| Owner | Filings | Most Recent |
|---|---|---|
| The Rector Church Wardens and Vestrymen of TR | 219 | 07/08/2026 |
| Trinity Church Wall Street | 195 | 10/04/2026 |
| Benson Industries | 11 | 03/21/2026 |
| Parish of Trinity Church | 8 | 03/21/2026 |
| Stephen B Jacobs Group | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Robert Derector Associates | 51 | 05/05/2026 |
| John F. Giuseffi, Architect | 13 | 05/04/2026 |
| Jaros Baum & Bolles | 7 | 04/22/2026 |
| Stephen B Jacobs Group | 5 | 04/08/2026 |
| Bitopi Consultants | 1 | 01/27/2026 |
| WSP | 4 | 01/20/2026 |
| Rigid Structural Design | 2 | 11/13/2025 |
| MG Engineering | 5 | 09/17/2025 |
| Horacio Repetto | 1 | 06/11/2025 |
| Gensler | 1 | 01/29/2025 |
| Leon Skvirsky PE | 8 | 09/04/2024 |
| Tohfaz Uddin PE | 2 | 11/17/2021 |
| Margaret Kittinger | 2 | 09/02/2021 |
| Gilsanz Murray Steficek | 2 | 06/25/2021 |
| Jose L. Pena, P.E | 12 | 10/22/2019 |
| Dooling & Company Architects | 4 | 10/26/2017 |
| Representative | Filings | Most Recent |
|---|---|---|
| Empire City Consultants | 99 | 03/21/2026 |
| Louis Striar | 40 | 03/21/2026 |
| Codegreen | 6 | 03/21/2026 |
| Outsource Consultants | 5 | 03/21/2026 |
| Stephen B Jacobs Group | 16 | 03/21/2026 |
| AE Design Solution | 8 | 03/21/2026 |
| Rigid Structural Design | 4 | 03/21/2026 |
| KD Designs | 1 | 03/21/2026 |
| Milrose Consultants | 14 | 03/21/2026 |
| A1 Expediting Service | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Ocgp | General Contractor | 65 | 07/08/2026 |
| Unity Construction Group | General Contractor | 32 | 07/08/2026 |
| PJP Installers | Scaffold | 24 | 07/08/2026 |
| Tru-Art Sign Co | Sign hanger | 20 | 07/08/2026 |
| A & M Warshaw Plumbing & Heating | Plumbing | 7 | 07/08/2026 |
| Demar Mechanical | Plumbing | 6 | 07/08/2026 |
| Demar Plumbing | Fire Protection | 5 | 07/08/2026 |
| William C. Gerakaris P&H | Plumbing | 5 | 07/08/2026 |
| A M Warshaw Services | Plumbing | 4 | 03/22/2026 |
| Metropolitan Building Services | General Contractor | 3 | 03/21/2026 |
| A&M Warshaw Services | Fire Protection | 3 | 07/08/2026 |
| Leader Electric Co | Electrical | 3 | 03/22/2026 |
| Americon Construction | General Contractor | 2 | 04/09/2026 |
| Ami and Associates | Fire Protection | 2 | 07/08/2026 |
| York Scaffold Equipment | Scaffold | 2 | 03/21/2026 |
| Allstate Sprinkler | Fire Protection | 2 | 07/08/2026 |
| Tristate Plumbing Services | Fire Protection | 2 | 07/08/2026 |
| JR Mechanical NY | specialty_contractor | 2 | 06/28/2026 |
| Accurate Mechanical | Fire Protection | 1 | 07/08/2026 |
| Egg Electric | Electrical | 1 | 03/22/2026 |
| I.P. Electric | Electrical | 1 | 03/22/2026 |
| L.E.A. Electric | Electrical | 1 | 03/22/2026 |
| Ami Associates | Plumbing | 1 | 03/22/2026 |
| Arsenal Scaffold | Scaffold | 1 | 04/09/2026 |
| Intersystem Construction | Scaffold | 1 | 04/09/2026 |
| Intersystems Installation S&S | Scaffold | 1 | 04/09/2026 |
| Agir Electrical Ltd D/B/A | Electrical | 1 | 03/22/2026 |
| Amok | Fire Protection | 1 | 07/08/2026 |
| Cma Plumbing & Heating | Fire Protection | 1 | 07/08/2026 |
| DC Building Services | Plumbing | 1 | 07/08/2026 |
| DC Building Services | Fire Protection | 1 | 07/08/2026 |
| Enobrac Plumbing | Plumbing | 1 | 07/08/2026 |
| Enobrac Plumbing | Fire Protection | 1 | 07/03/2026 |
| LCS Plumbing & Consulting | Plumbing | 1 | 07/08/2026 |
| Pace Plumbing | Fire Protection | 1 | 07/08/2026 |
| Pace Plumbing | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Atlas ATC Engineering | 8011 | 33 | 05/05/2026 |
| Consulting and Testing SE | 6152 | 1 | 04/22/2026 |
| Outsource Special Inspection | 2827 | 5 | 01/20/2026 |
| MEP Inspections | 1102 | 6 | 09/17/2025 |
| Atlantic Engineeringlabor | 1381 | 22 | 09/12/2025 |
| Sag Engineering & Consulting | 608 | 4 | 01/09/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | Unity Construction Group | 06/22/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Unity Construction Group | 06/08/2026 |
| DOB NOW | Sprinklers | Permit Issued | Ami and Associates | 05/18/2026 |
| DOB NOW | General Construction | Signed-off | JR Mechanical NY | 05/01/2026 |
| DOB NOW | Mechanical Systems | Signed-off | JR Mechanical NY | 05/01/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Arsenal Scaffold | 01/28/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Intersystem Construction | 01/27/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | Intersystems Installation S&S | 10/23/2025 |
