← Back
Elevator apt, fireproof without stores
107 WEST 97 STREET
MANHATTAN · Upper West Side-Manhattan Valley · BIN 1089696
💬 Discuss this project
1950Year Built
16Stories
D3Building Class
R7-2Zoning
257,760 sfGross Floor Area
287Units
LL97 Covered27 Open Violations 26 unresolved · 1 paperwork only ▸FISP: UNSAFE
Elevator apt, fireproof without stores · Owner of record: CF PWV LLC · 24,477 sf lot · 10.53 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Permit Issued — active, not yet Signed-off
RoofUnder Construction1p · 1 filing · 5 docs
Floor 16Under Construction5p · 1 filing · 5 docs
Floor 15Under Construction5p · 1 filing · 5 docs
Floor 14Under Construction5p · 1 filing · 5 docs
Floor 13Under Construction5p · 1 filing · 5 docs
Floor 12Under Construction7p · 3 filings · 16 docs
Floor 11Under Construction5p · 1 filing · 5 docs
Floor 10Under Construction5p · 1 filing · 5 docs
Floor 9Under Construction5p · 1 filing · 5 docs
Floor 8Under Construction5p · 1 filing · 5 docs
Floor 7Under Construction5p · 1 filing · 5 docs
Floor 6Under Construction5p · 1 filing · 5 docs
Floor 5Under Construction5p · 1 filing · 5 docs
Floor 4Under Construction5p · 1 filing · 5 docs
Floor 3Under Construction5p · 1 filing · 5 docs
Floor 2Under Construction5p · 1 filing · 5 docs
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CF PWV LLC603/22/2026
PWV ACQUISITION OWNER LLC1803/22/2026
PWV AQUISITIONS LLC7403/22/2026
DURALIFT, INC.303/22/2026
PMV ACQUISITION OWNER LLC1103/22/2026
PWW ACQUISITON OWNER LLC103/22/2026
PWV OWNER LLC103/22/2026
FLUV ACQUISITION LLC103/22/2026
HKO GROUP303/22/2026
AKI RENOVATIONS GROUP103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ASHRAF CORP211/24/2025
RIGID STRUCTURAL DESIGN, LLC108/13/2024
HOWARD L ZIMMERMAN ARCH & ENG DPC107/18/2023
ATELIER NY ARCHITECTURE210/01/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Rigid Structural Design, LLC603/21/2026
RIGGING CONSULTANTS403/21/2026
HLZAE103/21/2026
ATELIER NEW YORK ARCHITECTURE203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
INTERSYSTEMS INSTAL S&SGeneral Contractor1507/08/2026
OPTIMUM BUILDING RESTORATIONGeneral Contractor507/08/2026
LAN RENOVATION LLCGeneral Contractor407/08/2026
I.K.E. ELECTRICAL CORP.Electrical303/22/2026
YITZHAK ADIKAElectrical203/21/2026
INTERSYSTEM CONSTRUCTIONGeneral Contractor204/09/2026
VINCENT LOMBARDOZZIElectrical103/21/2026
TROADIO MENENDEZElectrical103/21/2026
CREATIVE PLUMBING INPlumbing107/08/2026
SPIRO VALENTISElectrical103/21/2026
JOHNSON CLIVEElectrical103/21/2026
JLC ELEC'L CONTR'G INCElectrical103/22/2026
RJB CONTRACTING CARTING CORPGeneral Contractor107/08/2026
U.S. ELECTRIC CORP.Electrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HOWARD L ZIMMERMAN ARCHIT1712107/18/2023
ATELIER NY ARCHITECTURE2438110/01/2021
Building Lifecycle
All (112)Filed (8)Permit Issued (18)Facade (FISP) (18)Violation (60)Special Inspection (8)
08/12/2026
Permit issued — Sidewalk Shed
M00919167-I1-SH
08/10/2026
Violation issued (ECB, open)
Unknown
04/29/2026
Violation issued (HPD, open)
A
04/20/2026
Violation issued (ECB, open)
Local Law
04/07/2026
Violation issued (ECB, closed)
Construction
03/20/2026
Permit issued — Supported Scaffold
