← Back
BuildNYC
Office with commercial, 1-6 stories
1070 MCDONALD AVENUE
BROOKLYN · BIN 3129320
💬 Discuss this project
1931Year Built
2Stories
O5Building Class
M1-1Zoning
11,585 sfGross Floor Area
3Units
1 Active Violation 3 likely answered ▸FDNY Report ↗
Office with commercial, 1-6 stories · 8,550 sf lot · 1.35 FAR built · Flood zone X
Locations of Work
Architecture
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Site & exteriorHatzoloh7p · 1 filing · 12 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Shahrish Shuvo Engineering201/29/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PDG Building Consultants403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Remo ConsultantsGeneral Contractor104/09/2026
Building Lifecycle
All (34)Filed (2)Permit Issued (1)Signed Off (1)Violation (22)Special Inspection (8)
01/27/2026
Signed off — Alteration
Alter the existing Facade of the building. No change in use, occupancy or egress.
B01158048-I1
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
02/04/2025
Special inspection requirement — Final
PRAMODRAY SHAH
02/04/2025
Special inspection requirement — Fenestration air leakage
PRAMODRAY SHAH
02/04/2025
Special inspection requirement — Fenestration areas
PRAMODRAY SHAH
02/04/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
PRAMODRAY SHAH
01/29/2025
Filed — Alteration
Alter the existing Facade of the building. No change in use, occupancy or egress.
B01158048-P1
01/20/2025
Special inspection requirement — Final
PRAMODRAY SHAH
01/20/2025
Special inspection requirement — Fenestration areas
PRAMODRAY SHAH
01/20/2025
Special inspection requirement — Fenestration air leakage
PRAMODRAY SHAH
01/20/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
PRAMODRAY SHAH
12/24/2024
Permit issued — General Construction
B01158048-I1-GC
12/19/2024
Filed — Alteration
Alter the existing Facade of the building. No change in use, occupancy or egress.
B01158048-I1
06/30/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/30/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/20/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/17/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/30/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
04/06/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/07/2017
Violation issued (ECB, closed)
Boilers
07/18/2016
Violation issued (DOB, closed)
V-DOB VIOLATION - ACTIVE
10/19/2015
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
10/01/2015
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/03/2015
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/31/2014
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/15/2014
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/01/2013
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/13/2011
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/31/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/01/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/26/2002
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/27/2001
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/01/1994
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/01/1993
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offRemo Consultants12/24/2024
BISBLISSUEDWNW & Sons Plumbing & Heating12/31/2018
BIS—ISSUEDBarry Halpern Chany Construction04/13/2018
BISPLISSUEDWNW & Sons Plumbing & Heating05/12/2017
BIS—ISSUEDBarry Halpern Chany Construction04/07/2017
BISPLISSUEDWNW & Sons Plumbing & Heating03/31/2017
BISSPISSUEDWNW & Sons Plumbing & Heating03/31/2017
BISBLISSUEDWNW & Sons Plumbing & Heating03/08/2017
BISPLISSUEDWNW & Sons Plumbing & Heating05/11/2016
BIS—ISSUEDBarry Halpern Chany Construction04/12/2016
BISPLISSUEDWNW & Sons Plumbing & Heating03/30/2016
BISSPISSUEDWNW & Sons Plumbing & Heating03/30/2016
BISEQISSUEDBarry Halpern Chany Construction08/24/2015
BIS—ISSUEDBarry Halpern Chany Construction08/24/2015
BISBLISSUEDWNW & Sons Plumbing & Heating07/08/2015
BISPLISSUEDWNW & Sons Plumbing & Heating03/30/2015
BISPLISSUEDWNW & Sons Plumbing & Heating03/30/2015
BISSPISSUEDWNW & Sons Plumbing & Heating03/30/2015
BISEQISSUEDBarry Halpern Chany Construction09/03/2014
BIS—ISSUEDBarry Halpern Chany Construction09/03/2014
BISPLISSUEDWNW & Sons Plumbing & Heating03/18/2014
BISSPISSUEDWNW & Sons Plumbing & Heating02/18/2014
BISPLISSUEDWNW & Sons Plumbing & Heating02/18/2014
BIS—ISSUEDBarry Halpern Chany Construction08/29/2013
BISEQISSUEDBarry Halpern Chany Construction08/29/2013
BISPLISSUEDWNW & Sons Plumbing & Heating11/13/2012
BISSPISSUEDWNW & Sons Plumbing & Heating11/13/2012
BIS—ISSUEDBarry Halpern Chany Construction08/30/2012
BISEQISSUEDBarry Halpern Chany Construction08/30/2012
BISPLISSUEDWNW & Sons Plumbing & Heating08/08/2012
BIS—ISSUEDBHC Construction & Development05/08/2012
BISEQISSUEDBHC Construction & Development05/08/2012
BISEQISSUEDBHC Construction & Development05/13/2011
BIS—ISSUEDBHC Construction & Development05/13/2011
BISOTISSUEDMybem06/15/2010
BISMHISSUEDAmerican Cool Air04/21/2008
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
02/04/2025FinalPRAMODRAY SHAHprogress
02/04/2025Fenestration air leakagePRAMODRAY SHAHenergy_progress
02/04/2025Fenestration areasPRAMODRAY SHAHenergy_progress
02/04/2025Fenestration and door U-factor and product ratingsPRAMODRAY SHAHenergy_progress
01/20/2025FinalPRAMODRAY SHAHprogress
01/20/2025Fenestration areasPRAMODRAY SHAHenergy_progress