| DOB NOW | Sprinklers | Signed-off | Cma Plumbing & Heating | 07/24/2025 |
| DOB NOW | Plumbing | Signed-off | William C. Gerakaris P&H | 07/23/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Americon Construction | 06/23/2025 |
| DOB NOW | General Construction | Signed-off | Americon Construction | 06/18/2025 |
| DOB NOW | General Construction | Signed-off | Unity Construction Group | 06/11/2025 |
| DOB NOW | General Construction | Signed-off | Unity Construction Group | 06/11/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Unity Construction Group | 06/10/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Unity Construction Group | 06/10/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Unity Construction Group | 05/14/2025 |
| DOB NOW | General Construction | Signed-off | Unity Construction Group | 05/14/2025 |
| DOB NOW | Sprinklers | Signed-off | Ami and Associates | 05/13/2025 |
| DOB NOW | Sprinklers | Signed-off | A&M Warshaw Services | 04/08/2025 |
| DOB NOW | Plumbing | Signed-off | A & M Warshaw Plumbing & Heating | 03/17/2025 |
| DOB NOW | Sprinklers | Signed-off | Accurate Mechanical | 02/24/2025 |
| DOB NOW | Plumbing | Signed-off | Attention to Detail P&H.I | 02/21/2025 |
| DOB NOW | General Construction | Signed-off | Unity Construction Group | 02/11/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Unity Construction Group | 02/03/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Unity Construction Group | 01/03/2025 |
| DOB NOW | General Construction | Signed-off | Unity Construction Group | 01/03/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Unity Construction Group | 01/03/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Unity Construction Group | 01/02/2025 |
| DOB NOW | General Construction | Signed-off | Unity Construction Group | 01/02/2025 |
| DOB NOW | General Construction | Signed-off | Unity Construction Group | 01/02/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Unity Construction Group | 01/02/2025 |
| DOB NOW | General Construction | Signed-off | Unity Construction Group | 12/11/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Unity Construction Group | 11/20/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Unity Construction Group | 11/20/2024 |
| DOB NOW | General Construction | Signed-off | Unity Construction Group | 11/20/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Unity Construction Group | 11/20/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Unity Construction Group | 11/20/2024 |
| DOB NOW | General Construction | Signed-off | Unity Construction Group | 11/20/2024 |
| DOB NOW | Plumbing | Signed-off | Demar Mechanical | 10/30/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/22/2026 | Signed-off | JR Mechanical NY | Air Conditioning Systems | Cooling Mitsubishi Electric PUY-2H24NL 24,000 BTU · Condensing Unit ×1 PUY-AK24NL 705 CFM · Fan Coil Indoor ×1 |
| 01/20/2026 | Signed-off | Americon Construction | Air Conditioning Systems, Heating and Air Conditioning Systems, Refrigeration Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/04/2026 | Permit Issued | Ami and Associates | 8 heads |
| 01/20/2026 | Signed-off | Cma Plumbing & Heating | 177 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/20/2026 | Signed-off | William C. Gerakaris P&H | Water/Sanitary |
| 05/05/2021 | Permit Issued | Demar Mechanical | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/10/2025 | Complete | Leader Electric Co | General Wiring |
| 10/18/2025 | Permit Issued | Aurora Electrical Contg | — |
| 07/31/2025 | Complete | A.S.K. Electrical | General Wiring |
| 07/09/2025 | Complete | Leader Electric Co | General Wiring |
| 03/18/2025 | Complete | Leader Electric Co | General Wiring |
| 10/04/2024 | Complete | Leader Electric Co | General Wiring |
| 08/28/2024 | Permit Issued | Phoenix Electric NY | General Wiring |
| 03/11/2024 | Complete | Leader Electric Co | General Wiring |
| 12/20/2023 | Complete | I.P. Electric | General Wiring |
| 05/04/2023 | Permit Issued | I.P. Electric | General Wiring |
| 08/03/2022 | Permit Issued | Leader Electric Co | General Wiring |
| 03/11/2022 | Complete | L.E.A. Electric | General Wiring |
| 05/10/2021 | Permit Issued | Leader Electric Co | General Wiring |
| 02/05/2021 | Complete | L.E.A. Electric | General Wiring |
