← Back
Miscellaneous two family
107 ECKFORD STREET
BROOKLYN · BIN 3066790
💬 Discuss this project
1910Year Built
2Stories
B9Building Class
R6BZoning
2,223 sfGross Floor Area
2Units
3 Open Violations ▸FDNY Report ↗
Miscellaneous two family · Owner of record: 107 ECKFORD LLC · 2,000 sf lot · 1.11 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanical
Roof8p · 1 filing · 20 docs
Floor 25p · 1 filing · 20 docs
Floor 15p · 1 filing · 20 docs
Cellar6p · 1 filing · 20 docs
Basement5p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/09/2022$1.4M—— → —$639/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SHARON ENGINEERING, P.C809/23/2024
A.B.A STUDIO D.P.C.804/03/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BMB BUILDING CONSULTING1603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
OLIWA CONSTRUCTION INCGeneral Contractor707/08/2026
ATLANTIDA HVAC CORPGeneral Contractor203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
STRUCT. ENGINEERING INTEG4174609/23/2024
ABA ARCHITECTURE8907302/28/2024
Building Lifecycle
All (105)Filed (16)Permit Issued (6)Signed Off (6)Violation (3)Objection (44)Special Inspection (30)
07/15/2025
Signed off — Alteration
NEW INDOOR A/C UNITS AND CONDENSERS
B00872653-S6
07/15/2025
Signed off — Alteration
NEW INDOOR A/C UNITS AND CONDENSERS
B00872653-S3
07/11/2025
Signed off — Alteration
NEW INDOOR A/C UNITS AND CONDENSERS
B00872653-S7
07/11/2025
Signed off — Alteration
NEW INDOOR A/C UNITS AND CONDENSERS
B00872653-S4
07/03/2025
Signed off — Alteration
NEW INDOOR A/C UNITS AND CONDENSERS
B00872653-I1
07/03/2025
Signed off — Alteration
NEW INDOOR A/C UNITS AND CONDENSERS
B00872653-S2
09/27/2024
Special inspection requirement — Post-installed Anchors
Chris Yiu
09/27/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Chris Yiu
09/27/2024
Special inspection requirement — Structural Steel - Welding
Chris Yiu
09/27/2024
Special inspection requirement — Structural Steel - Details
Chris Yiu
09/27/2024
Special inspection requirement — Structural Steel - High Strength Bolting
Chris Yiu
09/27/2024
Special inspection requirement — Final
Chris Yiu
09/27/2024
Special inspection requirement — Masonry
Chris Yiu
09/27/2024
Special inspection requirement — Concrete - Cast-In-Place
Chris Yiu
09/23/2024
Filed — Alteration
NEW INDOOR A/C UNITS AND CONDENSERS
B00872653-P8
09/18/2024
Special inspection requirement — Post-installed Anchors
Chris Yiu
09/18/2024
Special inspection requirement — Structural Steel - Details
Chris Yiu
09/18/2024
Special inspection requirement — Concrete - Cast-In-Place
Chris Yiu
09/18/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Chris Yiu
09/18/2024
Special inspection requirement — Structural Steel - Welding
Chris Yiu
09/18/2024
Special inspection requirement — Final
Chris Yiu
09/18/2024
Special inspection requirement — Structural Steel - High Strength Bolting
Chris Yiu
09/18/2024
Special inspection requirement — Masonry
Chris Yiu
05/14/2024
Permit issued — Support of Excavation
B00872653-S4-SE
05/08/2024
Permit issued — Foundation
B00872653-S6-FO
05/02/2024
Permit issued — Structural
B00872653-S3-ST
04/24/2024
Permit issued — General Construction
B00872653-I1-GC
04/23/2024
Permit issued — Construction Fence
B00872653-S7-FN
04/16/2024
Objection resolved — Addressed
04/16/2024
Objection resolved — Addressed
04/15/2024
Objection raised — Structural
04/15/2024
Objection raised — Structural
04/09/2024