M01095162-I1-SF
03/19/2026
Permit issued — Sidewalk Shed
M00919167-I1-SH
02/18/2026
Violation issued (HPD, open)
B
02/02/2026
Violation issued (ECB, open)
Elevators
01/27/2026
Permit issued — Sidewalk Shed
M00919167-I1-SH
01/26/2026
Permit issued — Supported Scaffold
M01095162-I1-SF
01/21/2026
Filed — Alteration
Suspended Scaffold for Facade Restoration and Inspection as Shown on Plans
M01335682-I1
12/17/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Michael Walsh
11/24/2025
Filed — Alteration
Installation of a temporarily heavy-duty sidewalk per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00919167-P1
10/09/2025
Violation issued (ECB, closed)
Construction
08/21/2025
Permit issued — Sidewalk Shed
M00919167-I1-SH
08/20/2025
Violation issued (ECB, open)
Elevators
08/19/2025
Permit issued — Supported Scaffold
M01095162-I1-SF
06/04/2025
Violation issued (HPD, closed)
A
05/31/2025
Violation issued (HPD, open)
C
05/31/2025
Violation issued (HPD, closed)
C
05/31/2025
Violation issued (HPD, closed)
B
05/31/2025
Violation issued (HPD, closed)
B
03/12/2025
Violation issued (ECB, open)
Elevators
03/05/2025
Permit issued — General Construction
M00781572-I1-GC
12/01/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/07/2024
Permit issued — General Construction
M00781572-I1-GC
09/06/2024
Permit issued — Sidewalk Shed
M00919167-I1-SH
08/16/2024
Violation issued (ECB, closed)
Construction
08/13/2024
Filed — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01095162-I1
08/13/2024
Permit issued — Supported Scaffold
M01095162-I1-SF
08/01/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/13/2024
Violation issued (HPD, open)
B
06/13/2024
Violation issued (HPD, open)
B
06/13/2024
Violation issued (HPD, open)
B
06/11/2024
Violation issued (HPD, open)
A
06/11/2024
Violation issued (HPD, open)
B
04/05/2024
Permit issued — Suspended Scaffold
M01006288-I1-SC
02/27/2024
Violation issued (ECB, closed)
Construction
02/21/2024
Cycle 9 facade report submitted
02/21/2024
Cycle 9 facade report signed — UNSAFE
02/21/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
02/20/2024
Permit issued — General Construction
M00781572-I1-GC
02/16/2024
Filed — Alteration
M01006288-I1
01/30/2024
Cycle 9 facade inspection completed
12/07/2023
Violation issued (HPD, open)
B
12/07/2023
Violation issued (HPD, open)
B
12/07/2023
Violation issued (HPD, open)
B
12/07/2023
Violation issued (HPD, open)
B
12/07/2023
Violation issued (HPD, open)
B
12/07/2023
Violation issued (HPD, open)
B
12/07/2023
Violation issued (HPD, open)
B
11/03/2023
Permit issued — General Construction
M00781572-I1-GC
09/07/2023
Permit issued — Sidewalk Shed
M00919167-I1-SH
09/05/2023
Filed — Alteration
Installation of a temporarily heavy-duty sidewalk per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00919167-I1
07/25/2023
Violation issued (HPD, open)
A
07/25/2023
Violation issued (HPD, closed)
B
07/25/2023
Violation issued (HPD, closed)
A
07/25/2023
Violation issued (HPD, closed)
C
07/25/2023
Violation issued (HPD, closed)
B
Latest 60 of 112 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedINTERSYSTEM CONSTRUCTION08/12/2026
DOB NOWSupported ScaffoldPermit IssuedINTERSYSTEM CONSTRUCTION03/20/2026
