00608886-P5Open ↗
08/17/2026Q00608886-P4Open ↗
Showing 3 of 4 on file for this type
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
08/09/2021421789498Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/17/2026Q00608886-I1Open ↗
▸Seals & Professional Certifications57
▸DOB NOWProgress Inspector Seal & Signature30
09/02/2026Q00619161-I1Open ↗
09/02/2026Q00619161-I1Open ↗
09/02/2026Q00608886-P4Open ↗
Showing 3 of 30 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature15
09/02/2026Q00619161-I1Open ↗
09/02/2026Q00608886-P4Open ↗
09/02/2026Q00608886-P4Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature12
08/21/2026Q00619161-P3Open ↗
08/21/2026Q00619161-I1Open ↗
08/21/2026Q00619161-P2Open ↗
Showing 3 of 12 on file for this type
▸Trade Schedules & Equipment6
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)6
08/17/2026Q00608886-I1Open ↗
08/17/2026Q00608886-P3Open ↗
08/17/2026Q00608886-P5Open ↗
Showing 3 of 6 on file for this type
▸Energy Compliance2
▸DOB NOWEN2: As Built Energy Analysis.2
08/17/2026Q00608886-I1Open ↗
08/13/2026Q00619161-I1Open ↗
▸Inspections & Test Reports7
▸DOB NOWSOIL REPORT6
08/17/2026Q00608886-I1Open ↗
08/17/2026Q00608886-P4Open ↗
08/17/2026Q00608886-P2Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWTR4 Test Report and Plot Diagram1
08/17/2026Q00608886-I1Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
07/01/2021421789498Open ↗
▸Other Documents23
▸DOB NOWProperty Ownership Certification6
08/17/2026Q00608886-P4Open ↗
08/17/2026Q00608886-P2Open ↗
08/17/2026Q00608886-P5Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSite Survey: Initial6
08/17/2026Q00608886-I1Open ↗
08/17/2026Q00608886-P4Open ↗
08/17/2026Q00608886-P2Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone6
08/17/2026Q00608886-P4Open ↗
08/17/2026Q00608886-P3Open ↗
08/17/2026Q00608886-I1Open ↗
Showing 3 of 6 on file for this type
▸BISPD11
03/15/2022421789498Open ↗
▸BISFINANCE DEPARTMENT DOCUMENT1
03/15/2022421789498Open ↗
▸BISDEED1
03/15/2022421789498Open ↗
▸DOB NOWFinal Survey1
08/17/2026Q00608886-I1Open ↗
▸DOB NOWPARTIAL DEMO: 10-DAY Notice1
08/17/2026Q00608886-I1Open ↗