Permit issued — Mechanical Systems
B00872653-S2-MS
04/03/2024
Filed — Alteration
NEW INDOOR A/C UNITS AND CONDENSERS
B00872653-S7
03/20/2024
Special inspection requirement — Fire-Resistance Rated Construction
ASA BARAK
03/20/2024
Special inspection requirement — Energy Code Compliance Inspections
ASA BARAK
03/20/2024
Special inspection requirement — Air barrier - visual inspection
ASA BARAK
03/20/2024
Special inspection requirement — Final
ASA BARAK
03/20/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
ASA BARAK
03/20/2024
Special inspection requirement — Insulation placement and R values
ASA BARAK
03/20/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
ASA BARAK
03/13/2024
Objection resolved — Addressed
03/13/2024
Special inspection requirement — Final
Chris Yiu
03/13/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Chris Yiu
03/13/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
ASA BARAK
03/13/2024
Special inspection requirement — HVAC-R and service water heating equipment
Chris Yiu
03/13/2024
Special inspection requirement — Mechanical Systems
Chris Yiu
03/13/2024
Special inspection requirement — Energy Code Compliance Inspections
ASA BARAK
03/13/2024
Special inspection requirement — HVAC-R and service water heating system controls
Chris Yiu
03/07/2024
Filed — Alteration
NEW INDOOR A/C UNITS AND CONDENSERS
B00872653-P7
03/04/2024
Objection raised — Zoning
02/28/2024
Filed — Alteration
NEW INDOOR A/C UNITS AND CONDENSERS
B00872653-P6
01/29/2024
Filed — Alteration
NEW INDOOR A/C UNITS AND CONDENSERS
B00872653-P5
12/29/2023
Objection raised — Structural
12/29/2023
Objection resolved — Addressed
12/28/2023
Filed — Alteration
NEW INDOOR A/C UNITS AND CONDENSERS
B00872653-P3
12/28/2023
Filed — Alteration
NEW INDOOR A/C UNITS AND CONDENSERS
B00872653-P2
12/28/2023
Filed — Alteration
NEW INDOOR A/C UNITS AND CONDENSERS
B00872653-P4
11/14/2023
Objection resolved — Addressed
11/14/2023
Objection resolved — Addressed
Latest 60 of 105 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupport of ExcavationSigned-offOLIWA CONSTRUCTION INC05/14/2024
DOB NOWFoundationSigned-offOLIWA CONSTRUCTION INC05/08/2024
DOB NOWStructuralSigned-offOLIWA CONSTRUCTION INC05/02/2024
DOB NOWGeneral ConstructionSigned-offOLIWA CONSTRUCTION INC04/24/2024
DOB NOWConstruction FenceSigned-offOLIWA CONSTRUCTION INC04/23/2024
DOB NOWMechanical SystemsSigned-offATLANTIDA HVAC04/09/2024
1 job · most recent 09/23/2024
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
09/23/2024Signed-offOLIWA CONSTRUCTION INCHeating and Air Conditioning Systems
Heat / Cool
Mitsubishi Electric MSZ-FH09NA 9,000 BTU · Ahu ×27
MXZ-3C30NAHZ2-U1 27,400 BTU · Condensing Unit ×9
1 job · most recent 09/23/2024
Water/Sanitary
FiledStatusContractorScope
09/23/2024——Water/Sanitary
2 jobs · most recent 07/25/2024
General Wiring
FiledStatusContractorScope
07/25/2024Permit IssuedRONEY ELECTRIC INCGeneral Wiring
06/09/2024Permit IssuedPOWER SURGE ELECTRIC, INCGeneral Wiring
1 job · most recent 09/23/2024
Steel Concrete Masonry
FiledStatusContractorScope
09/23/2024Signed-offOLIWA CONSTRUCTION INCSteel, Concrete, Masonry
1 job · most recent 09/23/2024
Fence
FiledStatusContractorScope
09/23/2024Signed-offOLIWA CONSTRUCTION INCFence
1 job · most recent 09/23/2024
Construction Fence Earthwork Support of Excavation
FiledStatusContractorScope
09/23/2024Signed-offOLIWA CONSTRUCTION INCConstruction Fence, Earthwork, Support of Excavation