DOB NOWSidewalk ShedPermit IssuedINTERSYSTEM CONSTRUCTION03/19/2026
DOB NOWSidewalk ShedPermit IssuedINTERSYSTEMS INSTAL S&S01/27/2026
DOB NOWSupported ScaffoldPermit IssuedINTERSYSTEMS INSTAL S&S01/26/2026
DOB NOWSidewalk ShedPermit IssuedINTERSYSTEMS INSTAL S&S08/21/2025
DOB NOWSupported ScaffoldPermit IssuedINTERSYSTEMS INSTAL S&S08/19/2025
DOB NOWGeneral ConstructionPermit IssuedOPTIMUM BUILDING RESTORAT03/05/2025
DOB NOWGeneral ConstructionPermit IssuedOPTIMUM BUILDING RESTORAT10/07/2024
DOB NOWSidewalk ShedPermit IssuedINTERSYSTEMS INSTAL S&S09/06/2024
DOB NOWSupported ScaffoldPermit IssuedINTERSYSTEMS INSTAL S&S08/13/2024
DOB NOWSuspended ScaffoldPermit IssuedSPD CONSTRUCTION CORP04/05/2024
DOB NOWGeneral ConstructionPermit IssuedOPTIMUM BUILDING RESTORAT02/20/2024
DOB NOWGeneral ConstructionPermit IssuedRJB CONTRACTING CARTING C11/03/2023
DOB NOWSidewalk ShedPermit IssuedINTERSYSTEMS INSTAL S&S09/07/2023
DOB NOWGeneral ConstructionPermit IssuedLAN RENOVATION LLC10/17/2022
DOB NOWPlumbingPermit IssuedAB PLUMBING INC06/10/2022
DOB NOWGeneral ConstructionPermit IssuedLAN RENOVATION LLC03/23/2022
BISOTISSUEDLAN RENOVATION LLC10/17/2022
BISPLISSUEDCREATIVE PLUMBING IN06/13/2022
BISOTISSUEDLAN RENOVATION LLC04/20/2022
BISOTISSUEDLAN RENOVATION LLC07/07/2021
BIS—ISSUEDLAN RENOVATION LLC10/16/2019
BISOTISSUEDLAN RENOVATION LLC05/10/2019
BISOTISSUEDLAN RENOVATION LLC05/03/2019
BISOTISSUEDHKO GROUP LLC04/24/2019
BISOTISSUEDLAN RENOVATION LLC02/15/2019
BISPLISSUEDL&J PLG & HTG CO OF NY IN02/14/2019
BISPLISSUEDPLBG P & H INC02/08/2019
BISOTISSUEDEASTERN LEAF CONSTRUCTION12/18/2018
BISOTISSUEDLAN RENOVATION LLC12/13/2018
BISOTISSUEDHKO GROUP LLC12/11/2018
BISOTISSUEDLAN RENOVATION LLC10/27/2018
BISPLISSUEDARCH PLUMBING & HTNG CORP10/15/2018
BISOTISSUEDARMTECH INDUSTRIES, CO08/31/2018
BISPLISSUEDALL PRO PLBG & HTG INC08/02/2018
BISPLISSUEDL&J PLG & HTG CO OF NY IN07/17/2018
BISPLISSUEDARCH PLUMBING & HTNG CORP07/17/2018
BISOTISSUEDARMTECH INDUSTRIES, CO07/03/2018
BISPLISSUEDHP SERVICES INC04/10/2018
+ 28 more permits on file
1 project · most recent 10/01/2021
Gas Water/Sanitary
FiledStatusContractorScope
10/01/2021Permit IssuedCREATIVE PLUMBING INGas, Water/Sanitary
25 projects · most recent 11/08/2023
General Wiring
FiledStatusContractorScope
11/08/2023Permit IssuedAUR0RA ELECL CONTG INC—
12/21/2022Permit IssuedI.K.E. ELECTRICAL CORP.General Wiring
09/17/2019Permit IssuedI.K.E. ELECTRICAL CORP.General Wiring
09/16/2019Permit IssuedI.K.E. ELECTRICAL CORP.General Wiring
09/16/2019CompleteI.K.E. ELECTRICAL CORP.General Wiring
09/11/2019Permit IssuedI.K.E. ELECTRICAL CORP.General Wiring
09/11/2019Permit IssuedI.K.E. ELECTRICAL CORP.General Wiring
09/10/2019CompleteI.K.E. ELECTRICAL CORP.General Wiring
09/02/2019Permit IssuedI.K.E. ELECTRICAL CORP.General Wiring
08/26/2019Permit IssuedI.K.E. ELECTRICAL CORP.General Wiring
08/14/2019Permit IssuedI.K.E. ELECTRICAL CORP.General Wiring
08/07/2019Permit IssuedI.K.E. ELECTRICAL CORP.General Wiring
07/23/2019Permit IssuedI.K.E. ELECTRICAL CORP.General Wiring
06/25/2019CompleteJLC ELEC'L CONTR'G INCGeneral Wiring
06/06/2019CompleteJLC ELEC'L CONTR'G INCGeneral Wiring