01/20/2025Fenestration air leakagePRAMODRAY SHAHenergy_progress
01/20/2025Fenestration and door U-factor and product ratingsPRAMODRAY SHAHenergy_progress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
HatzolohMedical / Healthcare—
Project B01158048 Alteration · LOC Issued · 12/19/2024
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 173 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/23/2026B01158048-I1Request digital key ↗
08/23/2026B01158048-P1Request digital key ↗
▸Applications & Permits37
▸BISWORK PERMIT APPLICATION16
04/13/2018320233939Open ↗
04/21/2017320233939Open ↗
04/21/2016320233939Open ↗
Showing 3 of 16 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION16
01/08/2021320233939Open ↗
12/30/2020320157959Open ↗
12/21/2020320233939Open ↗
Showing 3 of 16 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION4
08/10/2020320233939Open ↗
02/25/2020320233939Open ↗
01/23/2020320233939Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
11/08/2017320233939Open ↗
▸Zoning, Tax Lot & Property Records1
▸BISADDRESS - NEW HOUSE NUMBER APPROVED1
05/03/2011320233939Open ↗
▸Seals & Professional Certifications26
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION16
02/21/2020320233939Open ↗
02/21/2020320233939Open ↗
02/05/2020321153737Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/01/2026B01158048-P1Open ↗
09/01/2026B01158048-P1Open ↗
08/23/2026B01158048-I1Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
07/06/2015321153737Open ↗
04/03/2008310111508Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/23/2026B01158048-P1Open ↗
08/23/2026B01158048-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
07/06/2015321153737Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
04/03/2008310111508Open ↗
▸Trade Schedules & Equipment26
▸BISSELF-CERT PLUMBING NOTICE8
12/11/2014320233939Open ↗
07/14/2014320297157Open ↗
06/30/2014320297157Open ↗
Showing 3 of 8 on file for this type
▸BISSCHEDULE B - PLUMBING5
12/17/2014320233939Open ↗
08/24/2012320297157Open ↗
04/19/2011320297157Open ↗
Showing 3 of 5 on file for this type
▸BISEQUIPMENT USE PERMITS5
03/13/2020320233939Open ↗
03/13/2020320233939Open ↗
03/13/2020320233939Open ↗
Showing 3 of 5 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT2
03/13/2020320233939Open ↗
04/28/2008310111508Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
12/28/2015320233939Open ↗
01/06/2015320233939Open ↗
▸BISSPRINKLER INSP REPORT : FP-851
07/14/2014320297157Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
09/07/2017320824024Open ↗
▸BISSEWER CONNECTION: DEP SD1 & SD21
05/02/2011320233939Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
07/06/2015321153737Open ↗
▸Safety & Tenant Protection3
▸BISSTREET TREE CHECKLIST3
01/24/2020320233939Open ↗
11/03/2010320233939Open ↗
05/03/2010320157959Open ↗
▸Environmental & Asbestos6
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'3
04/19/2011320297157Open ↗
11/03/2010320233939Open ↗
05/03/2010320157959Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/23/2026B01158048-P1Open ↗
08/23/2026B01158048-I1Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
04/03/2008310111508Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
02/05/2020321153737Open ↗
02/05/2020321153737Open ↗
▸BISTECHNICAL REPORT: ENERGY1
05/17/2011320233939Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
02/05/2020321153737Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
01/21/2021320233939Open ↗
▸Inspections & Test Reports7
▸BISTECHNICAL REPORT: RESPONSIBILITY5
01/13/2021320233939Open ↗
01/13/2021320233939Open ↗
12/28/2020320233939Open ↗
Showing 3 of 5 on file for this type
▸BISHYDRAULIC FLOW CALCULATIONS1
11/13/2012320297157Open ↗
▸BISHYDRO FLOW TEST LETTER1
04/19/2011320297157Open ↗
▸Approvals, Objections & Sign-offs25
▸BISADMINISTRATIVE OBJECTIONS6
07/06/2015321153737Open ↗
01/09/2014320824024Open ↗
04/19/2011320297157Open ↗
Showing 3 of 6 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION6
12/30/2020320157959Open ↗
12/30/2020320157959Open ↗
12/28/2020320233939Open ↗
Showing 3 of 6 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE6
01/08/2021320233939Open ↗
12/21/2020320233939Open ↗
11/12/2020320233939Open ↗
Showing 3 of 6 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
01/21/2021320233939Open ↗
02/05/2020321153737Open ↗
12/15/2017320297157Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter2
08/13/2026B01158048-P1Open ↗
08/13/2026B01158048-I1Open ↗
▸Cost, Insurance & Ownership11
▸BISCOST AFFIDAVIT10
02/05/2020321153737Open ↗
12/15/2017320297157Open ↗
11/13/2017320824024Open ↗
Showing 3 of 10 on file for this type
▸BISSTEEL AFFIDAVIT- FINAL1
11/14/2017320233939Open ↗
▸Filing & Intake Forms20
▸BISADDITIONAL INFORMATION9
12/28/2020320233939Open ↗
12/28/2020320233939Open ↗
12/23/2020320233939Open ↗
Showing 3 of 9 on file for this type
▸BISBOROUGH INTAKE FORM5
02/05/2020321153737Open ↗
12/15/2017320297157Open ↗
12/14/2017320157959Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING COVER SHEET4
07/06/2015321153737Open ↗
01/09/2014320824024Open ↗
04/19/2011320297157Open ↗
Showing 3 of 4 on file for this type
▸BISeFiling Job Application Cover Sheet2
11/03/2010320233939Open ↗
04/03/2008310111508Open ↗
▸Other Documents4
▸BISPLOT DIAGRAM2
01/08/2020320233939Open ↗
05/03/2011320233939Open ↗
▸BISDRY PIPE VALVE TEST : FP-101
07/14/2014320297157Open ↗
▸BISCPC: HUDSON YARDS FINAL CERTIFICATION1
01/08/2020320233939Open ↗