1950Year Built
1.5Stories
A0Building Class
R2Zoning
1,080 sfGross Floor Area
1Units
Cape Cod · Owner of record: QV 2025 LLC · 3,775 sf lot · 0.29 FAR built · Flood zone X
Locations of Work
ArchitectureGeneral
Roof1p · 1 filing · 7 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/15/2025$860K—QV 2025 LLC → Private party$796/sf building
04/11/2025$461K—— → —$427/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NKM ENGINEERING PLLC103/18/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NKM ENGINEERING PLLC6244103/18/2026
Building Lifecycle
All (8)Filed (1)Objection (2)Special Inspection (5)
04/07/2026
Objection raised — Admin
04/07/2026
Objection raised — Electrical
03/18/2026
Filed — Alteration
INSTALLATION OF SOLAR PANELS ON EXISTING ROOF. NO CHANGE IN USE, OCCUPANCY, OR EGRESS. NO CHANGE IN BULK
Q01368469-I1
03/06/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
03/06/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
NARESH MAHANGU
03/06/2026
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
03/06/2026
Special inspection requirement — Final
NARESH MAHANGU
03/06/2026
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
Nothing on file for this building.
1 project · most recent 03/10/2026
FiledStatusContractorScope
03/10/2026CompleteAMBER ELECTL CONTNG INC—
1 project · most recent 03/18/2026
FiledStatusContractorScope
03/18/2026——23 panels, 9.43 kw, 1,125 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
03/06/2026Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
03/06/2026Structural Stability – Alterations of existing buildingsNARESH MAHANGUspecial
03/06/2026Energy Code Compliance InspectionsNARESH MAHANGUprogress
03/06/2026FinalNARESH MAHANGUprogress
03/06/2026Air barrier - visual inspectionNARESH MAHANGUenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/17/2026Q01368469-I1Request digital key ↗
▸Seals & Professional Certifications5
▸DOB NOWProgress Inspector Seal & Signature2
08/28/2026Q01368469-I1Open ↗
08/28/2026Q01368469-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/28/2026Q01368469-I1Open ↗
08/28/2026Q01368469-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/17/2026Q01368469-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1