2 projects · most recent 11/24/2025
Sidewalk Shed Scaffold
FiledStatusContractorScope
11/24/2025Permit IssuedINTERSYSTEM CONSTRUCTIONSidewalk Shed
08/13/2024Permit IssuedINTERSYSTEM CONSTRUCTIONScaffold
1 project · most recent 01/21/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
01/21/2026——Suspended Scaffold (SC)
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
12/17/2025Alternative Materials - OTCR Buildings Bulletin NumberMichael Walshspecial
07/18/2023Tenant Protection Plan ComplianceJon Colatrellaspecial
08/02/2022FinalJon Colatrellaprogress
08/26/2021Fire-Resistant Penetrations and JointsAnatole Plotkinspecial
08/26/2021Energy Code Compliance InspectionsAnatole Plotkinprogress
08/26/2021Fire-Resistance Rated ConstructionAnatole Plotkinprogress
08/26/2021FinalAnatole Plotkinprogress
08/26/2021Lighting in dwelling unitsAnatole Plotkinenergy_progress
▾Documents — 824 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
09/03/2026M00584177-I1Request digital key ↗
09/03/2026M00584163-I1Request digital key ↗
08/29/2026M00781572-I1Request digital key ↗
Showing 3 of 8 on file for this type
▸Applications & Permits166
▸BISWORK PERMIT APPLICATION94
06/13/2022140847699Open ↗
04/20/2022140847699Open ↗
07/07/2021140923945Open ↗
Showing 3 of 94 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION71
09/02/2022140847699Open ↗
09/01/2022140847699Open ↗
07/15/2020140923945Open ↗
Showing 3 of 71 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications150
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY35
07/15/2020140923945Open ↗
05/09/2019140847699Open ↗
04/23/2019140844807Open ↗
Showing 3 of 35 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION34
05/09/2019140847699Open ↗
04/23/2019140844807Open ↗
12/17/2018140823296Open ↗
Showing 3 of 34 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT34
05/09/2019140847699Open ↗
04/23/2019140844807Open ↗
12/17/2018140823296Open ↗
Showing 3 of 34 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION32
03/12/2020140847699Open ↗
03/10/2020140847699Open ↗
07/12/2019122993760Open ↗
Showing 3 of 32 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
09/03/2026M00584177-I1Open ↗
08/29/2026M00781572-I1Open ↗
08/26/2026M01095162-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature5
08/28/2026M00584163-I1Open ↗
08/28/2026M00584163-I1Open ↗
08/28/2026M00584163-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/28/2026M00584163-I1Open ↗
08/27/2026M00781572-I1Open ↗
08/23/2026M01335682-I1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
07/15/2020140923945Open ↗
▸Trade Schedules & Equipment54
▸BISSCHEDULE B - PLUMBING33
05/09/2019140847699Open ↗
04/23/2019140844807Open ↗
12/17/2018140823296Open ↗
Showing 3 of 33 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE21
03/12/2020140847699Open ↗
03/10/2020140847699Open ↗
07/16/2019140821886Open ↗
Showing 3 of 21 on file for this type
▸Safety & Tenant Protection37
▸BISTENANT PROTECTION PLAN AND NOTES36
07/15/2020140923945Open ↗
05/09/2019140847699Open ↗
04/23/2019140844807Open ↗
Showing 3 of 36 on file for this type
▸BISSTREET TREE CHECKLIST1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos42