| 01/19/2021 | Complete | Agir Electrical Ltd D/B/A | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/28/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/23/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/23/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/29/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/17/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/17/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/16/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/15/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/04/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/02/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/25/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/25/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/19/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/18/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/13/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/09/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/01/2025 | Certified Sprinkler (SP) - Booster Pump Test | Certified | View ↗ |
| 09/26/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/16/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/16/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/15/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/09/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/28/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/01/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/09/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/01/2026 | Post-installed Anchors | RONALD GRAPIN | special |
| 04/29/2026 | Fire-Resistant Penetrations and Joints | RONALD GRAPIN | special |
| 04/29/2026 | Sprinkler Systems | RONALD GRAPIN | special |
| 04/17/2026 | HVAC-R and service water piping design and insulation | RONALD GRAPIN | energy_progress |
| 04/17/2026 | Energy Code Compliance Inspections | RONALD GRAPIN | progress |
| 04/17/2026 | Lighting controls | RONALD GRAPIN | energy_progress |
| 04/17/2026 | Interior lighting power | RONALD GRAPIN | energy_progress |
| 04/17/2026 | Sprinkler Systems | RONALD GRAPIN | special |
| 04/17/2026 | Fire-Resistant Penetrations and Joints | RONALD GRAPIN | special |
| 04/08/2026 | Sprinkler Systems | RONALD GRAPIN | special |
| 04/07/2026 | Final | John Giuseffi | progress |
| 04/07/2026 | Mechanical Systems | RONALD GRAPIN | special |
| 04/07/2026 | Final | RONALD GRAPIN | progress |
| 04/07/2026 | Fire-Resistant Penetrations and Joints | RONALD GRAPIN | special |
| 03/06/2026 | Final | Jennifer Cheuk | progress |
| 01/07/2026 | HVAC-R and service water heating equipment | JONAR MADRIAGA | energy_progress |
| 01/07/2026 | HVAC-R and service water heating system controls | JONAR MADRIAGA | energy_progress |
| 01/07/2026 | Lighting controls | JONAR MADRIAGA | energy_progress |
| 01/07/2026 | Interior lighting power | JONAR MADRIAGA | energy_progress |
| 01/07/2026 | HVAC-R and service water piping design and insulation | JONAR MADRIAGA | energy_progress |
| 01/07/2026 | Maintenance information | JONAR MADRIAGA | energy_progress |
| 01/07/2026 | Mechanical Systems | JONAR MADRIAGA | special |
| 01/07/2026 | Energy Code Compliance Inspections | JONAR MADRIAGA | progress |
| 01/07/2026 | Final | JONAR MADRIAGA | progress |
| 01/07/2026 | Duct leakage testing, insulation and design | JONAR MADRIAGA | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Industrious | Office | Floors 13, 14 | Project M01218691 |
| Trinity Church Wall Street | Religious | Floors 15, 17, 22–24, 26 | Project M01207643 Project M01166199 Project M01166215 Project M01166261 Project M01110768 Project M01110778 Project M01110779 Project M01103264 Project M01103266 Project M01103263 Project M01103265 Project M01103267 |
| Tepper Foundation | Office | Floor 26 | Project M01166199 Project M01166215 Project M01166261 Project M01166187 |
| The Rector, Church-wardens and Vest | Religious | Floors 9, 17, 19, 21, 25 | Project M00846708 Project M00846690 Project M00846726 Project M00846736 Project M08007176 Project M00764181 Project M00763999 Project M00764268 Project M00764697 Project M00689360 Project M00689894 Project M00690216 |
| The Rector Church-ward | Religious | Floors 1–5, 9, 12 | Project M00404608 Project M00407080 Project M00236328 Project M00236354 Project M00236362 Project M00236372 Project M00236388 Project M00236396 Project M00236436 Project M00236451 Project M00236463 Project M00210516 |