▾Special Inspection Requirements (DOB NOW) — 92
DateRequirementInspectorRole
09/27/2024FinalChris Yiuprogress
09/27/2024Structural Steel - DetailsChris Yiuspecial
09/27/2024Post-installed AnchorsChris Yiuspecial
09/27/2024Structural Steel - WeldingChris Yiuspecial
09/27/2024Structural Steel - High Strength BoltingChris Yiuspecial
09/27/2024MasonryChris Yiuspecial
09/27/2024Concrete - Cast-In-PlaceChris Yiuspecial
09/27/2024Structural Stability – Alterations of existing buildingsChris Yiuspecial
09/18/2024MasonryChris Yiuspecial
09/18/2024FinalChris Yiuprogress
09/18/2024Structural Steel - WeldingChris Yiuspecial
09/18/2024Structural Steel - High Strength BoltingChris Yiuspecial
09/18/2024Structural Steel - DetailsChris Yiuspecial
09/18/2024Structural Stability – Alterations of existing buildingsChris Yiuspecial
09/18/2024Post-installed AnchorsChris Yiuspecial
09/18/2024Concrete - Cast-In-PlaceChris Yiuspecial
03/20/2024FinalASA BARAKprogress
03/20/2024Fire-Resistant Penetrations and JointsASA BARAKspecial
03/20/2024Energy Code Compliance InspectionsASA BARAKprogress
03/20/2024Fire-Resistance Rated ConstructionASA BARAKprogress
03/20/2024Air barrier - visual inspectionASA BARAKenergy_progress
03/20/2024Insulation placement and R valuesASA BARAKenergy_progress
03/20/2024Fenestration and door U-factor and product ratingsASA BARAKenergy_progress
03/13/2024Mechanical SystemsChris Yiuspecial
03/13/2024Fire-Resistant Penetrations and JointsASA BARAKspecial
Latest 25 of 92.
▾Documents — 121 on file (BIS + DOB NOW)
▸Plans & Drawings16
▸DOB NOWPlans/Sketch16
08/26/2026B00872653-P8Request digital key ↗
08/26/2026B00872653-I1Request digital key ↗
08/26/2026B00872653-P1Request digital key ↗
Showing 3 of 16 on file for this type
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram3
08/13/2026B00872653-P6Open ↗
08/13/2026B00872653-P1Open ↗
08/13/2026B00872653-I1Open ↗
▸Seals & Professional Certifications67
▸DOB NOWSpecial Inspector Seal & Signature27
08/22/2026B00872653-P8Open ↗
08/22/2026B00872653-P6Open ↗
08/22/2026B00872653-P7Open ↗
Showing 3 of 27 on file for this type
▸DOB NOWProgress Inspector Seal & Signature24
08/22/2026B00872653-P7Open ↗
08/22/2026B00872653-P6Open ↗
08/22/2026B00872653-P6Open ↗
Showing 3 of 24 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature16
08/26/2026B00872653-I1Open ↗
08/26/2026B00872653-P1Open ↗
08/26/2026B00872653-S2Open ↗
Showing 3 of 16 on file for this type
▸Environmental & Asbestos15
▸DOB NOWDEP ACP-5: Asbestos Assessment Report15
08/26/2026B00872653-I1Open ↗
08/26/2026B00872653-P1Open ↗
08/26/2026B00872653-S2Open ↗
Showing 3 of 15 on file for this type
▸Inspections & Test Reports5
▸DOB NOWSOIL REPORT2
08/13/2026B00872653-S6Open ↗
08/13/2026B00872653-P3Open ↗
▸DOB NOWGeotechnical Report (BC 1803.6)2
08/13/2026B00872653-S5Open ↗
08/13/2026B00872653-S6Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026B00872653-S6Open ↗
▸Other Documents15
▸DOB NOWPlot Diagram8
08/26/2026B00872653-S4Open ↗
08/13/2026B00872653-P4Open ↗
08/13/2026B00872653-P3Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSite Survey: Initial3
08/13/2026B00872653-P6Open ↗
08/13/2026B00872653-P1Open ↗
08/13/2026B00872653-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/13/2026B00872653-P1Open ↗
08/13/2026B00872653-I1Open ↗
08/13/2026B00872653-P6Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026B00872653-S4Open ↗