▸BISASBESTOS: CERTIFICATION (DEP ACP5)39
07/15/2020140923945Open ↗
03/12/2020140847699Open ↗
03/10/2020140847699Open ↗
Showing 3 of 39 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
09/03/2026M00584177-I1Open ↗
08/29/2026M00781572-I1Open ↗
08/13/2026M00584163-I1Open ↗
▸Energy Compliance107
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS34
07/15/2020140923945Open ↗
05/09/2019140847699Open ↗
04/23/2019140844807Open ↗
Showing 3 of 34 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY32
07/15/2020140923945Open ↗
05/09/2019140847699Open ↗
04/23/2019140844807Open ↗
Showing 3 of 32 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS27
07/12/2019122993760Open ↗
04/03/2019140741623Open ↗
04/03/2019140741623Open ↗
Showing 3 of 27 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS12
04/03/2019140741623Open ↗
03/20/2019140794674Open ↗
03/13/2019140705663Open ↗
Showing 3 of 12 on file for this type
▸BISTR8: Energy Code Progress Inspections1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports35
▸BISTECHNICAL REPORT: RESPONSIBILITY32
07/22/2020140923945Open ↗
07/15/2020140923945Open ↗
05/09/2019140847699Open ↗
Showing 3 of 32 on file for this type
▸BISTECHNICAL REPORT: PILE DRIVING1
03/20/2019140794674Open ↗
▸BISINSPECTION REPORT - SUPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
03/20/2019140794674Open ↗
▸Approvals, Objections & Sign-offs24
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST12
04/03/2019140741623Open ↗
03/20/2019140794674Open ↗
03/13/2019140705663Open ↗
Showing 3 of 12 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION10
04/20/2022140847699Open ↗
07/07/2021140923945Open ↗
Showing 2 of 10 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSUPERSEDING LETTER1
05/06/2019140823296Open ↗
▸Cost, Insurance & Ownership119
▸BISCOST AFFIDAVIT56
07/15/2020140923945Open ↗
03/12/2020140847699Open ↗
03/10/2020140847699Open ↗
Showing 3 of 56 on file for this type
▸BISHIC LICENSE OR AFFIDAVIT35
07/22/2020140923945Open ↗
05/09/2019140847699Open ↗
05/06/2019140823296Open ↗
Showing 3 of 35 on file for this type
▸BISCIVIL PENALTY AFFADAVIT/REQUEST28
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 28 on file for this type
▸Filing & Intake Forms74
▸BISEFILING JOB APPLICATION COVER SHEET35
07/15/2020140923945Open ↗
05/09/2019140847699Open ↗
04/23/2019140844807Open ↗
Showing 3 of 35 on file for this type
▸BISBOROUGH INTAKE FORM17
04/20/2022140847699Open ↗
03/10/2020140847699Open ↗
07/11/2019140821886Open ↗
Showing 3 of 17 on file for this type
▸BISADDITIONAL INFORMATION17
09/02/2022140847699Open ↗
03/12/2020140847699Open ↗
07/16/2019140821886Open ↗
Showing 3 of 17 on file for this type
▸BISEFILING COVER SHEET5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸Other Documents8
▸DOB NOWManufacturer's Specifications2
08/13/2026M01335682-I1Open ↗
08/13/2026M01006288-I1Open ↗
▸DOB NOWCalculations2
08/13/2026M01335682-I1Open ↗
08/13/2026M01006288-I1Open ↗
▸BISSupporting Document: Fee Exempt1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTEMPORARY FLOOD SHIELDS: EMERGENCY FLOOD PLAN1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISPLOT DIAGRAM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type